RE: Next week24 Apr 2024 15:18
George Roach, CEO, commented, "The final step in commissioning Zulu looks to be the changes to be made to the material flow through the floatation plant as described in our announcement of 10 April 2024. These changes expect to see the floatation plant able to accept the design tonnage and to remove the restrictions on potential spodumene concentrate production.
Shouldn't we have news on this first then a delivery one
The required piping and valves are expected to load for site by Tuesday 16 April, and the expectation is that fitment could be complete as early as the week commencing 22 April 2024. A further update will be made in due course".
We all know Georges due course remarks could be a lot longer