Operations Update

18 Aug 2010 07:00

RNS Number : 2309R
Victoria Oil & Gas PLC
18 August 2010
 



18th August 2010

 

Victoria Oil & Gas Plc

 

("VOG" or the "Company")

 

Operations Update

Logbaba Gas and Condensate Project, Cameroon

 

Highlights

 

·; Second well, La-106 flowed gas at rates up to 22MMscf/d (ca. 3,600 boepd)

·; Facilities and pipeline projects and first gas delivery on schedule for December 2010

·; 20 year exclusive Gas Sales Agreements with the gas price fixed at $16 per million btu for the first 5 years

·; Appointment of Don Nelsen as Country Manager, Cameroon

 

 

Victoria Oil & Gas Plc, (AIM: VOG), the oil and gas exploration and development company with assets in Cameroon and the FSU, is pleased to announce an update on its operations at Logbaba, Cameroon.

 

Logbaba represents the first commercial onshore gas discovery in Cameroon. The field is located in the Eastern part of Douala, the industrial capital of Cameroon and the seaboard hub of Central Africa and its member countries.

 

The Company has successfully drilled and completed two production wells and is on schedule to deliver gas to first customers during December 2010. VOG aims to benefit from its significant first mover advantage and capitalise on Cameroon's strategic location and growing energy demands.

 

The Company offers a considerably cheaper source of fuel and reliability of supply to industrial users, power suppliers and liquid fuel users. Approximately 80% of the initial customer base lies within a 10km radius of the deposit and the Company forecasts that the market will grow to over 100MMscf/d per annum within the next five years.

 

 

Logbaba La-106 Well Testing

 

The second well drilled by the Company, La-106, has continued to flow from the initial perforated interval in the Lower Logbaba formation during most of July. As previously reported, the delivery of special equipment to assist with the high temperatures and pressures experienced in the well bore was duly procured and the perforation of the remaining intervals was successfully completed.

 

Following completion of the last perforations the well was re-opened to flow on Saturday 14 August and flowed at rates up to 22MMscf/day, (ca. 3,600 boepd,) at different choke sizes up to 36/64 inch and well head flowing pressures up to 3,078 psi. The Company's drilling and operations team are continuing to prepare this well for production.

 

The first well drilled by the Company, La-105, which flowed at rates of 55MMscf/d (ca. 9,100 boepd,) and 1,000 bbl/d of condensate is more than capable of servicing the anticipated market demand in the medium term.

Production Facilities and Pipeline

Following the award of the gas processing plant contract to Expro in July, contracts have now been awarded for the polyethylene pipeline and fittings, directional drilling and jointing equipment. The first pipe supplies have been shipped this week. All other activities including licences and permits are progressing on schedule.

The expected date for the first gas deliveries to customers remains December 2010. Our sales and gas marketing team in Douala have signed 20 year exclusive Gas Sales Agreements with the gas price fixed at $16 per million btu for the first 5 years. Additional customers continue to be signed up. 

Country Manager Appointment

The Board welcomes Mr. Don Nelsen to the company as Country Manager, Cameroon. Mr Nelsen is a 30-year veteran of the international oil and gas industry. A graduate of the US Military Academy, Boston University, and The University of Nebraska, he is an engineer, international business specialist and lawyer. Before joining VOG, he has worked as Country Manager for ConocoPhillips and Noble Energy in Cameroon and Venezuela, in successful exploration and development operations.

 

Chairman Kevin Foo commented, "We are very pleased with progress at Logbaba and we remain focussed on delivery of first gas to customers by the end of year. We welcome Don Nelsen to the Company. He has international project management experience and will be a valuable addition to our team."

 

For further information, please contact:

Victoria Oil & Gas Plc

Tel: +44 (0) 20 7921 8820

Jonathan Scott-Barrett / Kevin Foo 

 

Strand Hanson Limited 

Tel: +44 (0) 20 7409 3494

Simon Raggett / Angela Peace

 

Fox-Davies Capital

Tel: +44 (0) 20 7936 5236

Phil Davies / David Porter

 

Conduit PR 

Tel: +44 (0) 20 7429 6611 

Jonathan Charles / Ed Portman

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLDDLFFBVFZBBL
Date   Source Headline
18th Jun 20217:00 amRNSLoan Note Instrument
4th Jun 202111:07 amRNSNotice of Annual General Meeting
4th Jun 20217:00 amRNSCorporate Update
30th Apr 20217:00 amRNSQ1 2021 Operational Update
19th Apr 20212:06 pmRNSSecond Price Monitoring Extn
19th Apr 20212:01 pmRNSPrice Monitoring Extension
19th Apr 20211:44 pmRNSSettlement with Eneo Cameroon S.A. ("Eneo")
8th Apr 20217:00 amRNSLoan Note
6th Apr 20219:06 amRNSSecond Price Monitoring Extn
6th Apr 20219:00 amRNSPrice Monitoring Extension
1st Apr 20217:23 amRNSCorporate and Operational Update
28th Jan 20217:00 amRNSQ4 2020 Operational Update
22nd Jan 20212:06 pmRNSSecond Price Monitoring Extn
22nd Jan 20212:00 pmRNSPrice Monitoring Extension
24th Nov 20207:54 amRNSMinisterial Approval on Matanda Licence Extension
23rd Nov 20204:41 pmRNSSecond Price Monitoring Extn
23rd Nov 20204:36 pmRNSPrice Monitoring Extension
23rd Nov 20202:06 pmRNSSecond Price Monitoring Extn
23rd Nov 20202:00 pmRNSPrice Monitoring Extension
18th Nov 20207:00 amRNSIssue of Shares
16th Nov 20204:42 pmRNSSecond Price Monitoring Extn
16th Nov 20204:36 pmRNSPrice Monitoring Extension
13th Nov 20204:40 pmRNSSecond Price Monitoring Extn
13th Nov 20204:35 pmRNSPrice Monitoring Extension
12th Nov 20207:00 amRNSSettlement of litigation with CHL & La-108 update
11th Nov 20204:41 pmRNSSecond Price Monitoring Extn
11th Nov 20204:36 pmRNSPrice Monitoring Extension
3rd Nov 20204:40 pmRNSSecond Price Monitoring Extn
3rd Nov 20204:35 pmRNSPrice Monitoring Extension
2nd Nov 20204:36 pmRNSPrice Monitoring Extension
30th Oct 20207:00 amRNSHalf-year Report
29th Oct 202011:38 amRNSResult of General Meeting
28th Oct 20204:36 pmRNSPrice Monitoring Extension
27th Oct 20204:40 pmRNSSecond Price Monitoring Extn
27th Oct 20204:35 pmRNSPrice Monitoring Extension
26th Oct 20204:40 pmRNSSecond Price Monitoring Extn
26th Oct 20204:35 pmRNSPrice Monitoring Extension
30th Sep 20207:00 amRNSAudited Results for year ended 31 December 2019
14th Aug 202012:07 pmRNSSecond Price Monitoring Extn
14th Aug 202012:02 pmRNSPrice Monitoring Extension
11th Aug 20207:00 amRNSAppointment of Chief Financial Officer
27th Jul 20207:28 amRNSQ2 2020 Operational Update
7th Jul 20204:40 pmRNSSecond Price Monitoring Extn
7th Jul 20204:35 pmRNSPrice Monitoring Extension
3rd Jul 202012:36 pmRNSTermination of Agreement to Supply Gas to ENEO
29th Jun 20204:41 pmRNSSecond Price Monitoring Extn
29th Jun 20204:37 pmRNSPrice Monitoring Extension
29th Jun 202012:35 pmRNSResult of Annual General Meeting
26th Jun 20204:35 pmRNSPrice Monitoring Extension
25th Jun 20207:00 amRNSAnnual Report and Accounts & Trading update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.