RE: Planning approval only1 Feb 2021 19:57
I found this part of great interest for anyone that has researched
“SUP has since confirmed that it would not follow a ‘do nothing’ approach given the extent of investment in Uskmouth Power Station made to date. If the proposed development does not proceed, Uskmouth Power Station would re-energise and operate the existing power station at 393 MW on 50% coal and 50% biomass under its current permit with the aim to achieve the necessary emissions limits beyond 2027. This could be achieved without additional consent being required and utilising permitted development rights available for electricity generating stations.”
Section 2.21
Guess that is all we need to know !!!