Operations Update

18 Jul 2018 14:18

RNS Number : 0600V
Tlou Energy Ltd
18 July 2018
 

18 July 2018

 

Tlou Energy Limited

 

("Tlou" or "the Company")

 

Operations Update

 

 

Key Points:

 

· Tlou's core drilling rig has arrived at the Company's field camp in Botswana and when commissioned, will be utilised to provide flexible and cost-effective coring operations;

· Ordering of long lead time items, purchase of drilling equipment and rig selection for the gas production pods are progressing in a timely manner;

· A report detailing the optimum locations for the gas production pods is nearing completion.

 

Core drilling rig

Tlou Energy Limited is pleased to announce that a recently purchased core drilling rig has arrived onsite at the Lesedi CBM project in Botswana. The rig has low hours and will be ideal for obtaining coal and gas data in regions of sparse geological information, noting that the Company holds 100% of licences covering over 8,000 Km2.

 

Tlou already has its own desorption testing facilities onsite which allows the Company to test core-hole samples without the requirement to mobilise third party personnel. Owning the core rig and gas testing equipment is expected to greatly reduce the cost of Tlou's core-hole drilling and allows the company more flexibility and control of proposed coring operations.

 

Production drilling

As previously announced the Company is planning to drill production wells, commencing Q3 2018. Each gas production or "dual lateral" pod consists of three wells in total (two lateral wells which intersect a vertical well). In advance of this planned work, long lead items have been ordered and drilling rig selection is progressing with drilling of the first of the pods scheduled to begin later this quarter. Note that the rig required for these pods is a larger unit than the core drilling rig mentioned earlier and therefore is being externally sourced.

 

Production well locations

Tlou completed a seismic survey in late 2017 and a core-hole drilling program in early 2018. Following this work the company obtained a substantial upgrade of gas reserves. In addition, a significant amount of vital sub-surface information was acquired by the Company which continues to be assessed by Tlou's independent consultants. This process is nearing completion and a final report detailing optimum locations for the new gas production wells will be completed in the near term.

 

Corporate

Tlou Energy Limited has completed the quotation of all shares following the Non-Renounceable Entitlement Offer ("Entitlement Offer") announced on 6 June 2018 and placement of shares not subscribed for under the Entitlement Offer.

 

Following admission of the Shares, the total number of voting rights of the Company's ordinary shares is 409,113,535. This figure of 409,113,535 ordinary shares may be used by shareholders in the Company as the denominator for the calculations by which they will determine if they are required to notify their interest in, or a change in their interest in, the share capital of the Company under the FCA's Disclosure Guidance and Transparency Rules.

 

The information contained within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

 

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Tony Gilby, Managing Director

Solomon Rowland, General Manager

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke

Shore Capital (Broker)

+44 (0) 207 408 4090

Jerry Keen, Toby Gibbs, Mark Percy

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

Company Information

Tlou Energy is focused on delivering Gas-to-Power solutions in Botswana and southern Africa to alleviate some of the chronic power shortage in the region. Tlou is developing projects using coal bed methane ("CBM") natural gas. Botswana has a significant energy shortage and generally relies on expensive imported power and diesel generation to fulfil its power requirements. As 100% owner of the most advanced gas project in the country, the Lesedi CBM Project, Tlou Energy provides investors with access to a compelling opportunity using domestic gas to produce power and displace expensive diesel and imported power.

 

The Company is listed on the Australian Securities Exchange, London's AIM market and the Botswana Stock Exchange and is led by an experienced Board, management and advisory team including individuals with successful track records in the CBM industry.

 

Since establishment, the Company has significantly de-risked the project in consideration of its goal to become a significant gas-to-power producer. The Company flared its first gas in 2014, holds a Mining Licence and nine Prospecting Licences, covering an area of ~8,300Km2 in total, and the Lesedi Project already benefits from significant independently certified Contingent Gas Resources of ~3.2 trillion cubic feet (3C) and independently certified Gas Reserves of ~261 billion cubic feet (3P).

 

The Company is planning an initial scalable gas-to-power project. Following successful implementation of this first scalable project, the Company looks forward to evaluating longer-term prospects for the delivery of electricity generated from CBM in Botswana to neighbouring countries.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDSFIFDAFASEFW
Date   Source Headline
22nd Oct 20219:00 amRNSPrice Monitoring Extension
22nd Oct 20218:27 amRNSNotice of Annual General Meeting
20th Oct 20217:00 amRNSCorporate Presentation
19th Oct 20212:05 pmRNSSecond Price Monitoring Extn
19th Oct 20212:00 pmRNSPrice Monitoring Extension
18th Oct 202110:53 amRNS10MW Power Purchase Agreement Signed
18th Oct 20219:11 amRNSPower Purchase Agreement Signing Ceremony
21st Sep 20217:00 amRNSFinal Results
30th Jul 20212:33 pmRNSHeads of Agreement - Hydrogen Programme
30th Jul 20217:00 amRNSOperational Report - Quarter ending 30 June 2021
11th Jun 20214:40 pmRNSSecond Price Monitoring Extn
11th Jun 20214:35 pmRNSPrice Monitoring Extension
3rd Jun 20217:14 amRNSMrs. Linah Mohohlo
28th May 20217:00 amRNSHydrogen Strategy
26th Apr 20217:00 amRNSOperational Report - Quarter ending 31 March 2021
14th Apr 20217:01 amRNSTender awards for Transmission Line and Substation
9th Apr 20212:05 pmRNSSecond Price Monitoring Extn
9th Apr 20212:00 pmRNSPrice Monitoring Extension
30th Mar 20217:01 amRNSBoomslang Project – Environmental approval
24th Mar 20217:00 amRNSHolding(s) in Company
17th Mar 202111:06 amRNSSecond Price Monitoring Extn
17th Mar 202111:00 amRNSPrice Monitoring Extension
17th Mar 20217:00 amRNSResult of Placing
16th Mar 20214:35 pmRNSProposed placing to raise £2.6 million
8th Mar 20214:40 pmRNSSecond Price Monitoring Extn
8th Mar 20214:35 pmRNSPrice Monitoring Extension
4th Mar 20214:40 pmRNSSecond Price Monitoring Extn
4th Mar 20214:35 pmRNSPrice Monitoring Extension
1st Mar 20217:00 amRNSFinance progressing with key funding partner
26th Feb 20217:00 amRNSInterim Results
16th Feb 20217:00 amRNSTlou seeking Carbon Neutrality
28th Jan 20217:00 amRNSOperational Report Quarter Ended 31 December 2020
19th Jan 20217:00 amRNSMinistry Update On 100MW Tender
18th Dec 20207:00 amRNSTender timetable, finance, and project update
9th Nov 20204:32 pmRNSDirectors’ shareholdings
2nd Nov 20202:06 pmRNSSecond Price Monitoring Extn
2nd Nov 20202:00 pmRNSPrice Monitoring Extension
29th Oct 20207:00 amRNSOperational Report Quarter Ended 30 September 2020
28th Oct 20204:41 pmRNSSecond Price Monitoring Extn
28th Oct 20204:35 pmRNSPrice Monitoring Extension
28th Oct 20202:00 pmRNSPrice Monitoring Extension
27th Oct 20207:35 amRNSFunding update and Ministerial site visit
27th Oct 20207:00 amRNSResults of AGM and Chairman’s Address
26th Oct 202011:05 amRNSSecond Price Monitoring Extn
26th Oct 202011:00 amRNSPrice Monitoring Extension
23rd Oct 20204:40 pmRNSSecond Price Monitoring Extn
23rd Oct 20204:35 pmRNSPrice Monitoring Extension
23rd Oct 20202:05 pmRNSSecond Price Monitoring Extn
23rd Oct 20202:00 pmRNSPrice Monitoring Extension
23rd Oct 202011:05 amRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.