Operations Update

18 Dec 2014 07:00

RNS Number : 1400A
Petroneft Resources PLC
18 December 2014
 



 

PetroNeft Resources plc

("PetroNeft" or the "Group" or the "Company")

 

Operations Update

 

PetroNeft (AIM: PTR) an oil & gas exploration and production company operating in the Tomsk Oblast, Russian Federation, is pleased to provide an update on operations.

 

Licence 61

· Arbuzovskoye 106 well now in production at a stabilised average rate of 170 bopd

· Arbuzovskoye 103 well drilling ahead

· Drilling of Tungolskoye 5 horizontal well continuing

· Total production now at 1,850 bopd

· Seismic crew mobilised to the Sibkrayevskoye field

 

Licence 67

· Processing and interpretation of 3D seismic survey completed

· Reserves calculation for Russian State Approval being finalised

 

Corporate

· Weakening Russian Rouble acting as a natural hedge to falling oil prices

 

Licence 61

Arbuzovskoye

Following some delays the Arbuzovskoye 106 well has successfully encountered oil in the Upper Jurassic (J-1) formation at a depth of 2,465 metres, TVD. The well been brought into production at a stabilised rate of 170 bopd with no visible water cut. This rate exceeds pre-drill estimates of between 100-150 bopd.

 

Arbuzovskoye well 103, the next well in the drilling programme, is currently drilling ahead. This well is the southernmost well drilled at Arbuzovskoye to date and will help determine if further wells will be drilled in the southern lobe of Arbuzovskoye.

 

Tungolskoye

The horizontal segment of the Tungolskoye No. 5 well is currently being drilled, however drilling progress to this point has been slower than originally estimated. Production results on the horizontal segment are currently expected in January 2015. The pilot hole previously confirmed the structure, the net pay (8.2 m) and commercial oil flow (100 bopd non-stimulated) at the crest of the structure. The well is being drilled under a turn-key contract so additional time will not result in additional cost. The main regulatory approvals required for the development of the Tungolskoye field have been obtained and the tendering process for the various services and materials required for this work programme is well underway.

 

Sibkrayevskoye

The rig for the Sibkrayevskoye No. 373 well is currently being erected. It is expected that drilling will commence in February 2015.

 

The seismic crew has been mobilised to the field and work is well underway on the programme to acquire 1,000 km of high quality 2D seismic data across the Sibkrayevskoye oil field and other fields and prospects in the northern portion of Licence 61. The main acquisition of data will occur in the first quarter of 2015 with final interpreted results being available in Q3 2015. This will help formulate our work programme beyond the current drilling campaign.

 

Total production from Licence 61 is currently about 1,850 bopd.

 

Licence 67

The processing and interpretation of the 156.84 sq. km. of 3D seismic data acquired over the Cheremshanskoye and Ledovoye oil fields in Q1 2014 has been completed.

 

The reserves calculation for the two fields based on the 3D seismic data is being prepared for submittal and approval at the Russian State Reserves Committee in Moscow.

 

Oil price and Russian Rouble

While oil prices have fallen internationally in recent months, so too has the Russian Rouble as compared to the US Dollar. The vast majority of operating costs and capital expenditure are denominated in Russian Roubles and this acts as a natural hedge to falling oil prices. It should also enable PetroNeft to undertake more capital expenditures pursuant to the US$45 million farm-in carry being financed by Oil India Limited.

 

Dennis Francis, Chief Executive Officer of PetroNeft Resources plc, commented:

"I'm very pleased with the rate achieved from the first new well drilled at Arbuzovskoye since February 2013 and look forward to updating shareholders with the results of the additional wells at Arbuzovskoye.

 

The pilot hole at Tungolskoye has achieved its objectives in confirming the structure, net pay and oil flow and we look forward to the production test result from our first horizontal well in the New Year"

 

For further information, contact:

Dennis Francis, CEO, PetroNeft Resources plc

+1 713 988 2500

Paul Dowling, CFO, PetroNeft Resources plc

+353 1 647 0280

John Frain/Brian Garrahy, Davy (NOMAD and Joint Broker)

+353 1 679 6363

Henry Fitzgerald-O'Connor, Canaccord Genuity Limited (Joint Broker)

+44 207 523 8000

Martin Jackson/Shabnam Bashir, Citigate Dewe Rogerson

+44 207 638 9571

Joe Murray/Joe Heron, Murray Consultants

+353 1 498 0300

 

The information contained in this announcement has been reviewed and verified by Mr. Dennis Francis, Director and Chief Executive Officer of PetroNeft, for the purposes of the Guidance Note for Mining and Oil & Gas Companies issued by the London Stock Exchange in June 2009. Mr. Francis holds a B.S. Degree in Geophysical Engineering and a M.S. Degree in Geology from the Colorado School of Mines. He has also graduated from the Harvard University Program for Management Development. He is a member of the American Association of Petroleum Geologists and the Society of Exploration Geophysicists. He has over 40 years' experience in oil and gas exploration and development.

 

Glossary

bopd

Barrels of oil per day

TVD

True vertical depth

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGLBDDSXBBGSI
Date   Source Headline
21st Jul 20155:51 pmRNSHolding(s) in Company
30th Jun 20153:30 pmRNSAnnual Report & Annual General Meeting
30th Jun 201512:17 pmRNSHolding(s) in Company
23rd Jun 20157:00 amRNS2014 Final Results
22nd May 20157:00 amRNSOperations Update
20th Mar 20157:00 amRNSOperations Update
5th Mar 201511:55 amRNSHolding(s) in Company
4th Mar 20154:40 pmRNSSecond Price Monitoring Extn
4th Mar 20154:35 pmRNSPrice Monitoring Extension
27th Feb 20155:20 pmRNSHolding(s) in Company
3rd Feb 20157:00 amRNSOperations Update
18th Dec 20147:00 amRNSOperations Update
14th Oct 20147:00 amRNSTungolskoye No. 5 update
26th Sep 20147:00 amRNSHalf Yearly Report
8th Sep 20144:47 pmRNSHolding(s) in Company
29th Aug 20145:06 pmRNSAnnual General Meeting
19th Aug 20147:00 amRNSDrilling Operations Re-commencing
22nd Jul 20145:06 pmRNSHolding(s) in Company
4th Jul 20147:00 amRNSCompletion of Farmout
30th Jun 20144:45 pmRNSAnnual Report & Notice of AGM
30th Jun 20143:45 pmRNSFarmout Update
27th Jun 20148:35 amRNSFinal Results
28th May 201411:25 amRNSHolding(s) in Company
9th May 20143:54 pmRNSShareholder Meetings Update
24th Apr 201410:30 amRNSDocument Availability
17th Apr 20144:40 pmRNSSecond Price Monitoring Extn
17th Apr 20144:35 pmRNSPrice Monitoring Extension
17th Apr 20144:05 pmRNSLicence 61 Farmout Agreement
15th Apr 20147:00 amRNSFarmout Update
4th Apr 20143:16 pmRNSHolding(s) in Company
20th Mar 20147:00 amRNSEnterprise Securities Market Notice
18th Mar 20147:00 amRNSEGM Proposal
17th Mar 20147:00 amRNSFunding & Operations Update
23rd Jan 201412:01 pmRNSHolding(s) in Company
17th Jan 20146:24 pmRNSHolding(s) in Company
16th Jan 20147:00 amRNSOperations Update
5th Dec 20139:24 amRNSHolding(s) in Company
5th Dec 20139:22 amRNSHolding(s) in Company
3rd Dec 20137:00 amRNSOperations Update
28th Nov 201311:05 amRNSHolding(s) in Company
5th Nov 201312:16 pmRNSHolding(s) in Company
4th Oct 20134:13 pmRNSHolding(s) in Company
30th Sep 20137:00 amRNSHalf Yearly Report
20th Sep 20132:59 pmRNSHolding(s) in Company
11th Sep 20133:28 pmRNSResult of AGM
11th Sep 20137:00 amRNSOperations Update
28th Jun 20137:00 amRNSFinal Results
21st Mar 20137:00 amRNSOperations Update
18th Feb 201310:35 amRNSHolding(s) in Company
13th Feb 20132:28 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.