Milestones to the start of DMG FOAK31 Jan 2022 21:42
From the Peel L&P newsletter for January2022 , they state the important milestones as:
Feb/March - complete Protos grid substations, so electricity can be imported AND exported.
Spring -Planning decision EXPECTED for First plastic Park
Summer /Autumn. Start construction of DMG
In parallel with that time line is the construction by Element 2 of the hydrogen refueling station(s) needed to export the hydrogen.
I do not see any information to say where these will be but I assume the one for the DMG will be quite close to the plastic park and maybe even on one of the remaining plots. The Hynet map seems to indicate one very nearby.
However , in the initial stage of development ,the DMG could be configured to send all the syngas to produce electricity ( as originally envisaged), so the construction schedule of Element 2 should not be a problem.
So the major problem in keeping to schedule for the DMG could be the Spring planning decision for the plastic park. Others have speculated that this is already holding back the start of DMG construction and this news letter seems to confirm that.