Quarterly progress update

12 Jan 2018 07:00

RNS Number : 6777B
Sirius Minerals plc
12 January 2018
 

 

12 January 2018

 

Sirius Minerals Plc

Quarterly progress update

§ The project remains on track to deliver first polyhalite and commercial production on time and on budget

§ Wilmar offtake agreement signed

§ D-walling progress slightly behind schedule

§ Review of 2017 milestones demonstrates good progress

 

Sirius Minerals Plc ("Sirius" or the "Company") provides its latest quarterly progress update.

Safety

The project recorded one lost time incident during the period. As the organisation expands the Company is proactively engaging with all staff and construction partners to communicate its safety culture and Company values.

Cost and schedule

The project remains on track to deliver first polyhalite and commercial production on time and on budget. Current diaphragm walling ("D-walling") activities are approximately two months behind schedule following some delays in commissioning the D-walling equipment and some adverse weather conditions during the latter stages of the quarter. The Company is confident that this small loss of time will be recovered over the remainder of the project schedule.

Permitting

The conditions clearing process continues to function smoothly with all relevant conditions satisfied for the ongoing scopes of works at all locations.

The application for 'minor material' amendments to the original planning application was unanimously approved by the local planning authority. This approval covered the previously highlighted changes to the foreshaft and surface layout designs at the Woodsmith site.

Site preparation

The site preparation scope of work at the Woodsmith and Lockwood Beck sites is substantially complete. A number of minor activities remain ongoing and will be completed in 2018. At Wilton, site clearance and the removal of vegetation is underway to enable construction activities to commence.

Geotechnical investigation

The production shaft geotechnical borehole, SM14B, is nearing the polyhalite horizon with drilling and testing complete to 1,329m. Geotechnical and hydrogeological work continues to support and refine parameters used in the shaft design and construction methodology.

The mineral transport system ("MTS") seismic survey is nearing completion and continues to provide excellent quality data to support engineering activities. MTS drilling is ongoing with the majority of the scope completed. Over 2,500m of core has been recovered, logged and sub-sampled to confirm the geotechnical parameters required for detailed MTS design. Current activities are focussed on the Wilton Portal and the MTS caverns at Lockwood Beck.

Shaft sinking

D-walling activities are progressing smoothly with three rigs operating on the services shaft. Six panels are in progress or have been completed with a total of 48 panels required to complete the foreshaft for the services shaft. The D-walling scope of work is approximately two months behind schedule due to delays in commissioning and adverse weather conditions across the quarter. The Company is confident of recovering the lost time over the remainder of the project schedule.

Once D-walling activities are completed, excavation and fit-out of the foreshafts and surface basements will commence. Preparation for these activities is progressing well, including contractor procurement and engineering.

The Company is still working to finalise the shaft sinking contract. This activity is the key focus of management's attention and all avenues are being explored to ensure a shaft sinking contract will be executed as soon as possible and the impact on the overall construction programme is minimized.

Other project activities

Procurement activities for the MTS are well advanced with a view to commencing initial construction activities in 2018. The Company is working closely with a number of parties in relation to the commercial terms associated with the tunnelling scope of work.

Front end engineering and design work for the port and materials handling facility ("MHF") is now underway and Sirius is engaged with a number of potential delivery partners. The Company is also pursuing port outsourcing opportunities with potential partners and this process is progressing well.

Commercial activities across all scopes of work are scheduled to be substantially complete by the middle of 2018 in order to facilitate the completion of the stage 2 financing process.

Agronomy, sales and marketing

During the quarter, the Company announced the signing of a binding take-or-pay offtake agreement with Wilmar International for the use and resale of POLY4 exclusively in South East Asia. Wilmar is a leading global agribusiness with the capacity to reach a diverse customer base through well-established, trusted relationships.

The Company is continuing negotiations with a variety of potential customers in multiple regions to expand its commercial reach into new markets. POLY4 continues to gain market acceptance globally from both industry participants and experts.

The Company has initiated 28 new agronomy trials. The overall programme now encompasses over 260 trials on 32 crops in 17 different countries.

Corporate

Activities relating to the stage 2 financing process will gather momentum as the coming year unfolds. The Company is intending to re-engage with the bank group during the first quarter by issuing a comprehensive due diligence information package. This is the first major milestone in the timetable which is aiming to have commitments in place during the second half of 2018.

 

Performance against milestones for 2017

The Company set out key milestones for 2017 at the beginning of that year. Performance against these milestones is summarised below.

Complete site preparation works at Woodsmith Mine and Lockwood Beck

Status: Complete

• Site access works complete.

• Haul road, drainage, concrete batch plant and general infrastructure complete.

• Site welfare facilities installed and operational.

• MTS and reinjection pads complete.

 

Substantially complete D-wall installation for production and service shafts

Status: Partially complete - approximately two months behind schedule

• Scope of D-walling activities was substantially increased with the change to wider foreshafts.

• Progress on production shaft has been deferred to allow for the SM14B drilling programme.

• Delay is estimated by comparing progress against like for like scope (total m2 of panels).

 

Progress design activities for MTS and front-end design for harbour and MHF

Status: Complete

• MTS scope of work at advanced commercial discussion stage with multiple contractors.

• Design scope for MHF and overland conveyor complete and out for commercial tender.

• Port outsourcing opportunities are being negotiated in parallel with internal design and build process.

 

Execute incremental offtake agreements

Status: Partially complete

• Offtake agreement signed with Wilmar International for South East Asia. Seven years, peaking at 0.75 million tonnes per annum.

• Commercial discussions for other key regions (Europe, Brazil, China, Africa) progressing well.

• On track for stage 2 financing requirements.

 

Expand breadth and depth of the agronomy programme

Status: Complete

• 260 trials on 32 crops in 17 countries.

• Over 60 new trials commenced during the period.

 

Seek a Premium Listing and move to the Main Board

Status: Complete

• Premium Listing obtained in Q2.

• FTSE 250 inclusion obtained at half year index re-weighting.

• 2017 total shareholder return of 24% vs 14% for the FTSE 250.

 

Preparation work for stage 2 financing execution in late 2018

Status: Complete

• Key advisors appointed and due diligence programme well advanced.

• In principle agreement reached with IPA in relation to structure and financing process.

 

 

For further information, please contact:

Sirius Minerals Plc

Investor Relations Manager

Tristan Pottas

Email: ir@siriusminerals.com

Tel: +44 845 524 0247

Media enquiries

Tavistock

Jos Simson

 

Tel: +44 20 7920 3150

 

About Sirius Minerals Plc

Sirius Minerals Plc is focused on the development of the Woodsmith Mine, which will access the world's largest and highest grade polyhalite deposit located in North Yorkshire, United Kingdom. Polyhalite is a unique multi-nutrient fertilizer, which can be used to increase balanced fertilization around the world. Sirius Minerals' shares are traded on the Premium List of the London Stock Exchange. Its shares are also traded in the United States on the OTCQX through a sponsored ADR facility. Further information on the Company can be found at: www.siriusminerals.com.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLFFSILRILLIT
Date   Source Headline
31st Oct 20187:00 amRNSTotal Voting Rights
4th Oct 20184:30 pmRNSReplacement: Issue of Shares
4th Oct 20183:21 pmRNSIssue of shares
27th Sep 20187:00 amRNSQuarterly progress update
27th Sep 20187:00 amRNSHalf year results for period ended 30 June 2018
17th Sep 20187:00 amRNSSupply Agreement and Investment in South America
14th Sep 20187:03 amRNSRoyalty financing investment update
6th Sep 20187:00 amRNSProcurement and capital estimate update
31st Jul 20187:00 amRNSPartnership with Archer Daniels Midland Company
31st Jul 20187:00 amRNSTotal Voting Rights
26th Jul 20189:47 amRNSExercise of options
20th Jul 20187:00 amRNSPOLY4 Supply Agreements - China
12th Jul 201811:43 amRNSBlock listing application
9th Jul 20187:00 amRNSRBT materials handling agreement and lease
3rd Jul 201811:59 amRNSBlocklisting Six Monthly Return
2nd Jul 20187:00 amRNSQuarterly progress update
29th Jun 20187:00 amRNSTotal Voting Rights
26th Jun 20183:41 pmRNSDirector/PDMR Shareholding
20th Jun 20187:00 amRNSPOLY4 Supply Agreement - Nigeria
18th Jun 201810:47 amRNSExercise of options
12th Jun 20182:34 pmRNSDirector/PDMR Shareholding
8th Jun 201812:20 pmRNSDirector Declaration
31st May 20183:22 pmRNSResult of AGM
30th Apr 20184:32 pmRNSTotal Voting Rights
27th Apr 20181:25 pmRNSHolding(s) in Company
23rd Apr 20183:37 pmRNSAnnual Financial Report
20th Apr 20184:10 pmRNSApplication to issue shares
17th Apr 20187:14 amRNSResults of conversion of convertible bonds
11th Apr 20185:51 pmRNSInvitation for conversion of convertible bonds
3rd Apr 201811:11 amRNSDirector Declaration
29th Mar 20187:00 amRNSQuarterly progress update
6th Mar 20187:00 amRNSFull Year 2017 Results
1st Mar 20187:00 amRNSNotice of Full Year 2017 Results
28th Feb 20184:30 pmRNSTotal Voting Rights
14th Feb 20187:00 amRNSSirius signs shaft sinking contract with DMC
6th Feb 20187:00 amRNSIssue of shares
24th Jan 20183:51 pmRNSDirector Declaration
12th Jan 20187:00 amRNSQuarterly progress update
2nd Jan 20185:08 pmRNSBlock listing Six Monthly Return
26th Oct 20177:00 amRNSPOLY4 Offtake Agreement - South East Asia
29th Sep 20177:00 amRNSQuarterly development update
5th Sep 20174:30 pmRNSDirector/PDMR Dealing
4th Sep 20177:00 amRNSHolding(s) in Company
16th Aug 20177:00 amRNSHalf year results for period ended 30 June 2017
3rd Aug 20179:32 amRNSHolding(s) in Company
31st Jul 20171:00 pmRNSTotal voting rights
29th Jun 20172:36 pmRNSResults of Annual General Meeting
29th Jun 20177:01 amRNSQuarterly update for Q2 2017
29th Jun 20177:00 amRNSBlock listing application
26th Jun 20177:00 amRNSEmployee incentive awards & Director shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.