SDX Drilling7 May 2021 20:16
I've been looking for more data on SDX drills. Do SDX generally announce when they have completed a drill and moved to the next one. As they are using rig 101 I have a feeling they will have done the first one by this weekend (if they haven't already finished it). Maybe an announcement on Monday??
Also can someone just check that I am not going mad. People keep saying 3 drills for SDX but I work it out to be 4 actual drills from 3 locations. 1st 1160m, 2nd 1720m, 3rd 1600m and 4th 1790m.
I've reran my calculations with a 150m per day drill rate and a 2 day rig move/ setup and got it down to 48 days to complete their schedule. At 100m per day it is 69 days which would put us into July and outside of schedule. With the rig data MickTrick posted 150m looks very possible for rig 101. Allowing for a few extra days the last week of June is looking good for PRD to begin its Morocco adventure :)