RE: Moving forward10 Apr 2023 12:16
Think we need to differentiate between Project 1 wells and Project 2 wells.
Next Project 1 well is likely to be KRT-45 ST
Estimated cost from CPR = $1,498,000, good chance of replicating recent results of JKT-01Z and WR-BO1 Z, say 250 bopd.
I would say this well plus gas link up, etc would probably take 4 months start to finish
Project 2 wells
Est cost £100,000, - likely flow rate 50 bopd
I think these low cost wells are the ones that can be turned around in 60 days, start to finish.
So how about 1 no Project 1 well and 3 no project 2 wells this year??
Roll on tomorrow morning (or Wednesday)