Thank you for the link, great news! Copy of the 'Highlights' from link are as below:
Highlights
• The Shenandoah South 3H (SS-3H) well was successfully drilled, cased and cemented with 5-½-
inch casing to a measured depth of 21,169 feet (6,452 metres) within Beetaloo Basin exploration
permit EP 98.
• The well was drilled in 25 days (spud to total depth (TD)) and achieved an average drilling rate of
843 feet per day, 10 days and 43% faster than the SS-2H well, the only well previously drilled to
total depth of more than 20,000 feet. This follows the successful implementation of key lessons
from wells drilled earlier in the 2024 campaign.
• The SS-3H well is the first well drilled and cased with a useable 10,000-foot (3,048-metre)
horizontal section below 8,000 feet true vertical depth (TVD) for stimulation in the Beetaloo Basin.
• Data from the SS-3H well has demonstrated strong gas shows and a continuation of the high-
quality shale and rock properties observed in the Shenandoah region, including a gentle,
undulating structure with no faulting observed along the ~10,000-foot (3,048-metre) section.
• The Liberty Energy (NYSE: LBRT) stimulation equipment and sand has been mobilized to location
ahead of a 100 – 120-stage stimulation campaign, which is planned to commence in early 1Q 2025.
• The SS-2H ST1 well is planned to be stimulated with up to 45 stages following the casing of the
horizontal section to 5,577 feet (1,700 metres). The SS-3H completion design is expected to
increase up to 75 stimulated stages over the 10,000-foot section.
• IP30 flow tests from both wells remain on track for release in 1Q 2025.