RE: RNS: reduced decommissioning liability19 Aug 2020 11:18
Sageman - Angus accepted the £2.5million to use to get to First Gas...not for the decommissioning. And the CPR says it will cost Angus £2.79 million ....so Angus have to find another £279,000 from somewhere.
And I clearly stated I was referring to Angus pricing the decommissioning at £1.75 million....which they have now corrected themselves as of yesterday.
The December 2019 timeline was unachievable and most surprising that they would box themselves in which unrealistic schedules. It obviously helps to have done this before hence why we see the long delay. I don't see the oil industry shutting down? Business as usual with emails, phones calls and endless planning permits. They were due to produce First Gas in May 2020, so what had Angus achieved by February 2020? Pipeline design completed, trench dug, pipe laid, commissioned, faciites being completed? None of that took place, so Corona isn't to blame