dont expect fire works on Monday22 Apr 2022 16:18
RNS extract
"POX-2 is expected to experience 3-6 month slippage from the original schedule mostly due to logistical challenges. Early-stage projects (Veduga, Mayskoye backfill, Maminskoye) are delayed by one year. Pacific POX project has been suspended indefinitely with studies under way to potentially re-site the facility in Kazakhstan. Brownfield exploration schedule and volumes remain unchanged. Greenfield exploration budgets were reduced by 50% (mostly affecting junior JVs)."