15 Jan 2009 07:00

RNS Number : 6660L
ZincOx Resources PLC
15 January 2009
ย 

๏ปฟ

ZincOx Resources Plc

("ZincOx" or "the Company")

ยฃ10 millionย Shaimerden Paymentย expected by the end of January

ZincOx, whichย specialises in the recovery of zinc and zinc products from unconventional sources, today provides an update on progress with its variousย activities andย is pleased to announceย that it is dueย to receiveย US$15,703,785 (about ยฃ10 million)ย before the end of January 2009ย as part ofย the deferredย paymentsย from the sale of its Shaimerden zinc deposit.

Shaimerdenย Mine

In 2003 the Company sold its zinc depositย at Shaimerden inย Kazakhstan. The terms of this disposal required additional deferred payments to ZincOx on the first 200,000 tons of eligible zinc (expected to be spread over the period 2008 to 2011), related to zinc prices pertaining at the time.

A total of 523,759 tonnes of ore containing 118,118 tonnes of eligible zinc were mined from Shaimerden in 2008. In order to ensure that the payments were spread over a number of years, the amount of eligible zinc mined is limited in any one year to a maximum of 60,000 tonnes. During the period of eligible zinc miningย in 2008, the zinc price averaged US$1,902 per tonne,ย resulting in the Company being due a deferred payment amounting to US$15,703,785 (about ยฃ10 million).

Jabali Deposit

Development at Jabali is proceedingย within budget and all the major pieces of process equipment have been ordered.ย The access road to siteย is now open,ย accommodation for the miningย staffย and for the construction team isย in placeย andย terracing of the main process plant areaย is underway. Recruitment of key mining staffย is ongoing andย all the seniorย positionsย have now beenย filled. The mining equipment is on site andย trainingย has started. The first production is scheduled for the first quarter of 2010.

Recycling

Last year zinc started atย a price ofย US$2,240 per tonne and ended the year at half the value:ย US$1,120ย perย tonne.ย Some other metals fared even worse. The fall in price was particularly marked in the latter half of the year. The considerable uncertainty inย the international economic outlookย hasย led the Board toย reconsider theย timing of theย development programme for the Ohio Recycling Project. Furthermoreย the directorsย need to be absolutely confident thatย the Companyย hasย sufficient funds to developย fullyย the operationย before committingย toย purchaseย large capital items.

Unfortunately, the fall in the zinc price has resulted in a drop in the value of receiptsย the Companyย can expect from Shaimerden, especially next yearย (2010).ย As these were an essential component ofย theย fullย development financingย for theย Ohioย plant,ย the Board isย investigatingย alternative meansย of making up this shortfall.

Over the past few months discussions with banksย with a view toย providingย the Company withย traditional project finance have progressed.ย Whileย theย termsย under discussionย are more onerous than would have been the case a year ago,ย there are signs thatย some banks are making funds available forย qualityย projects.

In parallel withย the Board'sย discussionsย with the banks,ย the directors areย looking at a number of other options includingย talkingย toย potential joint ventureย partnersย forย the Ohio Recycling Project. Management would aim to raiseย sufficientย capital fromย aย minority partnerย in the projectย that,ย when takenย together withย the Company'sย existing cash resources and the debt facility arranged last year,ย would be sufficient to develop the project.ย Even at today's metal prices the project would still enjoy a significant operating margin.

Ourย engineers are using the delay in development caused by the economic uncertainty to obtain the best possible price for engineering services,ย equipment supply and fabrication. This will put us in an even stronger position once the funding issues are resolved.ย Some low cost long lead time items are also being ordered in order that the delay caused by financing is minimised.

Outlook

Following the receipt of the Shaimerden payment, expected before the end of this month,ย ZincOxย will haveย almostย US$92.5ย million in cash.ย The Company is therefore in a remarkably strong position compared to many of itsย peers in the juniorย miningย sector and is well equipped to ride out the current very challenging economic environment.

For more information please contact:

Andrew Woollett,ย ZincOx Resources plc

ย Tel:ย +44 (0) 1276 450100

John Harrisonย (Nominated Adviser)

James Blackย (Corporate Broker)

Numis Securities

Tel: +44 (0) 20 7260 1000

Charlie Geller,ย Conduit PR

Tel (Direct)ย : +44 (0) 20 7429 6604

This information is provided by RNS
The company news service from the London Stock Exchange
ย 
END
ย 
ย 
MSCBIGDBBGBGGCS
Date   Source Headline
26th Feb 20087:01 amRNSDirectorate Change
31st Jan 20085:53 pmRNSHolding(s) in Company
31st Jan 20085:46 pmRNSHolding(s) in Company
31st Jan 20085:40 pmRNSTotal Voting Rights
21st Jan 20087:01 amRNSCapital Raising
14th Jan 20087:01 amRNSJabali Mine development
3rd Oct 20079:25 amRNSTotal Voting Rights
27th Sep 20077:10 amRNSInterim Results
21st Sep 20073:00 pmRNSIssue of Equity
29th Aug 200712:49 pmRNSHolding(s) in Company
20th Aug 20077:00 amRNSAIM Notice 26
16th Aug 20074:28 pmRNSHolding(s) in Company
9th Aug 20071:55 pmRNSHolding(s) in Company
6th Aug 20075:34 pmRNSAGM Statement
2nd Aug 20077:00 amRNSJabali Mining Licence Granted
18th Jul 20073:28 pmRNSTrading on PLUS
9th Jul 20072:48 pmRNSIssue of Equity
29th May 200710:54 amRNSFinal Results
15th May 20077:03 amRNSIssue of Equity
30th Mar 200711:14 amRNSTotal Voting Rights
26th Mar 200711:43 amRNSHolding(s) in Company
15th Mar 20077:00 amRNSIssue of Equity
5th Mar 200712:15 pmRNSTotal Voting Rights
2nd Mar 20076:17 pmRNSHolding(s) in Company
27th Feb 20071:23 pmRNSHolding(s) in Company
22nd Feb 20077:00 amRNSIssue of Equity
20th Feb 20077:02 amRNSNew US Recycling Project
19th Feb 200711:50 amRNSIssue of Equity
14th Feb 20077:01 amRNSHolding(s) in Company
5th Feb 20073:00 pmRNSHolding(s) in Company
25th Jan 20077:00 amRNSShaimerden money received
16th Jan 20074:19 pmRNSGrant of Options
29th Dec 20069:16 amRNSHolding(s) in Company
28th Dec 20067:00 amRNSTotal Voting Rights
20th Dec 200611:32 amRNSIssue of Equity
12th Dec 20067:02 amRNSTeck Cominco Placing
27th Nov 20067:00 amRNSJabali Project Update
26th Sep 20067:03 amRNSInterim Results
10th Aug 20064:50 pmRNSHolding(s) in Company
10th Aug 20067:01 amRNSDirectorate Change
4th Aug 200612:01 pmRNSHolding(s) in Company
30th Jun 20069:35 amRNSHolding(s) in Company
27th Jun 20064:42 pmRNSIssue of Equity
26th Jun 200610:50 amRNSAcquisition of Big River
26th Jun 20067:02 amRNSIssue of Equity
19th Jun 20062:11 pmRNSPreliminary Results
19th Jun 200611:32 amRNSDirectorate Change
7th Jun 20066:28 pmRNSChange of Address
5th Jun 20067:00 amRNSBig River Zinc
2nd Jun 200611:57 amRNSProject Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.