PEA for the proposed Tongo-Tonguma Mine

5 Oct 2016 09:35

RNS Number : 7551L
Stellar Diamonds PLC
05 October 2016
 

 

 

 

 

 

 

NOT FOR DISTRIBUTION IN THE UNITED STATES OR FOR DISSEMINATION TO US NEWS WIRE SERVICES.

 

5 October 2016

 

AIM: STEL

Stellar Diamonds plc

("Stellar" or the "Company")

 

Preliminary Economic Assessment for the proposed Tongo-Tonguma Mine

 

Further to the announcement on 22 August 2016 on the proposed transaction ("the Transaction") (the "Transaction Announcement") between Stellar Diamonds plc ("Stellar" or "the Company") and Octea Mining ("Octea") to combine their adjacent Tongo and Tonguma diamondiferous kimberlite dyke properties in eastern Sierra Leone, Stellar announces the results of an independent Preliminary Economic Assessment ("PEA") for the combined mining project ("the Project").

 

The PEA demonstrates a financially robust and high margin 21 year life of mine over an initial resource of 4.5 million carats. The PEA also recognises considerable upside exists from additional high-grade kimberlite dykes on the properties which are not yet categorized into resource.

 

Highlights: 

· Estimated pre-tax Project NPV(10) and IRR of $172 million and 49% respectively

· Projected life of mine Project revenues of $1,518m with operating costs of $847 million

· Estimated operating margin of 50% over the life of mine

· First production expected within 12 months, ramping up to over 200,000 carats p.a. in 4th year

· Expected Capex of $31.8 million in first two years (including 15% contingency)

· Estimated 3.96 million carats recoverable from the initial 4.5 million carats resource at a +1.18mm cut-off

· Recoverable diamond grades and values for first three kimberlites to be mined of:

o Kundu: 260cpht and $209 per carat ($543 per tonne)

o Lando: 220cpht and $209 per carat ($440 per tonne)

o Tongo: 100cpht and $310 per carat ($310 per tonne)

· Exploration target of up to 8 million carats in addition to existing resource

 

Chief Executive Karl Smithson commented:

"The PEA of the combined Tongo-Tonguma mine demonstrates robust financial returns for a modest capital requirement and supports the Board's decision to pursue this strategic acquisition. Three kimberlite dykes, Kundu, Lando and Tongo are contained within the mine plan and have compellingly high diamond grades and values and together support a long life of mine. We are further encouraged by the potential which exists to significantly increase the resource base by bringing a number of additional high grade kimberlites that have been discovered to date on both licences into the long term resource base.

 

"We continue to make good progress with the legal and other due diligence processes that are required to complete the Transaction and will provide further updates in due course."

 

Resource Statements

Independent industry consultants Paradigm Project Management ("PPM") and SRK Consulting ("SRK"), based in South Africa ("the Consultants"), prepared the PEA on the basis of an underground mining scenario only. The consultants utilised independent resource statements prepared for Stellar by CAE Mining, in respect of Tongo Dyke-1, and Mineral Services Canada, in respect of Tonguma. Only 3 kimberlites dykes of a total of 11 on the properties (4 at Tongo and 7 at Tonguma) have been categorized as resource to date, being Tongo Dyke-1, Kundu and Lando for a total of 2.2 million tonnes and 4.50 million carats at a +1.18mm cut off.

Inferred Resources (by Mineral Services Canada and CAE Mining)

Dyke

Classification

cut-off

Depth (m)

Tonnes (mT)

Grade (cpt)

Carats (mcts)

Tonguma

Kundu

inferred

+1.18mm

20 - 200

0.5

2.9

1.5

Tonguma

Lando

inferred

+1.18mm

20 - 200

0.8

2.5

2.1

Tongo

Dyke-1

inferred

+1.18mm

0 - 300

0.9

1.0

0.9

Total

inferred

2.2

4.50

 

A further four dykes have been drilled out at Tonguma and along with certain sections of Lando and Kundu are classified by Mineral Services Canada as "exploration target" which offers a mid-range total of 5.6 million tonnes and potential for a further 7.96 million carats for the Project. Although it can't be guaranteed that further exploration will result in this exploration target becoming a mineral resource, the Directors consider that this target demonstrates significant upside to the overall resource base of the Project and it is the intention to bring the "exploration target" into the JORC resource category in due course through further drilling and sampling.

 

Exploration Target at Tonguma (by Mineral Services Canada)

Dyke

Cut-off

Depth (m)

Tonnes Range (mT)

Grade range (cpt)

Mid range tonnage (mT)

Mid range Grade (cpt)

Carats (mcts)

Kundu

+1.18mm

200 - 500, and 3 segements 20 - 200m

0.8 - 1.5

1.7 - 4.0

1.15

2.9

3.28

Lando

+1.18mm

200 - 500, and 3 segements 20 - 200m

0.6 - 1.1

1.5 - 3.5

0.85

2.5

2.13

Kpandebu

+1.18mm

0 - 500m

0.2 - 0.4

0.9 - 2.1

0.3

1.5

0.45

Panguma

+1.18mm

0 - 500m

1.0 - 1.9

0.9 - 2.0

1.45

1.5

2.10

Tongo

0 - 500

0.9 - 1.9

no info.

1.4

Seleima

0 - 500

0.3 - 0.5

no info.

0.4

5.55

7.96

 

Recoverable Resources

In preparing the mine plan and financial model for the PEA the Consultants used the total diamond resource of 5mcts and applied a standard +1.18mm plant cut off across all three dykes and also applied a recovery factor which could be expected during the mining and processing of the kimberlite ore. This resulted in an estimate of 3.96 million carats of recoverable resource during the life of mine from the total Project resource of 4.5 million carats. Diamond values range from $209/ct for Kundu and Lando to $310/ct for Tongo Dyke-1.

 

Recoverable Resources (by PPM/SRK PEA)

Dyke

Classification

cut-off

Depth (m)

Tonnes (mT)

Grade (cpt)

Carats (mcts)

Diamond Value $/ct

Tonguma

Kundu

inferred

+1.18mm

20 - 200

0.5

2.6

1.30

209

Tonguma

Lando

inferred

+1.18mm

20 - 200

0.8

2.2

1.76

209

Tongo

Dyke-1

inferred

+1.18mm

20 - 300

0.9

1.0

0.90

310

Total

inferred

2.2

3.96

 

Underground Mining

The underground mine plan is currently configured as a series of declines from surface at Kundu, Lando and Tongo. The declines will be 4m x 4m in cross section and will be developed at an angle of 8-degrees. Mining levels will be interspaced at 35m depth with the first levels being developed at 40m below surface. Based on the current resource models, Tongo will have a planned 11 levels, Lando 10 levels and Kundu 5 levels during the 21 year life of mine. The ore bodies will be accessed by 2m x 2m drives and cross-cuts into stopes that are mined by traditional overhand shrinkage stoping mining methods, with the ore being drawn from access points and transported on underground locos and tipped into bins on an ore pass system. These ore bins will feed haulage trucks that will transport the ore to surface and onto the processing plant. The existing 50tph processing plant at Octea's Koidu Mine is to be relocated to Tonguma and be further upgraded to serve as the processing plant for the new mine. This will save considerable time in getting the Project to production.

 

Financial Model

The financial model prepared by PPM for the underground mining study is based on mining the 3.90mcts of the 3.96mcts recoverable resource at Tongo, Kundu and Lando and does not include any of the 7.96mcts "exploration target" carats which may be brought into a future resource estimation.

 

The initial two year capital requirement to bring the mine into production is estimated to be $31.8 million (including a 15% contingency) and $90 million over the 21 year life of mine. Based on the life of mine project costs ($847 million) and revenues ($1,518 million) the financial model demonstrates an NPV(10) of $172 million and IRR of 49% on a pre-tax basis. Based on the un-escalated operating costs and carat recovery over the life of mine, the cost per carat at the present time is estimated at $115.3 per carat against the un-escalated average diamond price (across all three kimberlites) of $228.6 per carat, giving an operating margin of 49.6%.

 

Sensitivity Analysis

Sensitivity analyses were conducted by flexing by +25% to -25% the three key parameters of revenue, capital expenditure and operating costs around the base case $172m pre-tax NPV. This analysis confirms that the Project is financially robust. A graph of the sensitivity analysis can be seen at the following link;

 

http://stellar-diamonds.com/wp-content/uploads/2016/10/sensitivity_analysis.png

 

A summary of the financial model as prepared by PPM and SRK are given in the table below:

 

Tongo Dyke-1

Tonguma Kundu Dyke

Tonguma Lando Dyke

Pre-Tax Model

Life of mine (years)

21

Total tonnes mined

6,062,613

Carats recovered

3,905,490

Average recovered/diluted grade (cpht)

64.4

Years 1-2 capital cost (US$m)

31.8

Cost per carat (US$)

115.3

Revenue per carat (US$) average

228.6

Operating margin %

49.6

Life of mine gross revenues (US$m)

1,518

Life of mine working costs (US$m)

847.1

Life of mine net cash inflows (US$m) after capex

580.3

Net Present Value (at 10% discount rate) (US$m)

172

IRR

49%

 

The Tongo-Tonguma PEA report will be available for download from the Company's website www.stellar-diamonds.com 

 

Transaction Update

Work on the Transaction continues with ongoing legal and due diligence work. The Competent Persons Report on the Project will be announced in due course and marketing to new investors and existing shareholders will then commence. By virtue of the Transaction being classified as a reverse takeover under the AIM Rules for companies, trading in the Company's shares on AIM will remain suspended until either an admission document is published or the Company announces its or Octea's withdrawal from the Transaction. 

 

The Transaction, if completed, would result in Stellar having a 75% economic interest in the Project following, inter alia, preferential repayment of the initial investment made by Stellar and payment of certain revenue royalty payments as outlined in the Transaction Announcement. Shareholders should note that the Transaction remains subject to a number of conditions, including inter alia, publication of an admission document and shareholder approval.

 

Review by competent person

This announcement has been reviewed by Karl Smithson, Chief Executive of Stellar, a qualified geologist and Fellow of the Institute of Materials, Metals, Mining, with 27 years' experience.

 

This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014.

 

Caution regarding forward looking statements

Certain statements in this announcement, are, or may be deemed to be, forward looking statements. Forward looking statements are identified by their use of terms and phrases such as ''believe'', ''could'', "should" ''envisage'', ''estimate'', ''intend'', ''may'', ''plan'', ''potentially'', ''will'' or the negative of those, variations or comparable expressions, including references to assumptions. These forward looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the Company's future growth, results of operations, performance, future capital and other expenditures (including the amount, nature and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors.

 

A number of factors could cause actual results to differ materially from the results discussed in the forward looking statements including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets, reliance on key personnel, uninsured and underinsured losses and other factors, many of which are beyond the control of the Company. Although any forward looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions, the Company cannot assure investors that actual results will be consistent with such forward looking statements. Accordingly, readers are cautioned not to place undue reliance on forward looking statements. Subject to any continuing obligations under applicable law or any relevant AIM Rule requirements, in providing this information the Company does not undertake any obligation to publicly update or revise any of the forward looking statements or to advise of any change in events, conditions or circumstances on which any such statement is based.

 

About Stellar Diamonds plc

Stellar is an AIM listed (AIM: STEL) West African focused diamond company with projects at the trial mining and mine development stages in Guinea and Sierra Leone.

 

** ENDS **

 

For further information contact the following or visit the Company's website at www.stellar-diamonds.com.

 

Karl Smithson, CEO

Philip Knowles, CFO

Stellar Diamonds plc

Stellar Diamonds plc

Tel: +44 (0) 20 7010 7686

Tel: +44 (0) 20 7010 7686

Jon Bellis

Beaufort Securities Limited (Joint Broker)

Tel: +44 (0) 20 7382 8300

Rory Scott

Mirabaud Securities (Financial Advisers)

Tel: +44 (0) 20 7878 3360

Emma Earl

Sandy Jamieson

Cairn Financial Advisers (Nominated Adviser)

Tel: +44 (0) 20 7148 7900

Lottie Brocklehurst

Hugo de Salis

St Brides Partners Ltd

Tel: +44 (0) 20 7236 1177

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAPESEDFKFEF
Date   Source Headline
12th Nov 20159:30 amRNSUnsecured Bridge Loan
9th Nov 20157:00 amRNSSierra Leone Declared Ebola-Free
2nd Nov 20157:00 amRNSCapital Reorganisation
24th Aug 20157:00 amRNSTongo Project PEA & Mining Licence Application
14th Aug 20157:00 amRNSIssue of Convertible Loan Note & Grant of Warrants
28th May 20157:00 amRNSStrong Revenues from Baoule Diamond Auction
7th May 20157:00 amRNSBaoule Diamond Sale
20th Apr 20157:00 amRNSFirst 5,000 Carats Achieved at Baoulé Kimberlite
1st Apr 20157:00 amRNSApplication for Mining Licence at Tongo Project
27th Mar 20157:00 amRNSInterim Results
24th Mar 20157:00 amRNSMaiden Diamond Sale and Revenues
27th Feb 20157:00 amRNSDiamond Tender
18th Feb 20157:00 amRNSAnnual Report and Update
26th Jan 20157:00 amRNSDirector's Dealing
22nd Jan 20157:00 amRNSIssue of Equity
8th Jan 20159:27 amRNSDirector/PDMR Shareholding
6th Jan 20157:00 amRNSProgress Update on Trial Mining at Baoulé
5th Jan 20154:08 pmRNSDirector/PDMR Shareholding
10th Dec 20144:03 pmRNSChange of Adviser
9th Dec 20142:30 pmRNSLoan Facility
8th Dec 20144:30 pmRNSResult of AGM
4th Dec 20147:00 amRNSFirst Diamond Export from Trial Mining at Baoulé
3rd Dec 20147:00 amRNSPositive Study for Acceleration of Cash Flows
28th Nov 20147:00 amRNSSignificant Increase in Resource & Diamond Grade
13th Nov 20147:00 amRNSFinal Results and Notice of AGM
31st Oct 20147:00 amRNSTotal Voting Rights
27th Oct 201410:58 amRNSHolding(s) in Company
21st Oct 20147:00 amRNSLarge Diamonds Recovered from Trial Mining, Baoule
16th Oct 20147:00 amRNSShare Subscription and Issue of Warrants
9th Oct 20147:00 amRNSFirst Diamonds from Trial Mining at Baoulé Project
30th Sep 20147:00 amRNSBoard Changes
11th Sep 20147:00 amRNSCommissioning of Diamond Processing Plant
19th Aug 20147:00 amRNSExcellent bulk Sample Grade from Tongo Project
11th Aug 20147:00 amRNSProgress Update on Baoulé Kimberlite in Guinea
28th Jul 201410:33 amRNSHolding(s) in Company
18th Jul 20147:00 amRNSDirector Dealing
15th Jul 20147:00 amRNSDiamond Bulk Sample Grades Exceed 150cpht at Tongo
3rd Jul 20149:07 amRNSHolding(s) in Company
3rd Jul 20147:00 amRNSDirector Dealing
20th Jun 20144:41 pmRNSDirector Dealing
20th Jun 20141:45 pmRNSUpdated Corporate Presentation
13th Jun 201412:48 pmRNSGrant of Share Options
3rd Jun 20147:00 amRNSFast-Tracking of Baoule Project to Trial Mining
30th May 20148:00 amRNSTotal Voting Rights
21st May 20143:51 pmRNSDelay in Admission
14th May 20147:00 amRNSDiamond Grades Increased at Tongo Project
8th May 20147:00 amRNSGBP1.85M Placing
20th Mar 20147:00 amRNSInterim Results
19th Mar 20147:00 amRNSInterim Results Release Date and Investor Evening
18th Mar 20147:00 amRNSContinued High Grade and Diamond Quality at Tongo

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.