RE: Lidsey looks promising, too30 Nov 2021 15:54
Angus Energy Plc
("Angus Energy", "Angus" or the "Company")
Lidsey Seismic Reinterpretation
Saltfleetby Update
The Company's seismic reinterpretation of the Lidsey field is complete and, having been subject to rigorous third party verification, will now be considered by our partners in this Licence. This is the last part of the most comprehensive review of the Lidsey structure ever carried out and includes the reprocessing of all historical seismic lines, the use of a newly acquired east-west seismic line over the field and the data from both the wells on the field and also nearby wells.
This remapping has resulted in some further changes to the shape of the structure but it now fits and is consistent with all of the available data. The Company is confident that the new field mapping explains the issues which were experienced with the Lidsey X2 well in 2017. It is now the Directors' clear belief that the structure culminates near the wellsite area and extends to the east and northeast. Prior to the drilling of Lidsey X2, it was thought that the structure extended to the west and the westerly trajectory of the Lidsey X2 well accordingly targeted an area close to the edge of the structure.
The new mapping shows there to be a significant structure not dissimilar in area to the original structure considered by the previous Competent Person's Report, which continues to support a commercially significant estimate of oil in place.
However, the interpretation does allow Angus to narrow its field of focus in target selection and explore low-cost options for remediation of the field's productivity centre around the reuse, work-over or side-tracking of the existing wells and these will be considered with our partners in the next stage of the work.
The Company's re-mapping of the structure also shows it to extend a significant distance out of the licence area in some scenarios and Angus is now opening a dialogue with the holder of that surrounding licence to consider how we might proceed together to address the future of the field.
Update on Saltfleetby Procurement and Build Schedule
We continue to work with suppliers and contractors to maintain our procurement and build schedule targeting First Gas at the Saltfleetby Gas Field at the end of February. The full schedule involves over a thousand pieces of equipment, including valves, actuators, circuits, vessels, pipes and flanges. Most of the componentry is off the shelf, but taking here the highlights of only the more significant bespoke items: with our Kaldair Flare now on site, this will be followed by:
1) Elster-Honeywell Metering and Analysis skid in early December 2020
2) Condensate and water storage tanks in early January 2021
3) Site power gas fired Caterpillar generator from mid January 2021
4) First Service Compressor and Caterpillar engine in late January/early February 2021
5) Electrical/control housing units 2nd to 3rd wee