Siekierki Update

28 Apr 2014 07:00

RNS Number : 6035F
San Leon Energy PLC
28 April 2014
 



28 April 2014

San Leon Energy Plc

("San Leon" or the "Company")

 

Siekierki Update

San Leon Energy is pleased to announce it has agreed key commercial terms with Baker Hughes Poland Sp. Z.o.o. ("Baker") (together "the Companies") on the Siekierki gas field development on Polish Blocks 206, 207 and 208. The Companies are now moving forward to finalising transaction documents.

In February 2014, Baker signed a Letter of Intent ("LOI") to bring the Siekierki gas field into production. Commercial discussions and operational planning have progressed significantly since then in an effort to ensure workovers on the four Trzek wells are carried out in the summer and production is established as quickly as possible.

The work will be divided into three phases, with Phase Two dependent on the results of the first phase. Phase 1 encompasses the workover and testing of the Trzek-2ZH and Trzek-3H wells, permitting and commercialisation planning. Phase 2 includes the workover and testing of the Trzek-1 well and construction of a water disposal well, plus well permitting and commercialisation planning. The Krzesinki-1 well will be subject to further evaluation and will be included in Phase 2 at Baker Hughes' sole discretion. Phase 3 includes the design and installation of facilities and transport infrastructure necessary to begin sale of hydrocarbons from Phase 1 and Phase 2 wells.

In return for its funding of the above phases in the form of cash, in-kind oilfield services, or a combination of both, Baker will receive an undisclosed return on this risked investment from 75% of profits generated from production until Baker's investment has been fully recovered. Baker will also receive a net profit interest ("NPI") of 10% in any wells that they fund during Phase 1 and Phase 2, with the NPI to begin as soon as full recovery of Baker's costs has occurred. The duration of the NPI is expected to constitute the large majority of the wells' production period. The Companies will explore cost-effective solutions for funding Phase 3, which may include Baker funding the facilities.

Baker services will be provided at their standard prices and based upon a Master Service Agreement to be agreed between the Companies.

Baker will also receive a right of first refusal to provide services at competitive market rates for the full development of the Siekierki Field. The Companies may also agree to Baker providing the funding for a full field development (post Phase 3), which if invoked, will be on the same terms as provided for in Phase 1 and Phase 2.

Permissions are already in place for much of the Phase 3 development and associated infrastructure, meaning a fast-track route to production is planned. The Company also has permission for water disposal wells at Siekierki.

Oisin Fanning, San Leon Executive Chairman, commented:

 

"The goodwill and co-operation on this venture has been remarkable and we would like to thank all the people at Baker for their commitment and dedication to this project. We have agreed key commercial terms and are now finalising transaction documents. We expect a joint press release will be issued in the near future when final documents are signed. In the meantime, technical and operational teams from both companies are putting plans in place for Phase 1 testing and completion."

 

For further information contact:

 

San Leon Energy plc 

Oisin Fanning, Executive Chairman

 

+353 1291 6292

finnCap Ltd 

Corporate FinanceMatt Goode

Christopher RaggettCorporate BrokingElizabeth JohnsonJoanna Weaving

 

+44 (0) 20 7220 0500

Fox-Davies Capital Limited

Daniel Fox-DaviesOliver StansfieldJonathan Evans 

 

+44 (0) 20 3463 5000

Macquarie Capital (Europe) LimitedSteve BaldwinNicholas Harland

 

+44 (0) 20 3037 2000

Westhouse Securities LtdNominated AdviserRichard JohnsonAntonio Bossi

 

+44 (0) 20 7601 6100

Vigo CommunicationsFinancial Public RelationsPatrick d'AnconaChris McMahon

 

+44 (0) 20 7016 9573

Instinctif PartnersInvestor Relations AdviserDavid SimonsonCatherine Wickman

 

+44 (0) 20 7457 2020

Plunkett Public RelationsSharon Plunkett

+353 (0) 1 280 7873

 

Qualified person

Joel Price, who has reviewed this update, has 20 years' experience in the oil & gas industry and is a member of the Society of Petroleum Engineers. He holds a BA in Natural Sciences from Cambridge University, an MEng from Heriot-Watt University, and an MBA from Durham University. Joel is Chief Operating Officer for San Leon Energy and is based in San Leon's London office.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBDLLLZZFEBBD
Date   Source Headline
8th Jan 20154:35 pmRNSPrice Monitoring Extension
2nd Jan 20154:40 pmRNSSecond Price Monitoring Extn
2nd Jan 20154:35 pmRNSPrice Monitoring Extension
29th Dec 20144:35 pmRNSPrice Monitoring Extension
16th Dec 20144:35 pmRNSPrice Monitoring Extension
2nd Dec 20144:40 pmRNSSecond Price Monitoring Extn
2nd Dec 20144:35 pmRNSPrice Monitoring Extension
24th Nov 20147:00 amRNSSpudding of Rawicz-12 Well
18th Nov 20144:35 pmRNSPrice Monitoring Extension
18th Nov 20147:00 amRNSSpudding of Gieraltowice Well
13th Nov 20147:05 amRNSMorocco Update
5th Nov 20147:00 amRNSKety Well Update
20th Oct 20147:00 amRNSMorocco Well Testing
17th Oct 20144:40 pmRNSSecond Price Monitoring Extn
17th Oct 20144:35 pmRNSPrice Monitoring Extension
3rd Oct 20144:35 pmRNSPrice Monitoring Extension
2nd Oct 20144:35 pmRNSPrice Monitoring Extension
30th Sep 20147:00 amRNSInterim Results
26th Sep 201411:31 amRNSResult of AGM
26th Sep 20147:00 amRNSSpudding of Kety Well
17th Sep 20143:59 pmRNSPoland Update
8th Sep 20147:00 amRNSMorocco Update
21st Aug 201412:35 pmRNSSan Leon Energy Update
7th Aug 20148:19 amRNSBarryroe Update
31st Jul 20147:26 amRNSMorocco Update
28th Jul 20144:40 pmRNSSecond Price Monitoring Extn
28th Jul 20144:35 pmRNSPrice Monitoring Extension
21st Jul 20144:40 pmRNSSecond Price Monitoring Extn
21st Jul 20144:35 pmRNSPrice Monitoring Extension
11th Jul 20144:40 pmRNSSecond Price Monitoring Extn
11th Jul 20144:35 pmRNSPrice Monitoring Extension
1st Jul 20147:00 amRNSJoint Venture Focused on Polish Production
30th Jun 20147:00 amRNSFinal Results
16th Jun 20144:40 pmRNSSecond Price Monitoring Extn
16th Jun 20144:35 pmRNSPrice Monitoring Extension
30th May 20143:56 pmRNSAwarded CEE Exploration Company of the Year
27th May 201410:00 amRNSUpdate on Poland
9th May 20149:47 amRNSUpdate on Poland
8th May 201412:31 pmRNSDirector Dealing
28th Apr 20147:00 amRNSSiekierki Update
14th Apr 20147:00 amRNSAlpay Energi and Corporate Update
27th Mar 20147:00 amRNSTerm Sheet Agreement with TransAtlantic Petroleum
24th Mar 20148:43 amRNSHolding(s) in Company
24th Mar 20147:00 amRNSLOI for Cybinka and Torzym Concessions Amended
19th Mar 20147:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
10th Mar 20147:00 amRNSNew well to be drilled based on success of Rogity1
12th Feb 20147:00 amRNSSiekierki Path to Production
10th Feb 20147:00 amRNSAppointment of Joint Broker
31st Jan 201411:54 amRNSTotal Voting Rights
28th Jan 20147:00 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.