DECEMBER 2014 QUARTERLY REPORT

 

The Board of Wildhorse Energy Limited ('the Company' or 'Wildhorse') presents its December 2014 quarterly report, where the focus continued on restructuring the Company and operations with a view to substantially reducing costs and raising funds to place the Company in an improved position to progress its remaining project and to pursue new opportunities.

Highlights during, and subsequent to, the quarter were as follows:

· The Company substantially reduced costs for its operational and administrative functions and as announced on 28 October 2014, is now accessing options to divest its remaining Hungarian uranium project;

· The Company is now focused is on its remaining Golden Eagle Uranium Project in the USA;

· The Company completed a 1 for 30 consolidation of capital ('Consolidation') as approved by shareholders at the Annual General Meeting on Tuesday 25 November 2014, reducing the number of shares on issue to 13.6 million. Following the issue of shares as announced on 9 December 2014, the number of shares on issue is now 15,133,766;

· Following the completion of the Consolidation, the Company released a prospectus for a 5 for 1 pro rata renounceable entitlements issue to raise up to approximately $3.8 million before costs. The closing date for the offer is Friday 6 February 2015 (Tuesday 3 February 2015 for AIM holders);

· As announced on 28 January 2015, shareholders have again approved the participation of the Board in shortfall shares from the entitlements offer; and

· The Company continues in its efforts to identify and acquire suitable new business opportunities in the resource and other sectors both domestically and overseas.

The Board is confident that upon completion of the recapitalisation process, the new low cost structure will place the Company in a strong position to progress its current project and to pursue new opportunities in the resource and other sectors.

  

OPERATIONS

 

Golden Eagle Uranium and Vanadium Project

The Golden Eagle Uranium and Vanadium Project holds nine U.S. Department of Energy (DOE) Uranium/Vanadium Mining Leases, covering 22.7 km2 located in the Uravan Mineral Belt, Colorado USA.

Technical reports for a number of the lease have been drafted based on historic data, however, exploration drilling and core analysis need to be completed in order to finalise these reports. The leases will expire eight years after the courts complete their review of the Record of Decision (ROD) published this past spring in the Federal Register and the DOE allows the lease holders to resume activates on their leases.

It should be noted that the lease can be held beyond their expiration through continued renewals and the continuation of lease maintenance, including exploration work and future production. Historically these DOE leases have been renewed for 10 year periods after the expiration date; existing leases issued to past Lessee's have been renewed dating back to 1974.

Wildhorse also possesses an option on Gold Eagle Mining Inc (GEMI) leases; GEMI has three DOE properties of which two have active operating permits.

Upon completion of the recapitalisation process, the Company will undertake a staged and measured approach to advance this project, and will initially focus on a technical review of existing exploration information to determine the most appropriate manner to undertake further exploration activities.

Mecsek Hills Uranium Project

As part of the Company's ongoing restructuring efforts and decision to cease all activities in Europe, the Board resolved to divest of its holdings in the Mecsek Hills Uranium Project. As a result, the Company is continuing with its efforts to divest of its interest in this Project to extract the best value for shareholders. It is also noted that with effect from 31 December 2014, the Hungarian government has deemed the Project joint venture entity ("Magyar Uran Zrt") a company of national importance, which may impact on the sale process.

Mecsek Hills UCG Project

As previously disclosed, given that no recent development activities had been undertaken on this project and a number of unsuccessful attempts had been made to divest all or part of the Company's interest in this project, the Board resolved to formally cease all activities during the quarter, which resulted in the associated mineral interests terminating.

 

CORPORATE

Share Consolidation

As announced on 8 December 2014, the consolidation of the Company's capital, on the basis of 1 share for every 30 existing shares, as approved by shareholders at the Annual General Meeting of shareholders on 25 November 2014, has now been completed. The numbers of Options on issue have also been consolidated on a 1 for 30 basis, with the exercise price of the Options increasing in inverse proportion to the consolidation ratio. Following the issue of shares as announced on 9 December 2014, there are now 15,133,766 shares on issue.

General Meeting of Shareholders

As announced on 28 January 2015, shareholders again approved the participation of the Board in the shortfall issue of shares from the entitlement offer.

 

 

Entitlements Issue

The Company lodged a prospectus for the Offer (Prospectus) with ASIC, ASX and AIM on 15 December 2014. The Offer was made to all shareholders of the Company (Shareholders) named on its register of members at 4.00pm (WST) on 22 December 2014, with a registered address is in Australia, New Zealand or United Kingdom (Eligible Shareholders).

The Offer made is a renounceable entitlement issue of 5 New Shares for every 1 Share held by Shareholders registered at the Record Date at an issue price of $0.05 per Share. Assuming all entitlements are accepted, following completion of the Offer, the Company will issue approximately 75,668,830 fully paid ordinary shares (New Share) to raise approximately $3,783,441.

The Entitlement Issue Prospectus and Entitlement and Acceptance Form in respect to the Company's five for one renounceable entitlements issue was dispatched to eligible shareholders on 24 December 2014.

Summary of Exploration and Mining Tenements

 

As at 31 December 2014, the Company holds the following interests in the listed tenements:

 

Location

Name

Resolution Number

Percentage Interest

31 December 2014

Hungary

Pécs

PBK/6947/3/2006

100%*

USA - Colorado

C-SR-10

C-SR-10

80%

USA - Colorado

C-JD-5A

C-JD-5A

80%

USA - Colorado

C-SR-11A

C-SR-11A

80%

USA - Colorado

C-SR-15A

C-SR-15A

80%

USA - Colorado

C-SR-16

C-SR-16

80%

USA - Colorado

C-WM-17

C-WM-17

80%

USA - Colorado

C-LP-22A

C-LP-22A

80%

USA - Colorado

C-LP-23

C-LP-23

80%

* Refer to the Company's Announcement on 28 October 2014 regarding an update on the Company's restructure.

 

 

For further information please visit www.wildhorse.com.au or contact:

Sam Cordin

Wildhorse Energy Limited

Tel: +61 8 9322 6322

Colin Aaronson/Jen Clarke/Jamie Barklem

Grant Thornton UK LLP

Tel: +44 (0)207 383 5100

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPKKDNFBKKODN
Date   Source Headline
25th Mar 20217:00 amRNSHolding(s) in Company
22nd Mar 20217:00 amRNSLake Way Process Plant commissioning commences
16th Mar 20217:45 amRNSInterim Results
10th Mar 20217:00 amRNSCompany Presentation - Project Update
4th Mar 20217:00 amRNSSenior debt syndication to Sequoia and CBA
12th Feb 20218:42 amRNSDirector/PDMR Shareholding
11th Feb 20217:06 amRNSCompletion of Placement and Issue of Shares
3rd Feb 20217:00 amRNSIssue of Share Purchase Plan Shares
29th Jan 20217:00 amRNSDecember 2020 Quarterly Report
28th Jan 20217:00 amRNSSO4 Successfully Completes Share Purchase Plan
22nd Jan 20218:58 amRNSResult Of General Meeting
18th Jan 20217:00 amRNSLake Way Project Update. Interim CFO appointed
22nd Dec 20207:36 amRNSFunds from First Drawdown Received
21st Dec 20207:00 amRNSNotice of General Meeting
18th Dec 20209:15 amRNSPlacement, Share Purchase Plan, Securities Issue
11th Dec 20207:00 amRNSFundraising & Lifting of ASX Voluntary Suspension
10th Dec 20207:00 amRNSFunding Update & Short Extension to ASX Suspension
3rd Dec 20207:00 amRNSASX Voluntary Suspension and Funding Update
27th Nov 20203:39 pmRNSFunding Update
27th Nov 20207:00 amRNSASX Trading Halt
20th Nov 20207:00 amRNSResult of AGM
21st Oct 20207:15 amRNSNotice of AGM
19th Oct 20207:00 amRNSOperational and Potash Experience Added to Board
16th Oct 20207:00 amRNSSeptember 2020 Quarterly Report & Issue of Shares
14th Oct 20207:48 amRNSNew Corporate Presentation
12th Oct 20202:05 pmRNSSecond Price Monitoring Extn
12th Oct 20202:00 pmRNSPrice Monitoring Extension
29th Sep 202011:44 amRNSDirector and Other Shareholdings
28th Sep 20207:00 amRNSFinal Results
25th Sep 202011:04 amRNSDate of AGM and Delay to Admission of Shares
23rd Sep 202012:29 pmRNSAGM Statement. Issue of Ordinary Shares
14th Sep 20208:08 amRNSLake Way Project Reaches 60% Completion
3rd Sep 202010:21 amRNSHolding(s) in Company
1st Sep 20207:38 amRNSIssue of Shares - Director/PDMR Shareholding
28th Aug 20207:00 amRNSCompletion Of Retail Entitlement Offer
27th Aug 20207:00 amRNSHolding(s) in Company
24th Aug 20208:08 amRNSNotice of GM
20th Aug 202010:26 amRNSHolding(s) in Company
17th Aug 20207:00 amRNSIssue of Shares and Directors' Subscription
14th Aug 20207:00 amRNSDespatch of Retail Offer Booklet. Loan Conversion
11th Aug 20207:00 amRNSSuccessful Completion of Institutional Offer
6th Aug 20207:00 amRNSEntitlement Offer Amended Timetable for DI Holders
5th Aug 20207:00 amRNSDebt Facility, Equity Raising, Entitlement Offer
31st Jul 20207:00 amRNSJune 2020 Quarterly Report
13th Jul 20207:00 amRNSGreen Label Certification
9th Jul 20207:00 amRNSProcurement Update
3rd Jul 20209:30 amRNSAppendix 3Y Change of Director's Interest Notices
2nd Jul 20207:39 amRNSConvertible Note Placement
23rd Jun 20203:33 pmRNSHolding(s) in Company
17th Jun 20209:03 amRNSResult of Meeting. Completion of Placement.

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.