Operations Update - Excellent Progress at Lesedi

20 Nov 2018 07:00

RNS Number : 8727H
Tlou Energy Ltd
20 November 2018
 

20 November 2018

 

Tlou Energy Limited

 

("Tlou" or "the Company")

 

Operations Update - Excellent Progress at Lesedi

 

 

Tlou Energy Limited, the ASX, AIM and BSE listed company focused on developing gas-to-power projects in southern Africa using coal bed methane ("CBM") natural gas from its field in Botswana, is pleased to provide an update on drilling operations at the Lesedi CBM Project.

 

Key Points:

· Drilling at the Lesedi CBM Project is making excellent progress and is on budget;

· The second vertical well in the program 'Lesedi 4P' has been drilled and reached a total depth of 577m having encountered a very good target coal horizon;

· Top-hole drilling has been completed at the third vertical well 'Lesedi 5P';

· Top-hole drilling is progressing at the first lateral well 'Lesedi 3A'.

 

Update of Drilling operations

Tlou Energy Limited is currently drilling pilot production wells at the Lesedi CBM Project ('Lesedi') in Botswana. If successful, these wells will form part of the Company's initial gas-to-power project which will include installation of transmission lines and grid connection. The wells are located in close proximity to the Company's planned central processing facility.

 

The wells will be drilled as 'dual lateral pods', comprising a single vertical production well, intersected by two lateral (or horizontal) wells. The lateral wells will be drilled through the gassy coal seam, with gas extracted from this coal produced through the vertical production well where it can be gathered and used for power generation.

 

Up to three pods are planned. Pod one is designated 'Lesedi 3' and comprises a vertical production well ('Lesedi 3P') and two lateral wells ('Lesedi 3A' & 'Lesedi 3B'). Pod two is designated 'Lesedi 4' and pod three is designated 'Lesedi 5'. Vertical production wells Lesedi 3P and Lesedi 4P have been completed. The Lesedi 5P top-hole section has also been drilled. This pod will be completed subject to results from Lesedi 3 and 4 in order to retain optionality. Following completion of the top-hole section of Lesedi 5P, drilling of the top-hole section of lateral well Lesedi 3A commenced.

 

The drilling program will continue over the coming weeks and into early 2019. Once all six wells for pods one and two have been drilled, these pods will be completed using a separate workover rig and surface production facilities will be installed. The wells will then begin production testing to de-water and lower the pressure in the coal seam to achieve gas flow. The Company will provide further updates as the drilling program progresses.

 

Other

In October 2018 the Company submitted a response to a 100MW CBM Request for Proposal from the Government of Botswana, as outlined in the market announcement on 10 October 2018. The Company is awaiting feedback in relation to this and looks forward to providing an update to the market as soon as possible.

 

The information communicated within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

 

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Tony Gilby, Managing Director

 

Solomon Rowland, General Manager

 

 

 

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke, Seamus Fricker

 

 

 

Shore Capital (Broker)

+44 (0) 207 408 4090

Jerry Keen, Toby Gibbs, Mark Percy

 

 

 

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

 

Company Information

Tlou Energy is focused on delivering Gas-to-Power solutions in Botswana and southern Africa to alleviate some of the chronic power shortage in the region. Tlou is developing projects using coal bed methane ("CBM") natural gas. Botswana has a significant energy shortage and generally relies on expensive imported power and diesel generation to fulfil its power requirements. As 100% owner of the most advanced gas project in the country, the Lesedi CBM Project, Tlou Energy provides investors with access to a compelling opportunity using domestic gas to produce power and displace expensive diesel and imported power.

 

The Company is listed on the Australian Securities Exchange, London's AIM market and the Botswana Stock Exchange and is led by an experienced Board, management and advisory team including individuals with successful track records in the CBM industry.

 

Since establishment, the Company has significantly de-risked the project in consideration of its goal to become a significant gas-to-power producer. The Company flared its first gas in 2014, holds a Mining Licence and nine Prospecting Licences, covering an area of ~8,300Km2 in total. The Lesedi and Mamba Projects already benefits from significant independently certified Contingent Gas Resources of ~3 trillion cubic feet (3C) and independently certified Gas Reserves of 41 billion cubic feet (2C) and ~426 billion cubic feet (3P).

 

The Company is planning an initial scalable gas-to-power project. Following successful implementation of this first scalable project, the Company looks forward to evaluating longer-term prospects for the delivery of electricity generated from CBM in Botswana to neighbouring countries. 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDLIFVELRLIFIT
Date   Source Headline
22nd Oct 20219:00 amRNSPrice Monitoring Extension
22nd Oct 20218:27 amRNSNotice of Annual General Meeting
20th Oct 20217:00 amRNSCorporate Presentation
19th Oct 20212:05 pmRNSSecond Price Monitoring Extn
19th Oct 20212:00 pmRNSPrice Monitoring Extension
18th Oct 202110:53 amRNS10MW Power Purchase Agreement Signed
18th Oct 20219:11 amRNSPower Purchase Agreement Signing Ceremony
21st Sep 20217:00 amRNSFinal Results
30th Jul 20212:33 pmRNSHeads of Agreement - Hydrogen Programme
30th Jul 20217:00 amRNSOperational Report - Quarter ending 30 June 2021
11th Jun 20214:40 pmRNSSecond Price Monitoring Extn
11th Jun 20214:35 pmRNSPrice Monitoring Extension
3rd Jun 20217:14 amRNSMrs. Linah Mohohlo
28th May 20217:00 amRNSHydrogen Strategy
26th Apr 20217:00 amRNSOperational Report - Quarter ending 31 March 2021
14th Apr 20217:01 amRNSTender awards for Transmission Line and Substation
9th Apr 20212:05 pmRNSSecond Price Monitoring Extn
9th Apr 20212:00 pmRNSPrice Monitoring Extension
30th Mar 20217:01 amRNSBoomslang Project – Environmental approval
24th Mar 20217:00 amRNSHolding(s) in Company
17th Mar 202111:06 amRNSSecond Price Monitoring Extn
17th Mar 202111:00 amRNSPrice Monitoring Extension
17th Mar 20217:00 amRNSResult of Placing
16th Mar 20214:35 pmRNSProposed placing to raise £2.6 million
8th Mar 20214:40 pmRNSSecond Price Monitoring Extn
8th Mar 20214:35 pmRNSPrice Monitoring Extension
4th Mar 20214:40 pmRNSSecond Price Monitoring Extn
4th Mar 20214:35 pmRNSPrice Monitoring Extension
1st Mar 20217:00 amRNSFinance progressing with key funding partner
26th Feb 20217:00 amRNSInterim Results
16th Feb 20217:00 amRNSTlou seeking Carbon Neutrality
28th Jan 20217:00 amRNSOperational Report Quarter Ended 31 December 2020
19th Jan 20217:00 amRNSMinistry Update On 100MW Tender
18th Dec 20207:00 amRNSTender timetable, finance, and project update
9th Nov 20204:32 pmRNSDirectors’ shareholdings
2nd Nov 20202:06 pmRNSSecond Price Monitoring Extn
2nd Nov 20202:00 pmRNSPrice Monitoring Extension
29th Oct 20207:00 amRNSOperational Report Quarter Ended 30 September 2020
28th Oct 20204:41 pmRNSSecond Price Monitoring Extn
28th Oct 20204:35 pmRNSPrice Monitoring Extension
28th Oct 20202:00 pmRNSPrice Monitoring Extension
27th Oct 20207:35 amRNSFunding update and Ministerial site visit
27th Oct 20207:00 amRNSResults of AGM and Chairman’s Address
26th Oct 202011:05 amRNSSecond Price Monitoring Extn
26th Oct 202011:00 amRNSPrice Monitoring Extension
23rd Oct 20204:40 pmRNSSecond Price Monitoring Extn
23rd Oct 20204:35 pmRNSPrice Monitoring Extension
23rd Oct 20202:05 pmRNSSecond Price Monitoring Extn
23rd Oct 20202:00 pmRNSPrice Monitoring Extension
23rd Oct 202011:05 amRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.