Logbaba Operational Update

29 Nov 2011 07:00

RNS Number : 9263S
Victoria Oil & Gas PLC
29 November 2011
 



29 November 2011

 

Victoria Oil & Gas Plc

('VOG' or 'the Company')

Logbaba Project Operational Update

Highlights:

·; The Company remains on schedule for first gas sales by the end of the year

·; Production Facilities mechanically complete and pre-commissioning substantially completed

·; Completion of pipeline installation to first customer hub on the Magzi Industrial Estate

·; Pre-commissioning underway on first 5km of pipeline

 

Victoria Oil & Gas Plc, the AIM quoted oil and gas exploration and development company with assets in Cameroon and the FSU, announces that the Production Facilities at the Logbaba site, which will treat the gas from the wellheads and separate the condensate, are now mechanically complete. Pre-commissioning of the Production Facilities has commenced and approximately 80 per cent. of all instrumentation loops have been tested. All power circuits are in place and have been tested. Other successful tests completed include the La-105 and La-106 hydraulic valves control, two de-sander units, the 10,000 psi high pressure pipework from the production valves on the christmas trees to the adjustable chokes, the high pressure coolers, the firewater water pumps and the plant back-up diesel generator.

Pre-commissioning of all the remaining vessels and equipment is expected to be completed within the next week. Full commissioning commences thereafter with product and gas being flared while all instrumentation and systems are verified ahead of first gas production.

Pipeline installation to the first customer hub located on the Magzi Industrial Estate ('Magzi') is now complete. The total length of pipeline installed and backfilled to and around Magzi is 5km, comprising 400mm, 250mm and 63mm diameter pipe sizes.

Specialist hydraulic and pneumatic testing equipment has been utilised for pipeline pre-commissioning, which includes stress testing of the entire existing network. This work is expected to be completed within the next two weeks. Radiographic examination of all the pipeline welds will also be completed within this period. On completion of this work programme, the pipeline will be purged with gas for several days as part of the network commissioning process ahead of first gas production.

Customer conversion work has commenced on a number of sites on Magzi. The scope of work includes installation of dual fuel burners and control panels as wells as individual pressure reduction and metering stations. The first customers are scheduled to accept gas before the end of December with additional customers progressively coming on stream thereafter. The Company anticipates steadily building sales to approximately 20 customers by the end of the first year of operations as the entire pipeline network, consisting of 34km, is completed.

The Logbaba gas and condensate field has proven and probable reserves of 212 billion cubic feet of gas (35.3 million barrels of oil equivalent ('boe')) and 4.2 million barrels of condensate. The Company has a 95 per cent interest in and is operator of the Logbaba field. VOG anticipates gross gas sales of 8 million standard cubic feet per day ('mmscf/d') by the end of the first year of operations, rising to 44 mmscf/d (7,300 boe) by the end of 2014. The pipeline has a capacity of 60 mmscf/d, which the Directors anticipate to be of sufficient size to satisfy the Douala industrial market over the medium term. Condensate separated from the gas at the process plant will be stabilised and trucked to the Sonara refinery at Limbe, located 60km away. Condensate sales are anticipated to be 160 barrels of condensate per day by the end of 2012, rising to 880 barrels by the end of 2014.

The Company remains on schedule for first gas sales by the end of the year. With regard to the Logbaba development and production operations, the Company has an excellent HSE record with over 20,000 thousand man days completed, no serious injury and just one lost time incident.

For further information, please contact:

Victoria Oil & Gas Plc - Tel: +44 (0) 20 7921 8820

Kevin Foo / Martin Devine

Macquarie Capital (Europe) Limited Tel: +44 (0) 20 3037 2000

Jeffrey Auld / Steve Baldwin / Nicholas Harland

Fox-Davies Capital - Tel: +44 (0) 20 3463 5010

Daniel Fox-Davies/ Richard Hail

Strand Hanson Limited - Tel: +44 (0) 20 7409 3494

Simon Raggett / Angela Peace

Tavistock Communications - Tel: +44 (0) 20 7920 3150

Ed Portman/ Paul Youens

 

Background Information on Victoria Oil & Gas Plc:

Victoria Oil & Gas is an independent oil and gas exploration and development company with projects in Africa and the FSU. The Company's principal assets are the Logbaba gas and condensate project in Cameroon and the West Medvezhye project in Siberia, Russia. Logbaba is located in Douala, the economic capital of Cameroon. The field was discovered in the 1950s and all four exploration wells encountered gas. The Company drilled two successful development wells in 2009/10 and is now installing production facilities and a pipeline to serve industrial consumers of gas in Douala, anticipated to be complete by the end of 2011. The Company received an Exploitation Licence for the development of the Logbaba Field by Presidential Decree on 29 April 2011.

The Company's Logbaba proved and probable reserves are sufficient to supply an average of 30mmscf/d for the next 20 years. In the longer term, as further reserves may be proven, gas may be supplied to large gas fired power stations connected to the grid, with either VOG investing in an independent power producer joint venture or selling the gas to third parties.

West Medvezhye is situated in the prolific Yamal-Nenetsk hydrocarbon region in Siberia. An independent audit, carried out by Mineral LLC in 2011, estimated prospective resources for the area of over 1.4 billion barrels of oil equivalent. The Company also has a discovery well, 103, with C1 and C2 reserves, independently assessed under the Russian classification convention of 14.4 million boe as approved by the Russian Ministry of Natural Resources.

Reprocessing of 845km of 2D seismic has recently been completed and geophysical/geological modelling is currently underway. In addition, development studies are in progress to commercialise the Well-103 discovery and prospective resources.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLLFFTLLLTFIL
Date   Source Headline
16th Dec 20227:00 amRNSCancellation - Victoria Oil & Gas Plc
27th Oct 20225:30 pmRNSSuspended Companies Notice – Deletions
26th Oct 20227:00 amRNSUpdate on Settlement of The ICC Award to RSM
5th Oct 20229:15 amRNSOperational & Corporate Update
25th Jul 20227:30 amRNSAddendum to ICC Partial Final Award
22nd Jul 20227:00 amRNSQ2 2022 Operational & Corporate Update
30th Jun 20221:45 pmRNSResult of Annual General Meeting
30th Jun 20227:00 amRNSAnnual Report and Accounts & Trading Update
27th Jun 20227:00 amRNSChange of Registered Office
14th Jun 20229:45 amRNSHolding(s) in Company
14th Jun 20229:45 amRNSHolding(s) in Company
31st May 20226:00 pmRNSNotice of AGM
19th May 20227:00 amRNSQ1 2022 Operational & Corporate Update
4th Apr 20227:30 amRNSSuspension - Victoria Oil & Gas plc
4th Apr 20227:00 amRNSTemporary Suspension of Trading
2nd Mar 20227:00 amRNSLoan Note Issue
2nd Feb 20227:00 amRNSQ4 2021 Operational Update
18th Jan 20222:05 pmRNSSecond Price Monitoring Extn
18th Jan 20222:00 pmRNSPrice Monitoring Extension
7th Jan 20222:06 pmRNSSecond Price Monitoring Extn
7th Jan 20222:01 pmRNSPrice Monitoring Extension
7th Jan 202211:06 amRNSSecond Price Monitoring Extn
7th Jan 202211:00 amRNSPrice Monitoring Extension
23rd Dec 20217:00 amRNSMinisterial Approval on Matanda Licence Extension
16th Nov 20214:41 pmRNSSecond Price Monitoring Extn
16th Nov 20214:36 pmRNSPrice Monitoring Extension
16th Nov 20212:05 pmRNSSecond Price Monitoring Extn
16th Nov 20212:00 pmRNSPrice Monitoring Extension
16th Nov 202111:05 amRNSSecond Price Monitoring Extn
16th Nov 202111:00 amRNSPrice Monitoring Extension
16th Nov 20217:00 amRNSUpdate to Logbaba well La-108
1st Nov 20218:42 amRNSReplacement: Interim Results
1st Nov 20217:00 amRNSAnnual Financial Report
1st Oct 202112:00 pmRNSConvertible Loan Note Draw Down
29th Sep 20217:00 amRNSUNCITRAL Arbitration Update
23rd Sep 20212:15 pmRNSInterim Results Extension
10th Sep 20213:22 pmRNSResult of General Meeting
26th Aug 20217:00 amRNSPublication of Circular and Notice of GM
12th Aug 202112:28 pmRNSResult of General Meeting (“GM”)
4th Aug 20217:00 amRNSQ2 2021 Operational Update
16th Jul 20211:02 pmRNSGrant of Options, Issue of Shares and TVR
16th Jul 20217:00 amRNSNotice of General Meeting to receive Annual Report
13th Jul 20212:06 pmRNSSecond Price Monitoring Extn
13th Jul 20212:00 pmRNSPrice Monitoring Extension
13th Jul 202111:05 amRNSSecond Price Monitoring Extn
13th Jul 202111:00 amRNSPrice Monitoring Extension
13th Jul 20217:00 amRNSAudited Results for the year ended 31 Dec 2020
30th Jun 20211:38 pmRNSResult of Annual General Meeting
30th Jun 20217:20 amRNSAnnual Report and Accounts & Trading update
24th Jun 202111:13 amRNSAnnual General Meeting 2021 Update on Arrangements

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.