Operations Update

3 Feb 2015 07:00

RNS Number : 8414D
Petroneft Resources PLC
03 February 2015
 

3 February 2015

 

PetroNeft Resources plc

("PetroNeft" or the "Group" or the "Company")

 

Operations Update

 

PetroNeft (AIM: PTR) an oil & gas exploration and production company operating in the Tomsk Oblast, Russian Federation, is pleased to provide an update on operations at Licence 61.

 

Highlights

Tungolskoye

· Tungolskoye No. 5 well tested at over 600 bopd and is now in production

· Development of Tungolskoye to proceed immediately

o 11 well Tungolskoye campaign to commence in Q2 2015

o Tenders awarded for drilling and for the development of additional infrastructure at Tungolskoye

 

Arbuzovskoye & Sibkrayevskoye

· Arbuzovskoye 103 well now in production at a stabilised average rate of 125 bopd and confirms southern lobe of field

· Arbuzovskoye 104 well drilled with 5.4 metres of net pay, expected on production shortly

· Arbuzovskoye 107 well has been spudded

· Seismic acquisition underway at Licence 61.

· Drilling to commence later this month at Sibkrayevskoye 373

 

Production

· Total production now about 2,450 bopd (including Tungolskoye No. 5)

 

 

Tungolskoye

The horizontal segment of the Tungolskoye No. 5 well has been drilled and completed in the J1-1 and J1-2 Upper Jurassic intervals. The total horizontal segment was just over 350 metres of which over 80% was located in the productive J1-1 and J1-2 reservoirs at depths between -2,502 m and -2,517 m TVD. The well is still cleaning up and current production is 604 bopd using an Electric Submersible Pump (ESP). The oil is currently being trucked 25 km to the Lineynoye central processing facility.

 

Development of the Tungolskoye oil field which is estimated to contain 20 mmbbls in 2P reserves will now proceed immediately. Contracts are currently being finalized for the 2015/16 Tungolskoye development drilling programme. The programme is expected to comprise five horizontal and up to six vertical wells. Drilling is expected to commence in April 2015 and will be completed in Q1 2016. Further details will be announced once the drilling contract is executed.

 

Tenders have also been awarded for the construction of a pipeline and power line to connect the Tungolskoye oil field back to the Lineynoye central processing facility with contracts currently being finalised. All of the necessary drilling and other supplies for this programme have been ordered and are being delivered to the field. Capital expenditure on this project is included in the License 61 development plan agreed between the License Partners and is fully funded.

 

Arbuzovskoye

The Arbuzovskoye 103 well has been completed and brought into production at an initial rate of 125 bopd. The well was drilled as the maximum reach step out to the south to better define the oil water contact and productivity. The well encountered 5.0 m of oil saturated pay in the J1-1 Upper Jurassic interval at a depth of -2,460 m TVD and confirms oil in the southern lobe of the Arbuzovskoye field. Current plans are to develop the southern portion of the field with a combination of horizontal and vertical wells commencing in 2016.

 

The Arbuzovskoye 104 well has now been drilled in the northern part of the field adjacent to the A-106 well. The logs indicate that the well has 5.4 m of net oil pay in the J1-1 Upper Jurassic interval at a depth of -2,467 m TVD and looks similar to the adjacent A-106 well which is currently producing about 175 bopd. We are currently completing the A-104 well and anticipate bringing it on production within a week.

 

The Arbuzovskoye 107 was spudded on 1 February 2015 and is expected to take approximately four weeks to drill. It is located north-west of the A-103 well.

 

Total production from Licence 61 is currently about 2,450 bopd.

 

Sibkrayevskoye

The drilling rig for the Sibkrayevskoye No. 373 well is currently being erected. It is expected that drilling will commence later this month.

 

Work is well underway on the programme to acquire 1,000 km of high quality 2D seismic data across the Sibkrayevskoye oil field and other fields and prospects in the northern portion of Licence 61. The main acquisition of data will continue until April with final interpreted results being available in Q3 2015. This will help formulate our work programme beyond the current drilling campaign at Tungolskoye and Arbuzovskoye in order to develop the Sibkrayevskoye oil field which is estimated to contain 53 mmbbls in 2P reserves.

 

Dennis Francis, Chief Executive Officer of PetroNeft Resources plc, commented:

"We are delighted with the result of the T-5 well, our first horizontal well, which has exceeded our expectations and which bodes extremely well for the development of Tungolskoye where we plan a number of longer horizontal segments in an 11 well campaign.

 

We have also achieved two excellent results at Arbuzovskoye particularly from the A-103 well which has confirmed the southern lobe of the Arbuzovskoye field as well as adding to production, which has grown to 2,450 bopd."

 

 

For further information, contact:

Dennis Francis, CEO, PetroNeft Resources plc

+1 713 988 2500

Paul Dowling, CFO, PetroNeft Resources plc

+353 1 647 0280

John Frain/Brian Garrahy, Davy (NOMAD and Joint Broker)

+353 1 679 6363

Henry Fitzgerald-O'Connor, Canaccord Genuity Limited (Joint Broker)

+44 207 523 8000

Martin Jackson/Shabnam Bashir, Citigate Dewe Rogerson

+44 207 638 9571

Joe Heron / Douglas Keatinge, Murray Consultants

+353 1 498 0300

 

The information contained in this announcement has been reviewed and verified by Mr. Dennis Francis, Director and Chief Executive Officer of PetroNeft, for the purposes of the Guidance Note for Mining and Oil & Gas Companies issued by the London Stock Exchange in June 2009. Mr. Francis holds a B.S. Degree in Geophysical Engineering and a M.S. Degree in Geology from the Colorado School of Mines. He has also graduated from the Harvard University Program for Management Development. He is a member of the American Association of Petroleum Geologists and the Society of Exploration Geophysicists. He has over 40 years' experience in oil and gas exploration and development.

 

Glossary

2P reserves

Proved and probable reserves as defined by the standards of the Society of Petroleum Engineers

bopd

Barrels of oil per day

m

Metres

mmbbls

Million barrels

TVD

True vertical depth

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLDDGDDGSGBGUD
Date   Source Headline
10th Nov 20177:00 amRNSProduction Update
24th Oct 20177:00 amRNSOperations Update
10th Oct 201710:30 amRNSHolding(s) in Company
29th Sep 20177:00 amRNSHalf-year Report
15th Sep 20172:16 pmRNSResult of AGM
5th Sep 20177:00 amRNSOperations Update
28th Jul 20177:00 amRNSQuarterly Production Update
20th Jul 20177:00 amRNSOperations Update
30th Jun 20177:00 amRNSFinal Results
28th Apr 20177:00 amRNSQuarterly Production Update
31st Mar 20177:00 amRNS2017 Work Programme
14th Feb 20173:51 pmRNSHolding(s) in Company
31st Jan 20177:00 amRNSQuarterly Production Update
12th Oct 20167:00 amRNSQuarterly Production Update
28th Sep 20167:00 amRNS2016 Interim Results
16th Sep 20162:07 pmRNSResult of AGM
31st Aug 20167:00 amRNSDrilling and Operations Update
21st Jul 20167:00 amRNSOperations Update
5th Jul 20167:00 amRNSOperations Update
30th Jun 201612:00 pmRNSAnnual Report & Annual General Meeting
23rd Jun 20167:00 amRNS2015 Final Results
2nd Jun 20167:00 amRNSOperations Update
25th May 201612:19 pmRNSWithdrawal of General Invest EGM Requisition
26th Apr 20169:05 amRNSDirectors Declaration
25th Apr 20167:54 amRNSAgreement with Natlata
18th Apr 20162:00 pmRNSAdjournment of EGM
18th Apr 20168:26 amRNSRestriction Notice Update
6th Apr 20167:00 amRNSRestriction Notice Update
5th Apr 20162:37 pmRNSISS recommends vote AGAINST Natlata Resolutions
5th Apr 20168:05 amRNSRestriction Notices
31st Mar 201611:17 amRNSBoard Changes are vital for future of PetroNeft
23rd Mar 20167:00 amRNSExecution of Oil India Loan
21st Mar 201611:46 amRNSPetroneft offers no solutions except Poison Pill
21st Mar 20167:01 amRNS2016/2017 Work programme
21st Mar 20167:00 amRNSEGM Requisition and Publication of Circular
10th Mar 20164:55 pmRNSUpdate on Natlata EGM Requisition
2nd Mar 20161:55 pmRNSHolding(s) in Company
19th Feb 20165:03 pmRNSHolding(s) in Company
18th Feb 20163:16 pmRNSEGM Proposal
26th Jan 20162:30 pmRNSHolding(s) in Company
7th Jan 20167:00 amRNSDirector Shareholdings
31st Dec 20159:12 amRNSDirector Sharedealings
14th Dec 20157:00 amRNSOperational Update
29th Sep 20157:00 amRNSHalf Yearly Report
18th Sep 20153:10 pmRNSAnnual General Meeting
18th Sep 20151:49 pmRNSRetirement of Director
11th Sep 20154:33 pmRNSHolding(s) in Company
10th Sep 20157:00 amRNSOperations Update
12th Aug 20157:00 amRNSOperational Update
22nd Jul 20157:00 amRNSOperations Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.