Project Development Update

19 Jun 2019 07:00

RNS Number : 6854C
Tlou Energy Ltd
19 June 2019
 

19 June 2019

 

Tlou Energy Limited

("Tlou" or "the Company")

 

Project Development Update

 

 

Tlou Energy Limited is pleased to announce that the Lesedi 3 production pod has successfully reached Critical Desorption Pressure ("CDP"). CDP is the pressure that gas begins to come out of the coal after a careful dewatering process.

 

Highlights

· Lesedi 3 has reached CDP

· Lesedi 4 continues to be carefully dewatered in a consistent and controlled manner

 

Tlou's Managing Director, Mr Tony Gilby commented, "Since the commencement of production testing, the dewatering process at Lesedi 3 and Lesedi 4 has steadily progressed with CDP recently being reached at Lesedi 3. The primary objective remains to demonstrate a commercial gas flow rate."

 

Production Update

Lesedi 3, the first dual lateral production pod completed earlier this year, has reached Critical (gas) Desorption Pressure (CDP) in the horizontal well bores. Reaching CDP is a positive milestone in the operation and means that as a result of a careful and successful dewatering process to date, gas begins to come out of the coal.

 

The next stage of the operation at Lesedi 3 involves continued water pumping which should see gas pressure steadily increase inside the casing to an optimal point so that flow testing and flaring of the gas can begin.

 

Lesedi 4 (the second pod drilled and completed) continues to be carefully dewatered. Water is continuing to be drawn down in a controlled manner as planned.

 

Further updates on progress at Lesedi 3 and 4 will be provided in due course.

 

The information contained within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

 

****

 

 

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Tony Gilby, Managing Director

 

Solomon Rowland, General Manager

 

 

 

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke, Seamus Fricker

 

 

 

Shore Capital (Broker)

+44 (0) 207 408 4090

Jerry Keen, Toby Gibbs, Mark Percy

 

 

 

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

 

Company Information

Tlou Energy is focused on delivering Gas-to-Power solutions in Botswana and southern Africa to alleviate some of the chronic power shortage in the region. Tlou is developing projects using coal bed methane (CBM) natural gas. Botswana has a significant energy shortage and generally relies on imported power and diesel generation to fulfil its power requirements. As 100% owner of the most advanced gas project in the country, the Lesedi CBM Project, Tlou Energy provides investors with access to a compelling opportunity using domestic gas to produce power and displace expensive diesel and imported electricity.

 

The Company is listed on the Australian Securities Exchange, London's AIM market and the Botswana Stock Exchange and is led by an experienced Board, management and advisory team including individuals with successful track records in the CBM industry.

 

Since establishment, the Company has significantly de-risked the project in consideration of its goal to become a significant gas-to-power producer. The Company flared its first gas in 2014 and has a 100% interest over its Mining Licence and ten Prospecting Licences covering an area of ~9,300 Km2 in total. The Lesedi and Mamba Projects already benefit from significant independently certified 2P gas Reserves of ~41 BCF. In addition, 3P gas Reserves of ~427 BCF and Contingent Gas Resources of ~3,043 BCF provide significant additional potential.

 

The Company is planning an initial scalable gas-to-power project. Following successful implementation of this first scalable project, the Company looks forward to evaluating longer-term prospects for the delivery of electricity generated from CBM in Botswana to neighbouring countries.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDUWSORKKANAUR
Date   Source Headline
23rd Oct 202011:00 amRNSPrice Monitoring Extension
22nd Oct 20204:41 pmRNSSecond Price Monitoring Extn
22nd Oct 20204:35 pmRNSPrice Monitoring Extension
25th Sep 20208:30 amRNSNotice of Annual General Meeting
24th Sep 202010:17 amRNSAppendix 4G and Corporate Governance Statement
21st Sep 20207:00 amRNSFinal Results
16th Sep 20207:00 amRNSTransmission Line Update
14th Sep 20207:00 amRNSResults of General Meeting
3rd Sep 20207:00 amRNSDate of Annual General Meeting
26th Aug 20207:00 amRNSTransmission line and funding update
12th Aug 20207:00 amRNSNotice of General Meeting
7th Aug 20201:33 pmRNSHolding(s) in Company
30th Jul 20207:00 amRNSOperational Report - Quarter Ending 30 June 2020
24th Jul 20207:00 amRNSPlacement of remaining Entitlement Offer shares
16th Jul 20207:37 amRNSEntitlement Offer Closes
6th Jul 20207:00 amRNSNon-Renounceable Entitlement Offer – Closing Soon
25th Jun 20207:00 amRNSEntitlement Offer - Despatch of Booklet
18th Jun 20207:00 amRNSGeneration License Conditions received from BERA
15th Jun 20207:00 amRNSEntitlement Offer to raise up to A$3.0 million
15th Jun 20207:00 amRNSCorporate Presentation
29th Apr 202011:20 amRNSGas and Solar Presentation
16th Apr 20207:00 amRNSOperational Report - Quarter Ending 31 March 2020
9th Apr 202011:00 amRNSPrice Monitoring Extension
3rd Apr 202010:10 amRNSInterim Power Purchase Agreement
24th Mar 20207:00 amRNSResponse to Prevailing Financial Market Conditions
25th Feb 20207:00 amRNSHalf-year Report
20th Feb 20207:00 amRNSPower Purchase Agreement Update
20th Feb 20207:00 amRNSPower Purchase Agreement Update
20th Jan 20207:00 amRNSOperational Report - Quarter ending 31 Dec 2019
25th Nov 20197:00 amRNSOperational and Corporate Update
30th Oct 20197:00 amRNSCorporate Presentation
17th Oct 20197:00 amRNSResults of AGM, Chairman's Address, Field visit
16th Oct 20197:00 amRNSOperational Report Quarter Ended 30 September 2019
13th Sep 20198:13 amRNSAppendix 4G and Corporate Governance Statement
13th Sep 20198:07 amRNSNotice of Annual General Meeting
3rd Sep 201912:28 pmRNSManaging Director Share Purchase
2nd Sep 20193:11 pmRNSDirector/PDMR Shareholding
30th Aug 20199:01 amRNSCorporate Presentation
27th Aug 20197:00 amRNSDate of Annual General Meeting
27th Aug 20197:00 amRNSFinal Results
22nd Aug 20197:00 amRNSLesedi Pods Achieve Sustained Gas Flows
29th Jul 20197:00 amRNSOperational Report - Quarter Ending 30 June 2019
10th Jul 20197:00 amRNSLesedi Gas Flow Testing Update
19th Jun 20197:00 amRNSProject Development Update
20th May 20192:10 pmRNSConfirmation of Tender approval
15th May 20197:00 amRNSPublic Procurement & Asset Disposal Board Decision
1st May 20197:00 amRNSApproval Of Downstream EIS
29th Apr 20197:00 amRNSOperational Report - Quarter Ending 31 March 2019
18th Apr 20196:00 pmRNSTR-1: Notification of Major Holdings
16th Apr 20197:00 amRNSPlacement with Botswana based investors

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.