Tlou Energy Limited is pleased to announce that the Lesedi 4 production pod has successfully reached Critical Desorption Pressure ("CDP").

 

Highlights

· The Lesedi 4 pod has reached CDP;

· Short term gas flow test conducted at the Lesedi 3 pod yielding positive results;

· Dewatering of the Lesedi 3 & 4 pods is continuing according to plan.

 

Tlou's Managing Director, Mr Tony Gilby commented, "We are very pleased to have now reached CDP at both the Lesedi 3 and Lesedi 4 production pods. The short-term gas flow test at Lesedi 3 has also been positive, and with the primary objective of demonstrating a commercial gas flow rate, we look forward to further testing at both Lesedi 3 and 4. Further updates will be provided in due course."

 

Production Update

The Lesedi 4 pod has continued to dewater and CDP has now been reached successfully. CDP is the pressure that gas begins to come out of the coal after a careful dewatering process. Gas is now starting to come out of the coal and is steadily building pressure inside the closed casing.

 

A short-term gas flow test at Lesedi 3 took place after a significant gas pressure build-up inside the well casing. The result of this test is considered by the Company to represent a positive indication of the pod's potential. Post the short-term test, dewatering has continued with the plan to hold the water level just above the coal and continue to draw down pressure in the well allowing gas to flow in a controlled manner, ideally leading to a long-term gas flow from the Lesedi 3 pod.

 

Further updates on progress at the Lesedi project will be provided as operations develop.

 

The information contained within this announcement is deemed to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

 

****

 

For further information regarding this announcement please contact:

 

Tlou Energy Limited

+61 7 3012 9793

Tony Gilby, Managing Director

 

Solomon Rowland, General Manager

 

 

 

Grant Thornton (Nominated Adviser)

+44 (0)20 7383 5100

Samantha Harrison, Colin Aaronson, Harrison Clarke, Seamus Fricker

 

 

 

Shore Capital (Broker)

+44 (0) 207 408 4090

Jerry Keen, Toby Gibbs, Mark Percy

 

 

 

FlowComms Limited (Investor Relations)

+44 (0) 7891 677 441

Sasha Sethi

 

 

Company Information

Tlou Energy is focused on delivering Gas-to-Power solutions in Botswana and southern Africa to alleviate some of the chronic power shortage in the region. Tlou is developing projects using coal bed methane (CBM) natural gas. Botswana has a significant energy shortage and generally relies on imported power and diesel generation to fulfil its power requirements. As 100% owner of the most advanced gas project in the country, the Lesedi CBM Project, Tlou Energy provides investors with access to a compelling opportunity using domestic gas to produce power and displace expensive diesel and imported electricity.

 

The Company is listed on the Australian Securities Exchange, London's AIM market and the Botswana Stock Exchange and is led by an experienced Board, management and advisory team including individuals with successful track records in the CBM industry.

 

Since establishment, the Company has significantly de-risked the project in consideration of its goal to become a significant gas-to-power producer. The Company flared its first gas in 2014 and has a 100% interest over its Mining Licence and ten Prospecting Licences covering an area of ~9,300 Km2 in total. The Lesedi and Mamba Projects already benefit from significant independently certified 2P gas Reserves of ~41 BCF. In addition, 3P gas Reserves of ~427 BCF and Contingent Gas Resources of ~3,043 BCF provide significant additional potential.

 

The Company is planning an initial scalable gas-to-power project. Following successful implementation of this first scalable project, the Company looks forward to evaluating longer-term prospects for the delivery of electricity generated from CBM in Botswana to neighbouring countries.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDFKLLBKDFLBBQ
Date   Source Headline
22nd Oct 20219:00 amRNSPrice Monitoring Extension
22nd Oct 20218:27 amRNSNotice of Annual General Meeting
20th Oct 20217:00 amRNSCorporate Presentation
19th Oct 20212:05 pmRNSSecond Price Monitoring Extn
19th Oct 20212:00 pmRNSPrice Monitoring Extension
18th Oct 202110:53 amRNS10MW Power Purchase Agreement Signed
18th Oct 20219:11 amRNSPower Purchase Agreement Signing Ceremony
21st Sep 20217:00 amRNSFinal Results
30th Jul 20212:33 pmRNSHeads of Agreement - Hydrogen Programme
30th Jul 20217:00 amRNSOperational Report - Quarter ending 30 June 2021
11th Jun 20214:40 pmRNSSecond Price Monitoring Extn
11th Jun 20214:35 pmRNSPrice Monitoring Extension
3rd Jun 20217:14 amRNSMrs. Linah Mohohlo
28th May 20217:00 amRNSHydrogen Strategy
26th Apr 20217:00 amRNSOperational Report - Quarter ending 31 March 2021
14th Apr 20217:01 amRNSTender awards for Transmission Line and Substation
9th Apr 20212:05 pmRNSSecond Price Monitoring Extn
9th Apr 20212:00 pmRNSPrice Monitoring Extension
30th Mar 20217:01 amRNSBoomslang Project – Environmental approval
24th Mar 20217:00 amRNSHolding(s) in Company
17th Mar 202111:06 amRNSSecond Price Monitoring Extn
17th Mar 202111:00 amRNSPrice Monitoring Extension
17th Mar 20217:00 amRNSResult of Placing
16th Mar 20214:35 pmRNSProposed placing to raise £2.6 million
8th Mar 20214:40 pmRNSSecond Price Monitoring Extn
8th Mar 20214:35 pmRNSPrice Monitoring Extension
4th Mar 20214:40 pmRNSSecond Price Monitoring Extn
4th Mar 20214:35 pmRNSPrice Monitoring Extension
1st Mar 20217:00 amRNSFinance progressing with key funding partner
26th Feb 20217:00 amRNSInterim Results
16th Feb 20217:00 amRNSTlou seeking Carbon Neutrality
28th Jan 20217:00 amRNSOperational Report Quarter Ended 31 December 2020
19th Jan 20217:00 amRNSMinistry Update On 100MW Tender
18th Dec 20207:00 amRNSTender timetable, finance, and project update
9th Nov 20204:32 pmRNSDirectors’ shareholdings
2nd Nov 20202:06 pmRNSSecond Price Monitoring Extn
2nd Nov 20202:00 pmRNSPrice Monitoring Extension
29th Oct 20207:00 amRNSOperational Report Quarter Ended 30 September 2020
28th Oct 20204:41 pmRNSSecond Price Monitoring Extn
28th Oct 20204:35 pmRNSPrice Monitoring Extension
28th Oct 20202:00 pmRNSPrice Monitoring Extension
27th Oct 20207:35 amRNSFunding update and Ministerial site visit
27th Oct 20207:00 amRNSResults of AGM and Chairman’s Address
26th Oct 202011:05 amRNSSecond Price Monitoring Extn
26th Oct 202011:00 amRNSPrice Monitoring Extension
23rd Oct 20204:40 pmRNSSecond Price Monitoring Extn
23rd Oct 20204:35 pmRNSPrice Monitoring Extension
23rd Oct 20202:05 pmRNSSecond Price Monitoring Extn
23rd Oct 20202:00 pmRNSPrice Monitoring Extension
23rd Oct 202011:05 amRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.