RE: Power Plant8 Dec 2018 16:29
There is a G R E A T difference between capable and actually producing.
Currently EDL to all intense and purposes, see RNS 24th September 2018 :-
"1 July 2018 to 17 September 20,945 tonnes of Run of Mine ("ROM") coal processed, producing 6,186 tonnes of washed coal and 9,523 tonnes of fine coal. Of the 6,186 tonnes of washed coal, 4,947 tonnes were shipped"
"Average daily shipments (calculated on a calendar day basis) of coal of 63 tonnes post H1 period, up from 51 tonnes in July 2018 and 23 tonnes for the first half"
So 20,945 tonnes of ROM coal mined,, averaging 8.82K tons per month, producing on, average 2,500 tonnes of washed coal and 3,800 tonnes of fine coal per month. Leaving approx 2.5K tons per month left over??????
For ???????