Less Ads, More Data, More Tools Register for FREE

Pin to quick picksCornish Metals Regulatory News (TIN)

Share Price Information for Cornish Metals (TIN)

Share Price is delayed by 15 minutes
Get Live Data
110.00    1.50 (1.38%)
Bid:
108.00
Ask:
112.00
Spread: 4.00 (3.704%)
Market Cap: £138.02m
TIN Live PriceLast checked at - London Stock Exchange

Intraday Cornish Metals Share Chart

OPERATIONS UPDATE FOR THE SOUTH CROFTY TIN PROJECT

9 Feb 2026 07:00

RNS Number : 2155S
Cornish Metals PLC
09 February 2026
 

 

OPERATIONS UPDATE FOR THE SOUTH CROFTY TIN PROJECT

 

9 February 2026

Cornish Metals plc (AIM: TIN) ("Cornish Metals" or the "Company"), a mineral exploration and development company focused on advancing its wholly owned and permitted South Crofty tin project in Cornwall, United Kingdom, is pleased to provide an update on the progress of activities at South Crofty.

Highlights

Underground and surface works advancing in parallel, including:

· New Cook's Kitchen ("NCK") shaft mid-shaft pump station refurbishment completed

· NCK shaft refurbishment has resumed below the mid-shaft pump station and mine dewatering is ongoing

· Project schedule continues to be optimised, including bringing forward essential pre-production development at the 290-level to Q3 2026, providing access to the Roskear shaft for through-ventilation and drilling access

· With this refocused execution strategy, shaft refurbishment and mine dewatering are scheduled to be completed in early 2027. Guidance for first tin production is unchanged at mid-2028

· Process plant excavation is progressing according to plan, as are Front-End Engineering Design ("FEED") and Detailed Engineering for the plant

· Surface construction at Roskear shaft has commenced

· Installation of roof cladding for the Bartles Foundry stores and maintenance building is complete

· Mine Dry Phase 2 construction is progressing as planned, with completion targeted in Q1 2026

· Surface exploration drilling programme is planned to commence in March 2026 to target Mineral Resource expansion

Don Turvey, CEO of Cornish Metals commented:

"Activity levels at South Crofty continue to increase, with important milestones achieved both underground and on surface.

"We have optimised our development sequence by shifting our immediate focus to pre-production development of the 290-level. This mitigates certain execution risks for the project, improves schedule flexibility and maintains our guidance for first tin production in mid-2028. Further de-risking options are constantly being reviewed. With multiple workstreams advancing in parallel, we remain focused on disciplined execution as we continue to advance South Crofty towards production. The tin price is very well supported by a tight physical market, growing demand for technology applications and lagging supply, amplifying the need for new and secure mined tin supply that South Crofty can deliver."

Underground activities

Pump station, shaft refurbishment and mine dewatering: Refurbishment work on NCK's mid-shaft pump station (at approximately 360 metres below surface) is now complete following installation of the four new permanent pumps (see image 1). Further to the refurbishment of the pump station, and in addition to the initial scope of work, the Old Pool dam located at this level was restored for use. This brings significant advantages to the ongoing dewatering operation now and throughout the production years, with the dam functioning as a settling pond to remove suspended solids from the water prior to being pumped through the permanent pumps. This will serve to extend the operating life of the pumps and the water treatment plant.

Image 1: New Cook's Kitchen shaft pump station at approximately 360 metres below surface.

Optimised sequencing and bringing forward mine development: The projects and operations teams continually work towards optimising the execution schedule by prioritising essential workstreams and identifying opportunities to further de-risk the project. Pre-production development of the 290-level is being brought forward to commence in Q3 2026. This is essential as this level will provide access to Roskear shaft for through-ventilation and secondary egress. Ramp access will also be established at the 290-level (approximately 530 metres below surface) where mining is planned during early production.

The effect of this re-sequencing mitigates certain execution risks for the project, brings forward essential pre-production development, ventilation and access to underground exploration and infill drilling. With this optimised and refocused execution strategy, shaft refurbishment and mine dewatering are now scheduled to be completed in early 2027. Guidance for first tin production from South Crofty is unchanged at mid-2028.

25-level: Underground development at the 25-level (approximately 45 metres below surface) is underway and multiple drill and blast rounds have been completed (see image 2). Approximately 600 metres of lateral development is planned on this level, which is required to establish the sub-terranean skip discharge and rock handling facilities for the NCK shaft rock-hoisting system. The development training programme is ready and new starter miner training is now underway.

Image 2: 25-level underground development - jumbo drilling round.

Surface activities

Pre-concentration plant: The second phase of excavation for the new pre-concentration plant, focused on removing overburden and rock across the building footprint, is progressing according to plan (see image 3).

The FEED and Detailed Engineering contract for the processing facilities has been awarded to Ausenco with completion expected in Q4 2026, enabling construction of the pre-concentration plant to commence in Q1 2027.

Procurement of the main process equipment is expected to continue through 2026, with most key equipment planned to be ordered in the next 12 months.

 

Image 3: Pre-concentration plant excavation.

Roskear shaft: The first phase of surface work at Roskear shaft has been completed, and the earthworks are now underway (see image 4). Roskear shaft, located approximately 850 metres west of NCK shaft, is 610 metres deep with a 4.9 metre diameter and will be used for ventilation and secondary access for the mine. Local communities in the area have been contacted, with a drop-in session organised for early February to address any questions.

Image 4: Surface works at Roskear shaft.

Workshop and stores: Construction activities for the new workshop and stores facility located at the old Bartles Foundry site are progressing well with the roof panel installation now complete (see image 5) and the welfare area currently under construction. Due to the recent wet weather experienced in Cornwall, major works are now expected to be completed in April, from end-March previously.

Image 5: Workshop and stores building - roof panel installation complete.

Mine Dry: Phase 2 of the Mine Dry, which includes additional changing facilities and office space is progressing to plan and fit-out is currently underway. Completion is on track for March 2026.

Surface exploration drilling: A surface exploration drilling programme is scheduled to commence in March to explore the western edges of South Crofty's Roskear lodes, with the potential to intersect other lodes. The planned 2,400 metre drill programme seeks to extend the Inferred Mineral Resource of the Roskear lodes and demonstrate the potential to add to South Crofty's overall Mineral Resource inventory.

Other

The exploration and option deed entered into with Cornish Lithium Plc in January 2017, and extended through to 2025, was not extended for the upcoming year and has now been terminated.

 

ABOUT CORNISH METALS

Cornish Metals is a mineral exploration and development company that is advancing the South Crofty critical mineral project towards production. South Crofty:

· is a historical underground tin mine located in Cornwall, United Kingdom and benefits from existing mine infrastructure including multiple shafts that can be used for future operations;

· is the highest grade known tin Mineral Resource not in production with significant near-mine and regional Mineral Resource potential;

· is permitted to commence underground mining (valid to 2071), construct a new processing facility and for all necessary site infrastructure;

· will be a low environmental impact underground mine with zero surface tailings;

· would be potentially the first primary producer of tin in Europe or North America. Tin is a Critical Mineral as defined by the UK, American, and Canadian governments as it is used in almost all electronic devices and electrical infrastructure. Approximately two-thirds of the tin mined today comes from China, Myanmar and Indonesia;

· benefits from strong local community, regional and national government support with a growing team of skilled people, local to Cornwall, and could generate over 300 direct jobs;

· is an opportunity for a secure domestic supply of tin in the UK supporting a low carbon economy.

ENDS

 

 

Engage with us directly at our investor hub. Sign up at: https://investors.cornishmetals.com/link/P7bbor

 

For additional information please contact:

 

Cornish Metals

 

Fawzi Hanano

Emily Allhusen

investors@cornishmetals.com

info@cornishmetals.com

Tel: +44 1209 715 777

 

SP Angel Corporate Finance LLP

(Nominated Adviser)

 

 

Richard Morrison

Charlie Bouverat

Tel: +44 203 470 0470

 

Berenberg

(Joint Broker)

Jennifer Lee

Ivan Briechle

Tel: +44 20 3753 3040

 

 

Peel Hunt

(Joint Broker)

 

Ross Allister

David McKeown

 

Tel: +44 20 7418 8900

 

BlytheRay

(Financial PR)

Megan Ray

Said Izagaren

cornishmetals@blytheray.com

Tel: +44 207 138 3204

 

The Bartles Foundry project is part-funded by the UK Government through the UK Shared Prosperity Fund. Cornwall Council is responsible for managing projects funded by the UK Shared Prosperity Fund through the Cornwall and Isles of Scilly Good Growth Programme.

Market Abuse Regulation (MAR) Disclosure

The information contained within this announcement is deemed by the Company to constitute inside information pursuant to Article 7 of EU Regulation 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 as amended.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDUPUAUPUPQPGR
Date   Source Headline
4th Jun 20261:06 pmMFNCornish Metals: Results of 2026 Annual General Meeting
1st Jun 20267:00 amMFNCornish Metals: ROSKEAR EXPLORATION DRILLING UPDATE
27th May 20263:18 pmMFNCornish Metals: TR-1: Standard form for notification of major holdings
15th May 20267:00 amMFNCornish Metals: CORNISH METALS ANNOUNCES £52 MILLION CREDIT FACILITY WITH STRATEGIC SHAREHOLDERS
7th May 20266:00 amMFNCornish Metals: CORNISH METALS COMPLETES SUCCESSFUL PLACEMENT OF US$210 MILLION NORDIC BOND ISSUE
30th Apr 20267:56 amMFNCornish Metals: EXERCISE OF STOCK OPTIONS AND ISSUE OF EQUITY
22nd Apr 20268:42 amMFNCornish Metals: TR-1: Notification of major holdings
13th Apr 20267:00 amRNSPUBLICATION OF 2025 ANNUAL REPORT & NOTICE OF AGM
2nd Apr 20267:00 amRNSFINAL RESULTS FOR YEAR ENDED 31 DECEMBER 2025
9th Feb 20267:00 amRNSOPERATIONS UPDATE FOR THE SOUTH CROFTY TIN PROJECT
6th Feb 20261:32 pmRNSTR-1: Notification of major holdings
5th Feb 20267:00 amRNSLOI FROM EXPORT-IMPORT BANK OF THE UNITED STATES
2nd Feb 20267:00 amRNSAPPOINTMENT OF JOINT CORPORATE BROKERS
30th Jan 202610:59 amRNSEXERCISE OF STOCK OPTIONS AND ISSUE OF EQUITY
27th Jan 20262:14 pmRNSEXERCISE OF STOCK OPTIONS AND ISSUE OF EQUITY
26th Jan 20267:00 amRNSEXERCISE OF STOCK OPTIONS AND ISSUE OF EQUITY
18th Dec 20257:00 amRNSADMISSION TO AIM AND FIRST DAY OF DEALINGS
7th Jul 20081:35 pmRNSScheme of arrangement
1st Jul 20082:17 pmRNSRule 8.3- Tinopolis Plc
1st Jul 200811:13 amRNSDirector/PDMR Shareholding
30th Jun 20082:51 pmRNSInterim Results
16th Jun 20083:16 pmRNSScheme of arrangement
10th Jun 20082:58 pmRNSNotice of intention to delist
23rd May 20083:28 pmRNSOffer Document Posted
12th May 20081:56 pmRNSRule 8.3- Tinopolis Plc
12th May 20081:56 pmRNSRule 8.3- Tinopolis Plc
12th May 20081:46 pmBUSRule 8.3 - TINOPOLIS PLC
9th May 20087:01 amRNSOffer for Tinopolis PLC
31st Mar 20082:02 pmRNSAnnual Report and Accounts
20th Mar 20087:00 amRNSResult of AGM
29th Jan 20087:00 amRNSFinal Results
11th Oct 20077:00 amRNSTrading Statement
20th Aug 20078:52 amRNSAIM Rule 26 Disclosure
25th Jul 200711:21 amRNSTotal Voting Rights
25th Jun 20077:01 amRNSAcquisition
12th Jun 20077:01 amRNSInterim Results
4th May 20077:00 amRNSAcquisition
26th Mar 20076:21 pmRNSHolding(s) in Company-Amendmt
22nd Mar 20075:28 pmRNSHolding(s) in Company-Amendmt
21st Mar 20072:04 pmRNSDirector/PDMR Shareholding
21st Mar 200712:55 pmRNSHolding(s) in Company
21st Mar 200712:46 pmRNSHolding(s) in Company
19th Mar 20072:57 pmRNSContract Win
15th Mar 20071:06 pmRNSStatement on JAM
8th Mar 20072:11 pmRNSHolding(s) in Company
8th Mar 20071:05 pmRNSStatement re Contract Win
6th Mar 20073:24 pmRNSTransaction in Own Shares
2nd Mar 20075:12 pmRNSTransaction in Own Shares
27th Feb 20076:24 pmRNSHolding(s) in Company
31st Jan 20072:03 pmRNSTotal Voting Rights

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.