RE: MMS waiting for the drill results23 Dec 2022 09:53
Listened to some of the interview again to clarify the H1 for 2,000oz production.
Robbie said
'We haven't stopped constructing, kept doing construction works on site.
There's some big ticket items we needed the funding locked in to buy. The new crushing plant, the new elution plant, etc
The time frame including commissioning is by the end of H1
Construction will finish March/April
Then we've got 2 months for commissioning, we'll be producing gold during commissioning'