RE: Is it just me?22 Mar 2021 16:48
I think the origional time line may have been misinterpreted by many. Apart from the spud date, we're on track. My take is that it didn't mean 1 week to drill to 1,500' AND install/test the blow out preventer. It should have been read as drill to 1,500' and then it'll take 1 week to install and test the BOP.
The announcements during the process suggest that we probably got to 1,500' around the 15th March, and the update on 15th March said the BOP work was estimated for completion on 21st March, which is about a week.
Sure enough, the update today is that the BOP work is complete as per the 15th march update, and now drilling ahead.