RE: BLOE hidden Gem25 Oct 2018 16:51
I'm expecting news to take a few weeks.. They did say in the RNS they were doing preparation work on the four wells first and then using the tool. Might be wrong and very happy to be so but reckon this from the RNS could mean four wells worked over first then the tool applied to each in sequence then news?
"The programme begins with preparation work on four of the eight wells. The workovers will proceed in sequence with each expected to take five to seven days to complete. A perforation technology selected to bypass any damage caused by historic heavy mud drilling will then be applied to each well. The technique replaces conventional shaped charge perforation with a micro drilling tool able to cut horizontal drain holes at multiple levels. New or refurbished pumps will then be installed to bring the wells to production, before the process is repeated early next year on the remaining four wells."