Logbaba Operational Update

20 Dec 2011 07:00

RNS Number : 2884U
Victoria Oil & Gas PLC
20 December 2011
 



20 December 2011

 

Victoria Oil & Gas Plc

('VOG' or 'the Company')

 

Logbaba Project First Gas and Condensate Production

 

·; VOG delivers first commercial gas production on schedule

·; VOG becomes the first onshore gas and condensate producer in Cameroon, supplying the industrial market

·; Second stage of pipeline network under construction, expected to be completed in Q2 2012

·; Production expected to grow from 8 million standard cubic feet per day ('mmscf/d') by the end of 2012 to 44mmscf/d by the end of 2014

 

Victoria Oil & Gas Plc, the AIM quoted oil and gas exploration and production company with assets in Cameroon and the FSU, is pleased to announce the successful installation and commissioning of production facilities and a gas pipeline network in Douala. Rodeo Development Limited, the Company's wholly owned Cameroon subsidiary, made its first delivery of gas to customers on the Magzi Industrial Estate on the 17 December 2011.

VOG's Executive Chairman Kevin Foo commented, "This is a very significant milestone for the Company. We have now moved from an exploration and development company into a producer. The development of Logbaba is also important news for the city of Douala. The commissioning of two wells, production facilities and the first stage of the pipeline was successful and without incident.

This achievement is the culmination of three years of tireless effort by the team and strong support from shareholders and the Government of the Republic of Cameroon. I am very pleased that we have met our promised target of first production in Q4 2011."

Logbaba Development

Logbaba has gross proved and probable reserves of 212 billion cubic feet of gas and 4.2 million barrels of condensate. VOG has a 95 per cent. working interest and is the operator. The Company has two wells completed as producers. The first well, La-105, tested at rates of up to 55mmscf/d and 1,000 barrels per day of condensate and the second well, La-106, tested at rates of up to 22mmscf/d and unmeasured amounts of condensate. The Company estimates that there are additional prospective resources in excess of 1 trillion cubic feet of gas with associated condensate within the exploitation area.

The Logbaba field has been developed as a fast track project with gas production start-up to the first customer hub while the remainder of the pipeline network continues under construction. The Company anticipates installation of its entire 34km pipeline network, east of the Wouri River, by mid 2012, serving four main industrial hubs.

The Company anticipates gross gas production volumes to rise to a plateau rate of 44mmscf/d by the end of 2014 from 8mmscf/d anticipated by the end of the first year of operations as all initial thermal customers are brought on stream. The pipeline has an operating capacity of 60mmscf/d, which the Directors anticipate to be of sufficient size to satisfy the Douala industrial market over the medium term. Condensate separated from the gas at the production facilities will be stabilised and trucked to the Sonara refinery at Limbe, located 60km away.

Gas and Condensate Sales

In parallel with the development activity this year, gas sales agreements have been signed with 13 industrial customers, including a number of multinational firms. Contract prices have been fixed at $16 per million British thermal units for the first five years (approximately $16 per thousand cubic feet) with price re-sets thereafter. A further 10 gas sales agreements are anticipated to be agreed in early 2012 as the pipeline network expands from the first customer hub in the Magzi region onto the second customer hub in central Douala.

Condensate sales are anticipated to be 160 barrels of condensate per day by the end of 2012, rising to 880 barrels per day by the end of 2014.

 

For further information, please contact:

Victoria Oil & Gas Plc - Tel: +44 (0) 20 7921 8820

Kevin Foo / Martin Devine

Macquarie Capital (Europe) Limited Tel: +44 (0) 20 3037 2000

Jeffrey Auld / Steve Baldwin / Nicholas Harland

Fox-Davies Capital - Tel: +44 (0) 20 3463 5010

Daniel Fox-Davies/ Richard Hail

Strand Hanson Limited - Tel: +44 (0) 20 7409 3494

Simon Raggett / Angela Peace

Tavistock Communications - Tel: +44 (0) 20 7920 3150

Ed Portman/ Paul Youens

 

Background Information on Victoria Oil & Gas Plc:

Victoria Oil & Gas Plc is an independent oil and gas exploration and production company with projects in Africa and the FSU. The Company's principal assets are the Logbaba gas and condensate project in Cameroon and the West Medvezhye project in Siberia, Russia. Logbaba is located in Douala, the economic capital of Cameroon. The field was discovered in the 1950s when all four exploration wells drilled at the time encountered gas. The Company drilled two successful development wells in 2009/10 and was awarded an Exploitation Licence in April 2011.

The Company's Logbaba proved and probable reserves are sufficient to supply an average of 30mmscf/d for the next 20 years to industrial customers. Under current management projections, the Company forecasts industrial gas demand to rise to 44mmscf/d by the end of 2014. In the longer term, as further reserves may be proven, gas may also be supplied to large gas fired power stations connected to the grid, with either VOG investing in an independent power producer joint venture or selling the gas to third parties. The Company has signed a multitude of gas sales agreements with industrial customers to serve their energy requirements and anticipates in excess of 40 customers over the medium term.

West Medvezhye is situated in the prolific Yamal-Nenetsk hydrocarbon region in Siberia. An independent audit, carried out by Mineral LLC in 2011, estimated prospective resources for the area of over 1.4 billion barrels of oil equivalent. The Company also has a discovery well, 103, with C1 and C2 reserves, independently assessed under the Russian classification convention of 14.4 million boe as approved by the Russian Ministry of Natural Resources.

Reprocessing of 845km of 2D seismic has recently been completed and geophysical/geological modelling is currently underway. In addition, development studies are in progress to commercialise the Well-103 discovery and prospective resources.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLFFEFFILALIL
Date   Source Headline
24th Jan 20147:00 amRNSRSM Settlement and US$16.3m Received
17th Jan 20147:00 amRNSLoan and Customs bond with BGFIBank
13th Jan 20147:00 amRNSRSM Default
10th Jan 20144:40 pmRNSSecond Price Monitoring Extn
10th Jan 20144:35 pmRNSPrice Monitoring Extension
8th Jan 20147:00 amRNSCommercial Developments, Gaz du Cameroun
19th Dec 20137:00 amRNSPresidential Visit Video
13th Dec 20138:45 amRNSRestoration of Trading on AIM
13th Dec 20138:45 amRNSRestoration - Victoria Oil & Gas Plc
13th Dec 20137:00 amRNSRSM vs VOG and RDL Arbitration
12th Dec 20134:16 pmRNSICC International Court of Arbitration Award
12th Dec 20133:52 pmRNSSuspension - Victoria Oil & Gas plc
2nd Dec 20139:36 amRNSUpdate re Arbitration
27th Nov 20132:35 pmRNSResult of AGM
19th Nov 20138:22 amRNSPresidential Visit & Gas Launch
8th Nov 20137:00 amRNSAdditional Customer Online
1st Nov 20137:16 amRNSUpdate re: RSM Arbitration
25th Oct 20137:00 amRNSFinal Results
10th Oct 20137:00 amRNSTrading and Operations Update
2nd Oct 201310:45 amRNSHolding(s) in Company
1st Oct 20133:10 pmRNSShare Price Movement
30th Sep 20137:00 amRNSDirectorate Change
27th Sep 20134:40 pmRNSSecond Price Monitoring Extn
27th Sep 20134:35 pmRNSPrice Monitoring Extension
21st Aug 20134:40 pmRNSSecond Price Monitoring Extn
21st Aug 20134:35 pmRNSPrice Monitoring Extension
18th Jul 20137:00 amRNSChief Executive Officer's Letter to Shareholders
3rd Apr 201311:38 amRNSHolding(s) in Company
6th Mar 20135:46 pmRNSHolding(s) in Company
6th Mar 20139:00 amRNSHolding(s) in Company
1st Mar 20132:00 pmRNSResult of General Meeting
28th Feb 20137:00 amRNSInterim Results
27th Feb 20137:00 amRNSAppointment of Renaissance Capital
26th Feb 20133:57 pmRNSStatement: re RSM Production Corporation
26th Feb 20137:00 amRNSAppointment of New Chief Executive Officer
13th Feb 20137:00 amRNSHolding(s) in Company
12th Feb 201310:59 amRNSHolding(s) in Company
12th Feb 201310:59 amRNSHolding(s) in Company
11th Feb 20133:52 pmRNSHolding(s) in Company
11th Feb 20132:00 pmRNSNotice of GM & Investor Presentation
6th Feb 20131:25 pmRNSResignation of broker
6th Feb 20137:00 amRNSIssue of Equity
30th Jan 20137:00 amRNSOperations Update & Societe Generale Commitment
21st Dec 20127:00 amRNSOperational Update and Additional Listing
18th Dec 20124:40 pmRNSSecond Price Monitoring Extn
18th Dec 20124:35 pmRNSPrice Monitoring Extension
30th Nov 20127:00 amRNSResult of AGM and Operational Update
14th Nov 20127:00 amRNSGas Market Study on Logbaba
6th Nov 20124:40 pmRNSSecond Price Monitoring Extn
6th Nov 20124:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.