Operations Update

5 Feb 2020 07:00

RNS Number : 9714B
Victoria Oil & Gas PLC
05 February 2020
 

 

 

5 February 2020

Victoria Oil & Gas Plc

("VOG" or the "Company")

 

Operations Update

 

Victoria Oil & Gas Plc, whose wholly owned subsidiary, Gaz du Cameroun S.A. ("GDC"), the onshore gas producer and distributor with operations located in the port city of Douala, Cameroon, is pleased to provide shareholders an operations update of the Company.

 

Highlights

 

·; GDC has entered into a non-binding Letter of Intent ("LOI") with New Age Cameroon Offshore Petroleum S.A. ("New Age" and together with GDC, the "Parties") for the supply of a minimum of 25mmscfd of gas from the Etinde natural gas and condensate field ("Etinde");

·; To enable access to Etinde natural gas, additional downstream pipeline infrastructure proposed to be developed by GDC to connect this gas supply and be fully debt funded;

·; Non-binding term sheet for long term gas supply to satisfy Aksa Energy Uretim A.S. ("Aksa") off-take agreement and other future potential grid power contracts;

·; Altaaqa has suspended operations at ENEO's Logbaba site due to non-payment. GDC continues to invoice ENEO based on take-or-pay provisions; and

·; Remediation work to complete La-108 will recommence in early 2020.

 

Roger Kennedy, Chairman said:

"We have spent the past eight months addressing legacy issues, cutting costs and exploring long-term strategies for the Company to move away from its historical dilutive, capital intensive programmes to a strategy that we believe should deliver sustained profitability and generate shareholder value in the long term. Demand for gas powered energy remains strong in Douala, with the planned development by Aksa of a new 150 MW gas-fired power plant being highly positive for the people and business community of Douala and for our Company. The opportunity to secure the long-term supply of gas from the Etinde license will be a major step for our Company. Based on our review and work to date, we continue to refine our long-term business plan and vision. We look forward to making further announcements reflecting these changes throughout 2020."

 

 

Signed LOI for Long Term Gas Supply with New Age

 

The Company is pleased to report that it has entered into a non-binding LOI with New Age for the supply of gas from Etinde, which contains natural gas and condensate discoveries.

 

Under the LOI, the Parties will seek to negotiate and enter into a gas supply agreement ("GSA"). The LOI envisages that under the GSA, New Age will bring its gas from the offshore Etinde field to onshore Cameroon for processing. GDC would then purchase processed natural gas from the onshore New Age facilities and transport the gas to Douala to supplement the current gas sales. 

The LOI envisages that the GSA would be for a period of 20 years during which New Age would supply a minimum of 25mmscfd of gas to GDC for the first three years, followed by a minimum of 30mmscfd, with the potential to increase in the future as demand in the market increases. This would amount to a total gas supply in excess of 200bcf of gas over the contract period. GDC would then seek to distribute this gas to new independent power producers looking to produce power for the energy deficient Douala market as well as to existing and future thermal and retail power customers.

 

When combined with potential offtakes to be secured with long term industrial thermal customers plus grid power contracts, including with Aksa (subject to definitive agreements being entered into), GDC should be well positioned to grow into being the natural gas utility company leading the downstream gas distribution sector in Cameroon. The proposed GSA with Aksa alone would consume in excess of 20mmscfd for the initial 150MW power plant, with potential expansion.

 

In order to access the gas production from Etinde, GDC will need to install a 60km (approx.) high pressure gas pipeline from Limbe to Bekoko where it would connect with the existing low-pressure pipeline network which operates throughout Douala. The pipeline would be designed to allow for future expansion in Douala and the South-West region.

 

The installation of a major gas pipeline network from Limbe to Bekoko will provide numerous additional opportunities, which would have otherwise been deemed uneconomic, to supply gas into smaller towns along the route into Douala, such regions/towns as Ombe, Mutengene, Tiko and Buea, and provide much needed power using smaller gas-fired power plants.

 

GDC has commenced negotiations with multilateral and export credit agencies to fully debt finance this new pipeline project. The Parties are currently negotiating a fully termed GSA and subject to signing, anticipate a Final Investment Decision by the Parties on the project during H2 2020.

 

Further announcements will be made in due course.

 

 

LOGBABA UPDATE

 

Quarterly Production

Quarterly gross and net gas and condensate sales at Logbaba are as follows (amounts in bold are gas and condensate sales attributable to GDC (57%)):

 

 

Q4 2019

Q3 2019

Q2 2019

Q1 2019

Q4 2018

Gas sales (mmscf)

 

 

 

 

 

Thermal

230

405

211

369

206

361

211

370

200

352

Industrial power

14

24

13

24

14

25

14

25

15

27

Grid power

0

0

205

360

283

496

290

508

15

25

Total (mmscf)

244

429

429

753

503

882

515

903

230

404

Average gas production (mmscfd)

4.48

8.01

9.66

10.10

4.45

Condensate sold (bbl.)

2,294

4,025

3,071

5,388

3,451

6,054

3,825

6,710

2,701

4,738

 

 

 

Grid Power - ENEO

On 14 September 2019, Altaaqa, the generator supplier to ENEO, suspended operations at ENEO's Logbaba site due to non-payment of invoices by ENEO. Consequently, GDC has not provided gas to ENEO since that date, but has continued to invoice ENEO based on take-or-pay provisions agreed to in the binding term sheet and therefore projected revenue from gas sales is not expected to be affected in 2019.

 

The gross amount outstanding from ENEO as at 31 December 2019 was $10.5 million (net $6.0 million). Despite being outside of agreed payment terms, the Company expects to receive payment of these amounts in due course and is actively working with the Government of Cameroon and ENEO to recover these payables.

 

Furthermore, whilst GDC continues to operate under a legally binding term sheet with ENEO, the completion of the fully termed agreement and payment guarantee, the terms of which have been finalised, remains subject to signature.

 

La-108 Remediation

The wireline tool string and 130m of wire has been recovered. A clean out assembly was run to recover the remaining 50m of wire and clean the hole, but this became stuck in the tubing at approximately 900m. Operations were suspended at the end of October 2019 to mobilise additional equipment to complete the remediation programme. Prior to suspending operations, GDC used the available equipment on site to successfully perform additional perforations in well La-107. The additional equipment is on route to Douala. The remediation work to complete La-108 will recommence upon its arrival.

 

CORPORATE UPDATE

 

Cameroon Holdings Limited ("CHL") Royalty Agreement

GDC has ceased to make payments to CHL under the Royalty Agreement. As a result, in June 2019, CHL commenced proceedings against both GDC and the Company with regard to payments CHL believes it is entitled to under the Royalty Agreement including potential damages. The Company has vigorously defended such claim and litigation is ongoing. There is no definitive timetable for such litigation proceedings.

 

This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014.

 

For further information, please visit www.victoriaoilandgas.com or contact: 

 

Victoria Oil & Gas Plc

Ahmet Dik Tel: +44 (0) 20 7921 8820

Kate Baldwin

 

Strand Hanson Limited (Nominated and Financial Adviser)

Rory Murphy / James Dance / Jack Botros Tel: +44 (0) 20 7409 3494

 

Shore Capital Stockbrokers Limited (Broker)

Mark Percy / Toby Gibbs (corporate finance) Tel: +44 (0) 20 7408 4090

Jerry Keen (corporate broking)

 

Camarco (Financial PR)

Billy Clegg Tel: +44 (0) 20 3757 4983

Nick Hennis Tel: +44 (0) 20 3781 8330

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDVZLFBBLLBBBF
Date   Source Headline
6th Nov 201210:45 amRNSAdditional Listing, Directors' Dealing
25th Oct 20126:00 pmRNSFinal Results - Replacement
25th Oct 201211:05 amRNSFinal Results
19th Oct 20124:40 pmRNSSecond Price Monitoring Extn
19th Oct 20124:35 pmRNSPrice Monitoring Extension
1st Oct 20127:00 amRNSIndependent CPR on Logbaba Field
29th Aug 20121:30 pmRNSDirectorate Change
16th Aug 20127:00 amRNSLetter to Shareholders
9th Jul 20127:00 amRNSContinuous Production Operations at Logbaba
1st Jun 20127:00 amRNSCompletion of Pipeline, Equity Placing
9th May 201211:32 amRNSAppointment of Director of Projects
3rd Apr 20127:00 amRNSDirector Dealing and Additional Listing
29th Feb 20127:00 amRNSInterim Financial Report
24th Jan 20124:30 pmRNSLatest Corporate Presentation Available
20th Dec 20117:00 amRNSLogbaba Operational Update
30th Nov 20113:14 pmRNSResult of AGM
29th Nov 20117:00 amRNSLogbaba Operational Update
11th Nov 20117:00 amRNSDirector Dealing and Additional Listing
4th Nov 20117:00 amRNSCompletion of Acquisition of Royalty Interest
28th Oct 20117:00 amRNSAppointment of Joint Broker
28th Oct 20117:00 amRNSFinal Results
27th Sep 20117:00 amRNSEquity Placing of £9.5 million
9th Sep 20117:00 amRNSLetter to Shareholders
16th Aug 20117:00 amRNSIssue of Equity & Directors Dealings
11th Aug 20117:00 amRNSAcquisition of Royalty Interest in Logbaba
5th Aug 20114:40 pmRNSSecond Price Monitoring Extn
5th Aug 20114:35 pmRNSPrice Monitoring Extension
29th Jul 20117:00 amRNSAdditional Listing re SEDA drawdown
19th Jul 20117:00 amRNSUpdate re Logbaba Field
7th Jul 20117:00 amRNSWest Medvezhye Operational Update
25th May 20117:00 amRNSApplication for Listing of shares and Directors' s
20th May 20111:09 pmRNSDirector/PDMR Shareholding
18th May 20117:00 amRNSLetter to Shareholders
6th May 20119:41 amRNSExploitation Licence Awarded
28th Feb 20117:00 amRNSHalf Yearly Report
30th Nov 20101:55 pmRNSResult of AGM
16th Nov 20107:00 amRNSFundraising of £10.8m
8th Nov 20107:00 amRNSFinal Results
27th Oct 20104:35 pmRNSPrice Monitoring Extension
20th Oct 20107:00 amRNSReserves Update
1st Sep 201010:35 amRNSEquity placing of ?9.2m successfully completed
18th Aug 20107:00 amRNSOperations Update
22nd Jul 20107:00 amRNSLetter to Shareholders
7th Jul 20104:40 pmRNSSecond Price Monitoring Extn
7th Jul 20104:35 pmRNSPrice Monitoring Extension
23rd Jun 20104:40 pmRNSSecond Price Monitoring Extn
23rd Jun 20104:35 pmRNSPrice Monitoring Extension
12th May 20105:30 pmRNSResult of General Meeting
7th May 20104:40 pmRNSSecond Price Monitoring Extn
7th May 20104:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.