RE: Visiting host removed posts14 Jun 2023 08:53
VH are you saying this paragraph from the March 14th RNS is a complete total LIE
The 1.1 MWe plant, located in Gallina, near Castiglione d'Orcia, Tuscany, Italy (the "Plant") had already commissioned gasification and biochar production capabilities in January 2023. On 8 March 2023, following commissioning of the Jenbacher 612 engine, the Plant exported its first electricity to the national power grid. To finalise calibration and performance testing of the engine and to support Handover Protocols, a representative of INNIO Jenbacher (Italia) will be on site from 15 March 2023. Following completion of this work on the engine and before the end of March, the Company expects to fully transfer plant operations to the Italia MDC staff
Please advise