RR SMR on Wikipedia30 Mar 2025 23:39
RR began design work on the SMR c. 2015 with a team of about 150 people, with decisions made near the start of the project to use light water[a] as both coolant and moderator.[3]
In 2016, it was reported that the UK Government was assessing Welsh SMR sites - including the former Trawsfynydd nuclear power station - and on the site of former nuclear or coal-fired power stations in Northern England. Existing nuclear sites including Bradwell, Hartlepool, Heysham, Oldbury, Sizewell, Sellafield and Wylfa were stated to be possibilities.[4]
In 2017, the consortium headed by RR needed to seek UK government finance to support further development.[3][5][6] In December 2017 The UK government provided funding of up to £56 million over three years to support SMR research and development.[7]
In 2018, the UK SMR industry sought billions of pounds of government support to finance their putative First of a Kind projects. The Expert Finance Working Group on Small Reactors produced a report stating that there was "a current market failure in supporting nuclear projects generally" and identifying options for government to support SMR development in the UK.[8][9]
In 2019, the government committed a further £18 million to the development from its Industrial Strategy Challenge Fund, to begin designing the modular system.[10][11] In November 2021, the UK government provided funding of £210 million to further develop the design, partly matched by £195 million of investment by Rolls-Royce Group, BNF Resources UK Limited and Exelon Generation Limited.[12][13] At that point they expected the first unit would be completed in the early 2030s.[14]
In 2022, the CEO stated that the Rolls-Royce SMR investment business case was based on selling many hundreds of SMRs by 2050.[15]
On 1 April 2022, the regulatory Generic Design Assessment (GDA) of the Rolls-Royce SMR started.[16] The assessment will begin once the timescales and resources have been agreed.[17] The assessment is likely to take about 4 years, and be complete by 2026.[18][15]
In October 2022, Rolls-Royce announced that it was exploring eight possible sites in the UK to build the first of three expected factories for parts of the SMR.[19] In November 2022, four sites were identified suitable for multiple SMR units: Trawsfynydd, Sellafield, near Wylfa, and near Oldbury.[20]
In March 2023, Rolls-Royce stated that the current programme funding of £500 million will run out by the end of 2024, and requested negotiations with the UK government to find fresh investment. Hiring of new staff was stopped. About 600 staff work on the programme in Derby, Warrington and Manchester.[20][21] At the end of March 2023, the CEO and finance officer of the SMR unit were replaced by the newly appointed CEO of Rolls-Royce.[22]
In July 2023, Energy Secretary Grant Shapps said he was launching an international competition to select up to four different SMR technologies "to go through to the final design stage", supported by up t