Balcombe, Lidsey, from the interim results RNS of 30/06/254 Feb 2026 11:50
Balcombe (25% Working Interest)
... The decision of the High Court was made public on 16 April 2025 and ruled in favour of the Company. The Company is now evaluating options for the extended well test.
Lidsey (80% Working Interest)
Due to the high cost of water disposal, Lidsey has remained shut in, however, as previously stated, a planning application has been submitted to allow for transportation of produced water off-site to the Brockham oil field for voidage replacement and pressure maintenance. This application has now been approved, and we are awaiting imminent formal validation. Once received, the Company will progress to test the integrity of the well in readiness for future production, confirm the operability of the currently installed artificial lift, and establish the re-instatement production potential of the X2 well. This is low-cost operation, and if successful, it will allow for the reinstatement of the site with produced water trucked to Brockham for injection.