RE: The coming days......26 Aug 2024 17:19
Jimmy, not sure it has been made clear how long the actual EWT takes. On the day you are referring to in July they said Phase III - From spud to completion of EWT is expected to take 5 weeks.
On 6th Aug they RNSed the successful deepening of the well and then the casing will be cemented in place before EWT is ran.