Operational update

30 Nov 2011 07:46

RNS Number : 0349T
Volga Gas PLC
30 November 2011
 



30 November 2011

VOLGA GAS PLC

 

Operational update

 

Volga Gas plc ("Volga Gas" or the "Company"), the oil and gas exploration and production group operating in the Volga Region of Russia, announces the following update on its exploration and development operations.

 

Urozhainoye-2 licence area

 

The Yu. Romanovskaya #1 exploration well reached its initial target at a depth of 2,885 metres where the Bo layer was found to be thinner than prognosed and without hydrocarbons. Having completed logging operations, drilling is to continue to the primary target horizon at a depth of 3,800 metres. The rig used to drill the top section of the well will remain on location to drill the deeper section, in an operation that is expected to take about three months.

 

Uzenskoye oil field

 

Drilling is expected to commence shortly on the first of two sidetracks to existing wells on the Uzenskoye oil field in the Company's Karpenskiy Licence Area. The two wells are Uz #9 and Uz #4. Both wells are located at the edge of the field and are currently non-producing. The wells were previously planned to be converted into water injectors but recent studies showed that there is no need to have any water injection in the near future due to the presence of an active aquifer.

 

The planned bottom hole locations for the sidetracks are updip and infield from the current locations. It is expected that overall field production will increase substantially following the completion of these operations.

 

The Uzenskoye oil field is currently producing at a rate of approximately 1,200 bopd from four wells.

 

Dobrinskoye gas/condensate field

 

Drilling of a sidetrack to the existing well #22 on the Dobrinskoye field is expected to commence early in 2012 as planned. This well, which had been producing in 2010, has suffered water encroachment and has been shut in since June 2011. The well is to be sidetracked into the main reservoir and completed for production. On completion, Well #22 is expected to contribute a substantial proportion of future field production.

 

The Dobrinskoye field is currently producing from a single well, Well #26 and is currently producing at a rate of 6.0 mmcf/d gas  plus 448 bpd of condensate.

 

Vostochny Makarovskoye gas/condensate field

 

Preliminary trials of a proposed sulphur processing system on gas from the Vostochny Makarovskoye ("VM") gas/condensate field have been conducted at the Dobrinskoye gas plant with successful results. The Company has commenced a programme to upgrade the gas plant to provide additional capacity and sulphur treatment. It is expected that the upgrade will be completed during Q3 2012 and production from the VM field will commence shortly thereafter.

 

There are two existing production wells on the field: VM#1 and VM#2, both of which have been completed for production from the Evlansko-Livenskiy reservoir and connected to the plant. In addition, the Company plans to undertake the workover of another well, #30, as a producing well from the Bobrikovskiy reservoir. Well #30, which was drilled before Volga Gas acquired the VM licence, achieved a flow rate of over 7.4 mmcf/d under flow test from the Bobrikovskiy reservoir. The plan is to place all three wells on production when the gas plant upgrade is completed. Further development drilling, including a sidetrack of the VM#4 well is planned for 2013 and beyond.

 

Pre-Caspian Licence Area

 

An exploration well, Mirnaya #2, is to commence drilling in the Pre-Caspian licence area in Q1 2012. As announced on 1 August 2011, the State Committee for Resources approved C3 resource estimates of 58 million barrels of oil equivalent on this prospect. The well is to be drilled to a target depth of 1,220 metres into a supra-salt target believed to be prospective primarily for oil.

 

Capital expenditure programme

 

The planned capital expenditure programme for the remainder of 2011 and for 2012, including all of the above activities, totals US$16.3 million, of which US$5.8 million is related to exploration and US$10.5 million to production and field development activities.

 

This capital programme is expected to be funded from cash generated from operations and the Group's existing cash resources.

Mikhail Ivanov, Chief Executive of Volga Gas commented:

"While we are disappointed not to have discovered oil in our secondary target with the YR#1 well, we are excited with the programme of development drilling that we are commencing and especially with the project to bring the VM field into production. Successful completion of this programme will enable Volga Gas to achieve substantially increased production in 2012, from the current total Group production of approximately 2,600 barrels of oil equivalent per day,

 and consequently increased cash generation."

 

 

For additional information please contact:

 

Volga Gas plc

Mikhail Ivanov, Chief Executive Officer

+7 (495) 721 1233

Tony Alves, Chief Financial Officer

+44 (0) 20 8622 4451

Oriel Securities Limited, Nominated Adviser and Broker

Michael Shaw

Gareth Price

+44 (0)20 7710 7600

FTI Consulting

Billy Clegg

+44 (0)20 7831 3113

Ed Westropp

Alex Beagley

 

 

Editors' notes:

Volga Gas is an independent oil and gas exploration and production company operating in the Volga region of European Russia. The Company has 100% interests in its four licence areas.

 

The information contained in this announcement has been reviewed and verified by Mr. Mikhail Ivanov, Director and Chief Executive Officer of Volga Gas plc, for the purposes of the Guidance Note for Mining, Oil and Gas companies issued by the London Stock Exchange in June 2009. Mr. Mikhail Ivanov holds a M.S. Degree in Geophysics from Novosibirsk State University. He also has an MBA degree from Kellogg School of Management (Northwestern University). He is a member of the Society of Petroleum Engineers.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCURSBRASAAORA
Date   Source Headline
29th Apr 20107:00 amRNSKarpenskiy Licence Area: new supra salt prospect
30th Mar 20107:00 amRNSFull year results
4th Mar 201010:00 amRNSOperational Update - Vostochny Makarovskoye
23rd Nov 20097:00 amRNSOperational Update
26th Oct 20097:00 amRNSDrilling Update
16th Sep 20097:00 amRNSInterim Results
28th Aug 20097:00 amRNSDrilling commences on sub-salt Grafovskaya
25th Aug 20097:00 amRNSKarpenskiy supra-salt operational update
14th Aug 20094:40 pmRNSSecond Price Monitoring Extn
14th Aug 20094:35 pmRNSPrice Monitoring Extension
30th Jul 20097:00 amRNSDevelopment Drilling Update
10th Jul 200911:31 amRNSHolding(s) in Company
10th Jul 20099:21 amRNSHolding(s) in Company
7th Jul 20098:01 amRNSDealings by Directors and Significant Shareholders
6th Jul 20094:40 pmRNSSecond Price Monitoring Extn
6th Jul 20094:35 pmRNSPrice Monitoring Extension
6th Jul 200911:44 amRNSResult of General Meeting
22nd Jun 20091:59 pmRNSDirector/PDMR Shareholding
22nd Jun 20097:00 amRNSResult of Bookbuilding
19th Jun 20094:21 pmRNSPosting of Circular to Shareholders
18th Jun 20099:48 amRNSResult of AGM
18th Jun 20099:14 amRNSReplacement: Placing
18th Jun 20097:00 amRNSPlacing
17th Jun 20094:41 pmRNSSecond Price Monitoring Extn
17th Jun 20094:35 pmRNSPrice Monitoring Extension
10th Jun 20097:00 amRNSDrilling Update
14th May 20093:37 pmRNSDirector dealing
8th May 20094:35 pmRNSPrice Monitoring Extension
7th May 20093:27 pmRNSHolding(s) in Company
30th Apr 20098:55 amRNSChange of Adviser
31st Mar 20097:00 amRNSFinal Results
30th Mar 20097:00 amRNSReserve Report and Drilling Update
17th Mar 20098:47 amRNSReplacement: Issue of Equity
17th Mar 20098:45 amRNSReplacement: Total Voting Rights
10th Mar 200911:14 amRNSChange of Registered Address
2nd Mar 20094:40 pmRNSSecond Price Monitoring Extn
2nd Mar 20094:36 pmRNSPrice Monitoring Extension
27th Feb 20094:41 pmRNSSecond Price Monitoring Extn
27th Feb 20094:36 pmRNSPrice Monitoring Extension
3rd Feb 20093:28 pmRNSOperational update
15th Jan 20095:22 pmRNSHolding(s) in Company
14th Jan 20098:44 amRNSRe Management Share Options
7th Jan 200911:43 amRNSResult of EGM
19th Dec 20084:40 pmRNSSecond Price Monitoring Extn
19th Dec 20084:36 pmRNSPrice Monitoring Extension
18th Dec 20084:41 pmRNSSecond Price Monitoring Extn
18th Dec 20084:36 pmRNSPrice Monitoring Extension
17th Dec 20084:40 pmRNSSecond Price Monitoring Extn
17th Dec 20084:35 pmRNSPrice Monitoring Extension
16th Dec 20084:40 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.