RE: Plant8 Apr 2025 15:31
If you start with 0.6% Ore (as Asiamet have), and your plant is located hundreds of miles in the middle of nowhere with no electricity in a jungle, obiously you need a more expensive plant...
Cost of new power plant and water plant, what, 20% of Capex?
To get 13ktpa of cathode at 75% recovery rate from 0.6% copper, you need to process 2.88m tonnes of Ore
Marula have power and water onsite. And they are aiming for 3% copper, and 10ktpa copper cathode so they only need to process 444k tonnes of Ore
So near infostructure, no power, no water, and less than 20% of the Ore required to produce 10ktpa
And all near surface with high copper content outcrops up to 20% copper content
I think we can safely say Marula's cathode plant can come in at 10-20% the cost of Asiamets