Daily Telegraph : Ship shortages delay construction of giant British wind farm8 Feb 2024 11:38
One of Britainβs biggest offshore wind farms is facing a year-long delay to its completion because of a chronic shortage of construction ships.
The massive Dogger Bank site has suffered from significant disruption because of bad weather, storms and a lack of vessels able to build it according to its developer, the power company SSE.
Two key ship types are in short supply β foundation vessels that pour the 1,000-tonne foundations and the installation vessels that install the turbine towers