RE: New media24 Jul 2025 16:00
@carters: OK, following your suggestion, the RNS are patchy to say the least. Let's look at just the JV period (drilling related only).
14. March 2022: 3,000m "promised" commencing April.
31. March 2022: €4.5M for "WORK COMMITMENTS" of same 3,000m
18. Jan. 2023: three MORE (so others drilled?) holes of 1,053m extend Clontibret.
02. Feb. 2023: 268.5m drilled at Corkaskea (Clontibret).
08. Feb. 2023: 2,000m drilling planned for Clay Lake.
06. March 2024: 212.7m drilled at Clay Lake.
13. July 2023: 98m in SIX (so ~15m) holes at Creenkill.
04. Sept. 2023: 6,000m allegedly completed, but only 1,632m reported on.
13. Sept. 2024: 500m in 2 holes drilled at Slieve Glah.
22. Nov. 2023: results of 3 of 4 completed holes, 814m of 2,000m in 8 holes planned at Clay Lake.
20. Dec. 2023: 518m in 2 more holes at Clay Lake.
25. Jan. 2024: 3 holes 666m at Clontibret, 2 holes 545m at Slieve Glah, 2 holes 583m at Glenish.
14. Feb. 2024: 2 holes for 494m at Clay Lake. 2,303m completed.
29. April 2024: JV terminated, €5.56M spent.
So by my accounting, they claimed 6,000m "completed" to 4/9/23, then announced a further 4,120m to 14/2/24 for 10,120m total.
Clontibret: results announced on 1,987m.
Clay Lake: 2,303m drilled, results announced on 2,039m.
Others: results announced on 1,726m.
Unreported: 4,104m (if in fact ever drilled?)
Cost per reported metre: €924.