Hemerdon Tungsten Project Construction Update

28 May 2014 07:08

RNS Number : 1959I
Wolf Minerals Limited
28 May 2014
Β 

28 May 2014

Β 

Wolf Minerals Limited

Β 

Hemerdon Tungsten Project

Construction Update

Β 

Specialty metals exploration and development company, Wolf Minerals Limited (ASX: WLF, AIM: WLFE) ("Wolf" or "the Company") is pleased to provide an update on construction at its world class Hemerdon tungsten and tin project in Devon, in southwest England, following the successful completion of its Β£99.2m fundraise last week.

Β 

The project's Engineering-Procurement-Construction (EPC) contractor, GR Engineering Services Limited (ASX: GNG) (GRES), was formally authorised to commence the construction phase of the project in February, and a Ground Breaking ceremony was held at the project in March to mark the commencement of the project.

Β 

Wolf now advises that construction is well underway and is progressing on schedule. GRES is currently scheduled to finish the plant and hand it over to Wolf in the third quarter of 2015.

Β 

The Company's project management team, led by Project Manager Rupert McCracken and Operations Manager Jeff Harrison, is in place and there are currently more than 100 people working at the site.

Β 

The initial phase of construction activity at the project has been site preparation, which is now almost complete. Earthworks at the processing plant site are almost complete, and the site is being cleared and old plant infrastructure is being demolished. It is anticipated that that the site will be totally cleared by early June 2014. The first concrete pour for the project's processing plant took place in late May.

Β 

Wolf has also commenced an extensive tree-planting program at the Hemerdon site with over 40,000 trees planted.

Β 

The Company is currently working to complete construction of the mine access road, and the mine haul road, which will facilitate haulage of waste from the mine's open pit to the project's waste facility.

Β 

Construction of the project's mine waste facility is expected to commence in the near future. This will be one of the key components of the project and is one of the major undertakings in the project's construction phase.

Β 

Commenting on the progress of construction, Wolf Managing Director, Russell Clark said:

Β 

"We are delighted with the level of activity and progress achieved to date at the Hemerdon project site. The Company's project management team and our EPC contractor, GR Engineering, are working extremely well together and construction remains on schedule for the project to be completed on time and on budget in the third quarter of 2015. The next key steps will be further concrete pours at the processing plant and the commencement of the mine waste facility, and we look forward to reporting further updates on construction progress in due course."

Β 

A selection of images highlighting construction activity at the Hemerdon Project are available from the Company's website.

Β 

Β 

ENDS

Β 

Β 

Russell Clark

Managing Director

Β 

For further details, please contact:

Wolf Minerals Limited

Russell Clark

+61 8 6364 3776

managingdirector@wolfminerals.com.au

Investec

Chris Sim/Jeremy Wrathall/David Anderson

+44 (0) 20 7597 5970

Β 

Newgate Threadneedle

Graham Herring

+44 (0)Β 20 7653 9850

Β 

Promotion and Marketing

Β 

The Company has a corporate video, which provides an update on the Hemerdon Project and it is available to view on the home page of the Wolf company website, at www.wolfminerals.com.au.

Β 

The Company's latest Investor Presentation is available, via the following link;

http://www.wolfminerals.com.au/asx-announcements/presentations

Β 

Β 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
MSCQKFDPPBKKCPB
Date   Source Headline
8th May 20127:00 amRNSExercise of Options
2nd May 20127:00 amRNSExercise of Options
2nd May 20127:00 amRNSAppendix 3B
24th Apr 20127:00 amRNSAppendix 3B
24th Apr 20127:00 amRNSExercise of Options
24th Apr 20127:00 amRNSAppendix 5B
24th Apr 20127:00 amRNSQuarterly Activities Report
23rd Apr 20127:00 amRNSPublication of presentation
20th Apr 20128:35 amRNSOfftake agreements
11th Apr 20129:04 amRNSAppendix 3B
11th Apr 20129:00 amRNSAppendix 3B
11th Apr 20128:56 amRNSIssue of Shares and Options
27th Mar 20128:21 amRNSResponse to media speculation
12th Mar 20129:44 amRNSChange of Name of Nominated Adviser
9th Mar 20127:00 amRNSHalf Yearly Report
5th Mar 20127:00 amRNSCredit Approval for £55m Project Finance
16th Feb 20127:00 amRNSExercise of Options
16th Feb 20127:00 amRNSAppendix 3B
15th Feb 20127:00 amRNSInvestor Update
14th Feb 20127:00 amRNSExercise of Options
14th Feb 20127:00 amRNSAppendix 3B
30th Jan 20127:00 amRNSAppendix 5B
30th Jan 20127:00 amRNSQuarterly Activities Report
19th Jan 201211:01 amRNSAppendix 3B
19th Jan 20129:48 amRNSExercise of Options
13th Jan 20127:00 amRNSGovernment support for Hemerdon Tungsten Project
12th Jan 20127:01 amRNSAppendix 3B
12th Jan 20127:00 amRNSIssue of Shares
19th Dec 20117:00 amRNS£55 million project finance for Hemerdon project
15th Dec 20117:00 amRNSWolf Minerals to build early infrastructure
5th Dec 201112:44 pmRNSIssue of Options

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.