Talvivaara says the threat of having evaded the payment of the fine gypsum pond tyhjentämisasiassa . The company reports in his blog that it has got into the pool warehousing in the amount of water to calculate the Kainuu ELY Centre to the level required .
Northern Finland Regional State Administrative Agency ordered the company last May to clear the gypsum pools of water, because it was found in pools of their risk of leakage . Reservoirs under went a wealth of seepage waters in November 2012 and April 2013 spill pool . They justify the discharge order by the fact that reservoirs foundations, the condition of reliable information .
The company was initially supposed to get the empty pools as early as last fall. Drain the timetable was extended several times , as well as the Vaasa Administrative Court of the Northern Finland Regional State Administrative Agency Decisions. Of which , despite the continuation of emptying the pool made ​​for so long that the Kainuu ELY Centre urged the company in February to clear the waters by April. When the discharge is successful, ELY ordered the pools emptied of EUR 100 000 penalty of a fine .
Kainuu ELY demanded that the pool can be up to 500 000 cubic meters of water in the middle of May .
The company 's announcement on Wednesday that the amount of water the pool is a little more than 400 000 cubic meters. According to the company , it is close to the normal to the required amount of water . Remaining excess water must be removed from the end of August .
The drop out of the water will decrease
According to the company Talvivaara area ulosjohdettavien of purified water flow is reduced when approaching the summer because of the number of spring melt waters begin to decline. Talvivaara out DETERMINATION water is linked to the nearby Rocky River flow .
The company has received added the southern direction varoaltaana work Korte pond behind the dam, the free volume . According to the company Korte pond dam has a free volume of about 1.5 million cubic meters. The water level has fallen to last December's rainfall situation after up to two meters.
The company insists that even if the water is in the range of stock lots and will be up , the waters are safe places . Also caused problems in the past biokasaliuotuskierron varotilavuudet are at a good level , says the company blog.
Centre for Economic Development , stating the number of the day
Kainuu ELY Centre Head of Sari Myllyoja finds that the threat of penalties or määräämättömyys explicitly state inspection.
- Fixed date , ie May 15, Centre for Economic Development to inspect the situation in the pool. If the relevant conditions are met , a fine thing is dismissed. The committee did not make any decision at the time . If the situation is such that the conditions are not met , then the case becomes a separate penalty payment of charges , says Myllyoja
http://yle.fi/uutiset/tal