The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksTharisa Regulatory News (THS)

Share Price Information for Tharisa (THS)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 68.50
Bid: 68.00
Ask: 69.00
Change: 0.00 (0.00%)
Spread: 1.00 (1.471%)
Open: 68.00
High: 68.50
Low: 68.00
Prev. Close: 68.50
THS Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Q1 FY2019 Production Report 31 December 2018

11 Jan 2019 07:00

RNS Number : 7906M
Tharisa PLC
11 January 2019
 

Tharisa plc

(Incorporated in the Republic of Cyprus with limited liability)

(Registration number HE223412)

JSE share code: THA

LSE share code: THS

ISIN: CY0103562118

('Tharisa')

First quarter production report for the quarter ended 31 December 2018

 

Tharisa maintains its focus on optimising mining and processing performance

 

Salient features for the quarter ended 31 December 2018

§ PGM production of 33.6 koz (6E basis) and chrome concentrate production of 305.4 kt

‒ This represents quarter on quarter ('QoQ') decreases of 5.9% and 10.0% respectively, primarily as a result of reduced recoveries due to processing commissioning tailings

‒ Partially offset by PGM rougher feed grade improving by 7.4% for the quarter to 1.59 g/t and the Cr2O3 ROM feed grade improving by 1.1% to 18.5% for the period

§ Reduced recoveries driven by the processing of commissioning tailings to maintain plant throughput, following reduced availability of ROM material

‒ Decline in QoQ mining as a result of reduced availability of equipment, particularly in the drill and blast operations

‒ Ongoing planned maintenance programme to return the mining fleet to OEM standards

‒ Good progress on implementing the maintenance strategy to achieve planned mining rates

‒ Additional drilling capacity being added and new excavator being commissioned to address back‐log in waste extraction

§ From the end of January 2019, 24 hour continuous mining operations on the East Pit to increase capacity by c.15%

§ The average PGM contained metal basket price for the first quarter was US$983/oz (ZAR14 050/oz), an increase of 5.9% in US$ terms from the last quarter and 7.5% in ZAR terms

§ Sound safety performance with LTIFR of 0.17 per 200 000 man hours worked (0.18 per 200 000 man hours in Q4 2018)

§ FY2019 production guidance revised to between 150 koz and 160 koz of PGMs (6E basis) and 1.4 Mt to 1.5 Mt of chrome concentrates

Commenting on the production results, Tharisa CEO Phoevos Pouroulis, said:

"Although we had planned for a slower Q1 in terms of mining production, we did not anticipate the full impact that blending tailings material would have on our overall recoveries. We will revert back to processing fresh run of mine material from mid- January and will achieve our targeted recoveries. We are addressing the operational performance of the mining division with particular reference to equipment availability and utilisation through pro-active maintenance and enhancing the capacity of our drill and blast operations. We remain fully committed to our Vision 2020 targets and we are confident that the processes currently underway will see an improved performance in the months to come. "

Safety

Safety is one of Tharisa's core values and Tharisa continues to strive for zero harm at its operations. An LTIFR of 0.17 per 200 000 man hours worked was recorded at the end of the quarter.

Production update

The production update for the quarter ended 31 December 2018 is as follows:

Quarter ended 31 Dec 2018

Quarter ended 30 Sept 2018

QoQ movement %

Quarter ended 31 Dec 2017

Year ended 30 Sept 2018

Reef mined

kt

1 090.6

1 179.7

(7.6)

1 245.3

4 875.0

Stripping ratio

m3: m3

6.7

7.2

(6.9)

7.8

7.9

Reef milled

kt

1 192.5*

1 216.7

(2.0)

1 310.2

5 105.3

PGM flotation feed

kt

901.3

892.8

1.0 

959.6

3 718.1

PGM rougher feed grade**

g/t

1.59

1.48

7.4 

1.49

1.51

PGM recovery

%

76.5

84.1

(9.0)

84.3

84.1

6E PGMs produced

koz

33.6

35.7

(5.9)

38.8

152.2

Average PGM contained metal basket price

US$/oz

983

928

5.9

865

923

Average PGM contained metal basket price

ZAR/oz

14 050

13 067

7.5

11 827

12 038

Cr2O3 ROM grade**

%

18.5

18.3

1.1 

18.1

18.2

Chrome recovery

%

58.9

64.5

(8.7)

65.5

66.0

Chrome yield

%

25.6

27.9

(8.2)

27.9

28.4

Chrome concentrates produced (excluding third party)

kt

305.4

339.2

(10.0)

365.8

1 448.0

Metallurgical grade

kt

233.4

240.3

(2.9)

277.7

1 080.3

Specialty grades

kt

72.0

98.9

(27.2)

88.1

367.7

Third party chrome production

kt

52.2

56.0

(6.8)

52.8

221.8

Metallurgical grade chrome concentrate contract price

US$/t CIF China

164

164

179

186

Metallurgical grade chrome concentrate contract price

ZAR/t CIF China

2 311

2 313

(0.1)

2 426

2 415

Average exchange rate

ZAR:US$

14.3

14.1

1.4 

13.6

13.1

* includes the processing of 75.9 kt of commissioning tails through the processing plants

** mined ore only

Mining

Tharisa's mining division mined 1 090.6 kt of ROM during the quarter, a 7.6% decrease QoQ. A total of 2.1 Mm3 of over- and inter- burden was mined for the quarter. The stripping ratio of 6.7 on a m3:m3 basis remained below the LOM average of 9.5. The decline in QoQ mining was mainly due to reduced availability of equipment, particularly in the drill and blast operations and there were therefore delays in opening up adequate waste and reef benches to enable volume extraction. This was, in part, a result of an ongoing planned maintenance programme to return the mining fleet to OEM standards.

Several key initiatives are underway as the mining division focusses on improving its performance:

‒ three additional drill rigs are currently on site as the efficiencies of the drill and blast operations are addressed. This is essential to achieving the targeted stripping ratio, and enables us to drill in excess of 100 km per month which will provide capacity to produce in excess of 5.2 Mt and achieve the Vision 2020 target of 5.6 Mt

‒ implementation of the necessary preventative maintenance systems to drive equipment availability and utilisation increases

by the end of January 2019, mining of the East Pit will be moved to 24 hour continuous operations (currently 20 hour operation) to mirror the processing operations, thereby increasing capacity by some 15%

‒ new Caterpillar 6050 excavator commissioned to increase waste removal capacity as part of the planned asset replacement programme

In spite of the lower mined production volumes, the grade control initiatives have yielded positive results, with the PGM rougher feed grade improving by 7.4% for the quarter to 1.59 g/t and the Cr2O3 ROM feed grade improving by 1.1% to 18.5% for the period.

Processing

The reduced level of ROM material was supplemented with the re-processing of 75.9 kt commissioning tailings to maintain plant throughput, comprising 6.4% of combined mill throughput, allowing for a total of 1 192.5 kt of reef to be milled in the first quarter, a 2.0% decrease from the last quarter of FY2018. The processing of commissioning tailings negatively impacted on the overall production and recoveries for the quarter, with PGM production decreasing by 5.9% to 33.6 koz (6E basis), a recovery of 76.5%, and chrome concentrate production decreasing by 10.0% to 305.4 kt, a recovery of 58.9%. The production of specialty grade chrome concentrates decreased by 27.2%, from 98.9 kt in the last quarter of FY2018 to 72.0 kt.

The chrome production for the quarter from the Lonmin K3 chrome plant was 52.2 kt, a reduction of 6.8% from the previous quarter. This was caused by lower throughput due to the December holiday shut down.

Market update

The average PGM contained metal basket price for the first quarter was US$983/oz (ZAR14 050/oz), an increase of 5.9% in US$ terms from the last quarter and 7.5% in ZAR terms.

The average metallurgical grade chrome concentrate price was US$164/t (ZAR2 311/t), which remained flat in US$ terms and was marginally lower in ZAR terms for the quarter.

Specialty chrome concentrates, which accounted for 23.6% of Tharisa's quarterly chrome production, continued to attract a significant premium to metallurgical chrome concentrate prices.

Outlook

In light of the Q1 performance, Tharisa updates its FY2019 production guidance to output of between 150 koz and 160 koz of PGMs (6E basis) and 1.4 Mt to 1.5 Mt of chrome concentrates, of which 25% will be speciality grade chrome concentrates. The Tharisa team will continue to implement the Vision 2020 projects during FY2019, which will ensure that Tharisa delivers 200 koz of PGMs and 2.0 Mt of chrome concentrates in 2020 from the Tharisa Mine.

The above information has not been reported on or reviewed by Tharisa's auditors.

Paphos, Cyprus

11 January 2019

JSE Sponsor

Investec Bank Limited

Financial PR contacts:

Bobby Morse / Augustine Chipungu

+44 020 7466 5000

tharisa@buchanan.uk.com 

Broker contacts:

Peel Hunt LLP (UK Joint Broker)

Ross Allister / James Bavister / David McKeown

+44 207 7418 8900

BMO Capital Markets Limited (UK Joint Broker)

Jeffrey Couch / Thomas Rider

+44 020 7236 1010

Berenberg (UK Joint Broker)

Matthew Armitt / Sara MacGrath

+44 20 3207 7800

Nedbank Limited (acting through its Corporate and Investment Banking division) (RSA Broker)

Shabbir Norath / Reginald Demana

+27 11 295 6575

Investor relations contacts:

Daniel Thöle / Ilja Graulich

+27 61 400 2939 / +27 83 604 0820

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLBSGDBUXBBGCG
Date   Source Headline
13th Apr 20217:00 amRNSProduction Report Q2 FY2021
1st Apr 20217:00 amRNSTotal Voting Rights
23rd Mar 20217:00 amRNSBlock listing Interim Review
16th Mar 20211:00 pmRNSMajor holdings
3rd Mar 20217:00 amRNSInvestor Presentation
1st Mar 20211:30 pmRNSTotal Voting Rights
23rd Feb 20211:00 pmRNSDirector/PDMR Shareholding
15th Feb 20219:00 amRNSDirector/PDMR Shareholding
11th Feb 20217:00 amRNSAGM Statement, results of voting and dividend rate
1st Feb 202110:00 amRNSTotal Voting Rights
21st Jan 20217:00 amRNSDirectorate Change and notification regarding AGM
20th Jan 202112:00 pmRNSSalene Chrome Zimbabwe Option extended
12th Jan 20217:00 amRNSProduction Report Q1 FY2021
21st Dec 20207:00 amRNSDealings by directors of major subsidiaries
18th Dec 20207:00 amRNSMailing of 2020 Annual Report and Notice of AGM
17th Dec 20207:00 amRNSDealings by director of a major subsidiary
14th Dec 20208:04 amRNSTharisa Mine concludes 4-year wage agreement
9th Dec 20207:27 amRNSTharisa Investor Presentation via Investor Meet
30th Nov 20207:00 amRNSAnnual Financial Report FY2020
26th Nov 20207:00 amRNSAnnual results announcement FY2020 Call details
24th Nov 20207:00 amRNSTrading statement – Results for FY2020
13th Oct 20207:00 amRNSNotification of major holdings
8th Oct 20207:00 amRNSTharisa Q4 FY2020 Production Report
1st Oct 20207:00 amRNSTotal Voting Rights
21st Sep 20207:00 amRNSIssue of equity and voting rights
18th Sep 20201:00 pmRNSDealings in securities by directors and PDMRs
17th Sep 20202:00 pmRNSDirectorate Change
22nd Jul 20201:30 pmRNSDirector/PDMR Shareholding
13th Jul 20209:00 amRNSDealing in securities by an NED of Tharisa
9th Jul 20207:00 amRNSProduction report Q3 FY2020
30th Jun 20207:00 amRNSDirector/PDMR Shareholding
21st May 20207:00 amRNSHalf-year Report
20th May 20202:00 pmRNSInterim results release and presentation dial-in
9th Apr 20207:00 amRNSQ2 FY2020 Production Report
27th Mar 20208:00 amRNSUpdate on lockdown due to COVID-19
24th Mar 20202:00 pmRNSSouth African government imposed lockdown COVID-19
2nd Mar 20207:00 amRNSTransfer of treasury shares & total voting rights
19th Feb 20208:00 amRNSNotification of major holdings
30th Jan 20207:00 amRNSResult of AGM and dividend conversion rates
16th Jan 202012:00 pmRNSAppointment of non-executive director
10th Jan 20207:00 amRNSQ1 production report for the quarter ended 31Dec19
30th Dec 20197:00 amRNSBlock listing six monthly return 30 December 2019
19th Dec 20197:00 amRNSNo change statement and Notice of AGM
28th Nov 20197:00 amRNSFinal Results
27th Nov 20193:00 pmRNSFinal results for FY2019 Conference call details
22nd Nov 20197:00 amRNSTrading statement - results for FY2019
22nd Oct 20197:00 amRNSSpecial Economic Zone to benefit Karo Zimbabwe
9th Oct 20197:00 amRNS4th Quarter and full year production report FY2019
1st Oct 20197:00 amRNSTransfer of treasury shares & total voting rights
9th Sep 201912:00 pmRNSDealings in securities by directors and PDMRs

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.