RE: What would be great news to me would be that27 Feb 2025 18:04
Main Dar pipeline 533 km
Construction began in June 2013, with commissioning in October 2015.
29 months
533/29 = 18.38km p mnth
Madimba pipeline 35km
Should take less than 2 months comparatively speaking all being well