So from continental gold costs for Buriticá
Initial capital costs in the Feasibility Study dated February 24, 2016 were $389.2 million, including contingency but excluding working capital. As at August 8, 2018, the Company revised the total project costs estimate (including scope changes of $74 million) to be in the range of $475-$515 million (including contingency but excluding working capital)