Planned Work Programs
The Company has set out a program of exploration activity to be completed over the coming year, which
is set out in the table below. The Qualified Persons consider that this work program and expenditure is
warranted considering the potential for new discoveries in the project area and the potential to advance
the APTA deposit towards Mineral Resource estimation. It is recommended that the specific work
programs outlined in Section 26.1 should be incorporated within this overall work program.
Table 26-1 Orosur planned exploration expenditure in 2026
Exploration Activity Budget (USD$)
Diamond drilling (Pepas, APTA and Cedro programs) 2,514,400
Assays (drilling and surface samples) 570,545
Geophysical surveys (APTA, Jesuitas, Cedro, Virgencita) 250,000
Geological staff, mapping, sampling and data interpretation 722,116
Exploration logistics and field support 16,500
Total Exploration Budget 4,073,561