RE: ONGC CPO-5 block16 Mar 2019 10:23
Necessity of the Work
Development and exploration of CPO-5 block is presently at full swing with recent success of commercial hydrocarbon in Mariposa-1 and Indico-1X well. Building up the surface facilities for commercial production from these wells need construction of roads, production facilities and drilling location areas for exploratory as well as development wells. Presently 10 exploratory locations have been proposed/released in different areas of CPO-5 block in addition to land required for oil production facilities, of discovered wells.
According to Colombian legislation (law 1274 of 2009, Permanent legal entrant for hydrocarbon projects) a land negotiation processes and a constitution of servitude must be implemented in the areas selected for the construction of exploratory / surface facilities. Several activities must be executed including an independent land cadastral diagnosis, negotiation, acquisition and servitude constitution, which incorporates support from negotiation, land management and legal personnel. For this purpose, a legal firm needs to be hired for the execution of all these activities. Similar procedures have been followed in land negotiation and servitude constitution in other well locations of the block.
According to approved work program of CPO-5 block in 2019 two exploratory locations were firmed up for drilling. But with the major discovery in Indico-1X well, brings up new scenarios for drilling of at least 4 wells in 2019 in NW part of the block. The joint development of Mariposa-1 and Indico-1X and possible lay out of oil pipeline increases the LAQ work by multiple times.
In SE part of CPO-5 block, 4 exploratory locations are lined up for early drilling within extended phase II period of the block.
Therefore, all relevant documents are needed to be in placed in order to guarantee the drilling and development of the block without any delay. It is imperative to establish the land negotiation and servitude constitution before executing any construction job in the area since it is a legal requirement. By executing these procedures, will help ONGC-VL to saving time and adhere to the timelines of WP & ANH.