RE: cornishknocker24 Jan 2021 19:32
You can reduce trucking costs by on site crushing and DMS or ore sorting, which would reduce the trucked ore by approximately 30-40%, typically for a loss of 3-5% of metal.
I don't know how old you are, but I imagine you mean the river Gannel down Newquay? But there have been a lot of road improvements down here.
Tge county has one main Artery (The A30, which is now nearly all Dual Carriageway, with tge A38 feeding from Plymouth and South Devon and the A39 from North Devon.
The A30 links to the A38 via the A388 which runs right through Kelly Bray and Callington from Launceston to Saltash, other than tge section from Kelly Bray to Callington, its a pretty good road.
On the scoping study the plan is 600,000 TPA, which equates to 60 Artic tippers a day (6 an hour over 10 hours, 7 days a week). That could be reduced to 4 trucks an hour with Ore Sorting/DMS.