RE: Drill1 Oct 2019 16:54
Drilling will commence with the HH-2 vertical pilot programme and will be followed directly by the horizontal well section, HH-2z, with a planned trajectory of around 1000m wholly within the Portland reservoir. Drilling operations are expected to be completed in approximately 60 days. The HH-2z horizontal will then be tested using a bespoke downhole electric pump, or ESP.