Pinarova-1 campaign21 Mar 2023 12:25
For reference Basur-3 was spud at 5pm on 26th June 2021.
"UK Oil & Gas PLC (London AIM: UKOG) is pleased to announce that following formal acceptance of the Oceanmec Karahan ZJ40DZ rig at 1700 hrs BST+2, Saturday 26th June, air drilling of Basur-3's initial 17½ inch diameter hole section commenced at 1818 hrs local time. Upon completion of the 17½ inch hole section, 13? inch casing is expected to be set and it is anticipated that the well will switch to a water-based mud system for the 12¼ inch section and the remainder of the well."
Then on 1st July 2021 at 7.00am, 4 days later, we were told:
"UK Oil & Gas PLC (London AIM: UKOG) is pleased to announce that following completion of the Basur-3 appraisal well's initial 17½ inch diameter hole section, 13? inch casing has now been set, successfully cemented down to a drilled depth of 367 m (1204 ft) below surface and pressure tested. Following setting of blow out preventers, drilling will then resume in 12¼ inch hole section."
So it took about 4 days of drilling to reach 367 metres including all the casing with the blow-out preventer still to be set. So allow another 1 or 2 days to reach TD.