Operational Update

5 Jun 2008 07:00

RNS Number : 0018W
Volga Gas PLC
05 June 2008
 



5 June 2008

VOLGA GAS PLC

Operational Update

Volga Gas Plc ("Volga Gas" or the "Company") is pleased to provide an operational update on its activities.

Highlights

Yuzhny-Ershovskoye structure ("Y-E") on Karpenskiy licence area ("KLA") delineated, well location identified

Processing of 3-D seismic on the sub-salt Yuzhny-Mokrousovskoye ("Y-M") structure on the KLA complete

Well VM#2 spudded 29 May 2008

Well VM#1 cased and is undergoing production testing 

Construction of Vostochny-Makarovskoye gas processing plant ("GPP") commenced

Interpretation and processing of 3-D seismic data on 2 of 5 supra-salt structures on KLA complete. Drilling programme to commence in H2 2008

Karpenskiy Licence Area

Sub-salt

Yuzhny-Ershovskoye Structure

Schlumberger has completed the processing and interpretation of the 3-D seismic data. The structure has been delineated and the location of the first well identified. Further details are available on the Company's website:

http://volgagas.com/index.php?option=com_content&task=view&id=5&Itemid=7

Yuzhny-Mokrousovsky Structure

Schlumberger has completed processing of the Y-M structure and has started interpretation. It is expected that interpretation will be completed during Q3 2008.

Drilling 

Volga Gas is preparing well documentation and has entered in to detailed negotiations for the first well on Y-E now that parameters are known. The Company will provide an update once a contract has been entered in to.

Supra-Salt

Interpretation and processing of 3-D seismic data has been completed over 2 of the 5 structures in the southern block of the KLA. The Company has entered in to a well contract, at least 4 of which are expected to be completed during 2008.

Vostochny-Makarovskoye

On 29 May 2008, Volga Gas spudded well VM#2 at the northern end of the Vostochny-Makarovskoye licence area. The well is being drilled as a production well and is expected to be completed in early Q4 2008. The Company has contracted the BK Eurasia rig for a further well with an option for two more.

Well VM#1 has been cased and is currently being hooked up to the gas processing plant.  Initial cased hole testing has yielded commercial rates of gas and condensate and the well will be put on long term production testing in June.

Installation of the gas processing plant has commenced and is running to plan. We anticipate the plant to be capable of selling pipeline standard gas by year end, enabling first revenue to commence as previously announced.

Mikhail Ivanov, Chief Executive of Volga Gas commented:

"With the delineation of the sub-salt Y-E structure complete and the location for the first well identified, the Company is now well-placed to commence drilling operations on this high potential structure. Work on the equally important Y-M structure is progressing well.

"The Vostochny-Makarovskoye development schedule is on track to produce first revenue before year-end. Well VM#2 is essential to enhance our understanding of the Evlano-Livenskiy reservoir. Following the completion of VM#2, we will incorporate the data in to the reservoir model and will subsequently publish updated reserve calculations during 4Q 2008."

- Ends -

Volga Gas is an independent gas exploration and production company, which currently holds four subsoil licenses in the Volga Region of European Russia

For additional information please contact:

Financial Dynamics

+44 (0)20 7831 3113

Billy Clegg

Alex Beagley

KBC Peel Hunt

(Nominated Adviser)

+44 (0)20 7418 8900

Jonathan Marren

Alina Savych 

The information contained in this announcement has been reviewed and verified by Mr. Mikhail Ivanov, Director and Chief Executive Officer of Volga Gas plc, for the purposes of the Guidance Note for Mining, Oil and Gas companies issued by the London Stock Exchange in March 2006. Mr. Mikhail Ivanov holds a M.S. Degree in Geophysics from Novosibirsk State University. He has also MBA degree from Kellogg School of Management (Northwestern University). He is a member of the Society of Petroleum Engineers.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUSSVRWURNRAR
Date   Source Headline
14th Apr 20217:00 amRNSCancellation of trading on AIM
14th Apr 20217:00 amRNSCancellation - Volga Gas PLC
23rd Mar 20213:44 pmRNSHolding(s) in Company
11th Mar 20214:21 pmRNSCommencement of Compulsory Acquisition Process
9th Mar 20217:47 amRNSHolding(s) in Company
8th Mar 20217:00 amRNSProposed cancellation of trading on AIM
5th Mar 20216:00 pmRNSVolga Gas
5th Mar 20217:01 amRNSAcceptance of Offer by Directors of Volga Gas PLC
5th Mar 20217:00 amRNSOffer Declared Unconditional In All Respects
12th Feb 20217:00 amRNSOffer Declared Unconditional as to Acceptances
2nd Feb 20217:00 amRNSAcceptance Levels and Extension of Offer
19th Jan 20217:00 amRNSAcceptance Levels and Extension of Offer
5th Jan 20219:53 amRNSPRODUCTION REPORT FOR DECEMBER 2020
5th Jan 20217:00 amRNSAcceptance Levels and Extension of Offer
14th Dec 20207:00 amRNSPosting of Offer Document
2nd Dec 20207:00 amRNSPRODUCTION REPORT FOR NOVEMBER 2020
18th Nov 20202:25 pmRNSForm 8 (OPD) - GEM Capital Holdings (CY) Ltd
16th Nov 20207:00 amRNSAll Cash Offer for Volga Gas plc
4th Nov 20207:00 amRNSPRODUCTION & DRILLING UPDATE REPORT FOR OCT 2020
6th Oct 20207:00 amRNSEXPLORATION DRILLING UPDATE
2nd Oct 20207:00 amRNSPRODUCTION & DRILLING UPDATE REPORT - SEPTEMBER 20
30th Sep 202010:57 amRNSResult of AGM
30th Sep 20207:00 amRNSINTERIM RESULTS
28th Sep 20207:00 amRNSUPDATE ON FORMAL SALE PROCESS
8th Sep 20207:00 amRNS2019 ANNUAL RESULTS AND NOTICE OF AGM
2nd Sep 20207:00 amRNSPRODUCTION & DRILLING UPDATE REPORT FOR AUGUST 20
14th Aug 20207:00 amRNSOIL DRILLING UPDATE
7th Aug 20207:00 amRNSPRODUCTION & DRILLING UPDATE REPORT FOR JULY 2020
3rd Jul 20207:00 amRNSPRODUCTION REPORT FOR JUNE 2020
26th Jun 20207:00 amRNSUPDATE ON FORMAL SALE PROCESS
2nd Jun 20207:00 amRNSPRODUCTION REPORT FOR MAY 2020
29th May 202011:05 amRNSSecond Price Monitoring Extn
29th May 202011:00 amRNSPrice Monitoring Extension
29th May 20207:00 amRNSDELAY IN PUBLICATION OF 2019 ANNUAL REPORT
18th May 20202:00 pmRNSPrice Monitoring Extension
11th May 20207:00 amRNSSTATEMENT RE SHARE PRICE MOVEMENT AND FSP
4th May 20204:16 pmRNSPRODUCTION REPORT FOR APRIL 2020
20th Apr 20204:41 pmRNSSecond Price Monitoring Extn
20th Apr 20204:36 pmRNSPrice Monitoring Extension
17th Apr 20204:25 pmRNSForm 8.3 – Nicholas Mathys – Volga Gas plc
17th Apr 20204:25 pmRNSForm 8.3 - Genesis Development Holdings Co Ltd
17th Apr 20201:06 pmRNSForm 8 (OPD) Volga Gas PLC - Replacement
17th Apr 20208:04 amRNSForm 8 (OPD) Volga Gas PLC
14th Apr 20202:37 pmRNSPRODUCTION REPORT FOR MARCH 2020 - Replacement
9th Apr 20203:26 pmRNSHolding(s) in Company
7th Apr 20207:00 amRNSPreliminary Results
7th Apr 20207:00 amRNSStrategic Review including Formal Sale Process
2nd Apr 20207:00 amRNSPRODUCTION REPORT FOR MARCH 2020
20th Mar 20207:00 amRNSDirectorate Changes
10th Mar 20202:05 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.