RE: Amitsoq11 Aug 2021 08:55
I don't want to sound picky but how can you call only completing 8 holes out of a planned 15 hole drilling campaign 'successful'?
"Of the five drill pads that had been prepared, only Pads A, B, C, and E were utilised. The most northerly location, Pad D, was not reached due to technical issues. All eight completed holes intersected graphite mineralisation, two from Pad A, three from Pad B and three from Pad E. A total of 935m were drilled. This was down on the planned 15 holes for up to 1,700 metres, principally due to ground conditions at Pads C and D. Although drilling was commenced from Pad C, it did not manage to attain the required depths to intersect the expected graphite horizons due to ground conditions. This will be revisited in the next drilling programme, using different techniques to counteract the ground conditions."
It's like Team GB going for 25 gold medals, only attaining 15 but still calling it a success...