RE: Interviews and more interviews2 May 2024 12:43
Perhaps it will change this time, but it does sound like the same interview again and again for the past 18 months.
You really have to question why RF keeps saying things like "we could ramp up our production from 10'000 to 15'000 (tons) a month just by adding more equipment".
16th March 2023 he said - "By end April, no by end May probably, we’ll be at 10,000 tonnes per month”.
14th June 2023 he said - "Produce minimum of 6,000 tonnes per month, ramp up to 10,000 tonnes per month over the next few months, then potentially up to 15,000 tonnes per month”.
He talks about "ramping up", but production has been what, 6,000 tonnes in total over 18 months ? If that is what is actually ready to go - all we really know is that 2 x 40 tonne trucks have gone to OM Metals before the road couldn't handle any more.
They have never got even any order of magnitude near to 10,000 tonnes per month, or 6,000 tonnes. They doesn't seem to be any mine plan, any equipment ready, or any real infrastructure at Molulu to cope with that sort of ore volume.
It's just silly even to mention volumes like that at the moment.